Trans-Haryana Expressway


The Trans-Haryana Expressway or the Ambala–Narnaul Expressway is a 227-km long, 6-lane wide greenfield access-controlled expressway, connecting the cities of Ambala and Narnaul in the state of Haryana. The expressway connects Gangheri village in Kurukshetra district with Surana village on Narnaul Bypass in Mahendragarh district. It passes via Kaul, Pundri, Pillu khera, Julana, Kalanaur, Charkhi Dadri and Kanina. It will reduce the distance from Chandigarh to Delhi, Narnaul, and Jaipur, thus decongesting NH-44 and NH-48.
The alignment intersects with 15 national highways, including NH-9, and several State Highways, including SH6, SH9, SH8, SH11, SH12, SH14, SH10, SH16A, SH20, SH24 and SH26. The area around the expressway is being developed as an industrial corridor, named as the Ambala–Kotputli Economic Corridor. Construction was started in July 2020, and was completed and opened for traffic on 1 August 2022. The industrial corridor consists of four road projects, which have:
  • 39-km section of NH-152 from Ambala to Ismailabad
  • 227-km long Ambala-Narnaul Expressway
  • 14-km section of Narnaul Bypass
  • 30-km section of NH-148B from Narnaul Bypass to Paniyala Mor.
  • 22.85 km extension of Jalbehra to Shahbad Expressway

Details

Costing 5,108 crore, it will have 70 metre right of way, 122 bridges and underpasses and 1,36,000 trees would be planted on either sides is being developed by the National Highways Authority of India under Bharatmala project. Grenfield alignment will reduce the Ismailabad to Narnaul distance by 35 km from the existing 265 km route to 230 km new route. Construction will create 1,500 full-time jobs for 3 years and 120 ongoing jobs will be created for the Toll Plaza staff. To reduce the environmental impact the fly ash will be used from the Tau Devilal Thermal Power Plant at Panipat, Indira Gandhi Super Thermal Power Project at Jhajjar and Rajiv Gandhi Thermal Power Station at Hisar.

Route alignment

It passes through the areas lying in the following 8 districts of Haryana:
1. Kurukshetra district
  • Gangheri, NH152D will interchange with the exiting NH152 at Gangheri which is 8 km south of Ismailabad and 8 km north of Pehowa
  • Pehowa, interchange with SH6 east of Pehowa
2. Kaithal district
  • Kaul, interchange with SH9 at Dhand just north of Kaul
  • Pundri, interchange with SH8 3 km east of Pundri
3. Jind district
  • Jind city,
  • * northeast: interchange with SH12 25 km northeast of Jind near Badhana-Popran
  • * northeast: interchange with Delhi–Amritsar–Katra Expressway west of village Ratoli
  • * east: interchange with SH14 15 km east of Jind at Jamni near Pilu Khera
  • * southeast: interchange with SH11 15 km east of Jind
  • * Kila zafargarh, interchange with NH352 4 km south of Julana
4. Rohtak district
5. Bhiwani district
6. Charkhi Dadri district
7. Mahendragarh district

Inter-connectivity

Narnaul–Alwar Expressway

Paniyala–Barodameo Expressway, an 86.5 km long 6-lane, access-controlled greenfield expressway from Paniyala. There are plans to extend the expressway from Barodameo through the following:
Bardameo to Vrindavan, Yamuna Expressway and BareillyTanakpur–Gunji–Kalapani territory.
  • To Nepal:
Nagar to BharatpurAchhneraAgra, Yamuna Expressway and FarrukhabadSitapurNepalgunj.
Bardameo–Jhansi Expressway from Bardameo–Kherli–Suroth–Khurdiya Nayagaon–Golari/Saipur to Kailaras–Bhitarwar–Bhagour–Sijwaha–Jhansi.

Hisar-Rewari Expressway

Hisar-Rewari Expressway will intersect Trans-Haryana Expressway north of Mahendragarh.

Regional Circular Expressway-2

Regional Circular Expressway-3 will intersect with Trans-Haryana Expressway in two places, between Mahendragarh-Kanina and between JindUchana.

History

Construction

The NHAI has divided the construction work of 227 km-long Ambala–Narnaul Expressway into 8 packages. Package-1 is a joint venture of JiangXi Construction Engineering, Ceigall India and Shiv Build India; Package-4 is a JV of JiangXi Construction Engineering and Shiv Build India and Package-7 is a JV of Gawar Construction and Shivalaya Construction Company. The list of contractors is as follows:
Sr. NoPackageLength in kmContractor
1.Ismailabad –Dhand 23JiangXi – Ceigall – Shiv Build JV
2.Dhand –Rajound 33Gawar Construction
3.Rajound –Kheri 24Galfar Engineering and Contracting
4.Kheri –Julana 28JiangXi – Shiv Build JV
5.JulanaKharkara 23Gawar Construction
6.KharkaraCharkhi Dadri34Gawar Construction
7.Charkhi DadriKanina 35Gawar – Shivalaya JV
8.KaninaNarnaul27Gawar Construction

Construction progress

Dec 2018: The required 1,826 hectares of land has been acquired at the cost of ₹529.29 crores.Jul 2020: Union Minister Nitin Gadkari laid the foundation stone for the expressway on 14 July 2020 via video conferencing.Sep 2020: The expressway will be connected with the under-construction Delhi–Mumbai Expressway.Mar 2021: An under-construction flyover of Package-2 collapsed at Dulyani near Pundri, Kaithal.Mar 2022: About 95% construction work on the expressway is completed.Aug 2022: The expressway underwent a trial run for two days, and was opened for traffic on 1 August.