Nuclear decommissioning


Nuclear decommissioning is the process leading to the irreversible complete or partial closure of a nuclear facility, usually a nuclear reactor, with the ultimate aim at termination of the operating licence. The process usually runs according to a decommissioning plan, including the whole or partial dismantling and decontamination of the facility, ideally resulting in restoration of the environment up to greenfield status. The decommissioning plan is fulfilled when the approved end state of the facility has been reached.
The process typically takes about 15 to 30 years, or many decades more when an interim safe storage period is applied for radioactive decay. Radioactive waste that remains after the decommissioning is either moved to an on-site storage facility where it is still under control of the owner, or moved to a dry cask storage or disposal facility at another location. The final disposal of nuclear waste from past and future decommissioning is a growing still unsolved problem.
Decommissioning is an administrative and technical process. The facility is dismantled to the point that it no longer requires measures for radiation protection. It includes clean-up of radioactive materials. Once a facility is fully decommissioned, no radiological danger should persist. The license will be terminated and the site released from regulatory control. The plant licensee is then no longer responsible for the nuclear safety.
The costs of decommissioning are to be covered by funds that are provided for in a decommissioning plan, which is part of the facility's initial authorization. They may be saved in a decommissioning fund, such as a trust fund.
Worldwide, there are hundreds of thousands small nuclear devices and facilities, for medical, industrial and research purposes, that will have to be decommissioned at some point.

Definition

Nuclear decommissioning is the administrative and technical process leading to the irreversible closure of a nuclear facility such as a nuclear power plant, a research reactor, an isotope production plant, a particle accelerator, or uranium mine. It refers to the administrative and technical actions taken to remove all or some of the regulatory controls from the facility to bring about that its site can be reused. Decommissioning includes planning, decontamination, dismantling and materials management.
Decommissioning is the final step in the lifecycle of a nuclear installation. It involves activities from shutdown and removal of nuclear material to the environmental restoration of the site. The term decommissioning covers all measures carried out after a nuclear installation has been granted a decommissioning licence until nuclear regulatory supervision is no longer necessary. The aim is ideally to restore the natural initial state that existed before the construction of the nuclear power plant, the so-called greenfield status.
Decommissioning includes all steps as described in the decommissioning plan, leading to the release of a nuclear facility from regulatory control. The decommissioning plan is fulfilled when the approved end state of the facility has been reached. Disposal facilities for radioactive waste are closed rather than decommissioned. The use of the term decommissioning implies that no further use of the facility for its existing purpose is foreseen. Though decommissioning typically includes dismantling of the facility, it is not necessarily part of it as far as existing structures are reused after decommissioning and decontamination.,p. 49-50
From the owner's perspective, the ultimate aim of decommissioning is termination of the operating license, once he has given certainty that the radiation at the site is below the legal limits, which in the US is an annual exposure of 25 millirem in case of releasing of the site to the public for unrestricted use. The site will be dismantled to the point that it no longer requires measures for radiation protection. Once a facility is decommissioned no radioactive danger persists and it can be released from regulatory control.
The complete process usually takes about 20 to 30 years. In the US, the decommissioning must be completed within 60 years of the plant ceasing operations, unless a longer time is necessary to protect public health and safety; up to 50 years are for radioactive decay and 10 years to dismantle the facility.

Steps in the decommissioning process

The decommissioning process encompasses:
;pre-decommissioning
  • development of a decommissioning plan
  • involvement of the public
  • application for a decommissioning license
  • permanent shutdown
  • removal and disposal of nuclear fuel, coolant and/or moderator
;decommissioning
  • dismantling and decontamination
  • in the US, a License Termination Plan has to be submitted two years prior to termination of the plant license.
  • restoration of the environment
  • termination of the operating license; turn over responsibilities
  • monitoring of the site
  • monitoring and maintenance of the interim storage of spent fuel
  • final disposal of radioactive waste

Decommissioning plan

Under supervision of the IAEA, a member state first develops a decommissioning plan to demonstrate the feasibility of decommissioning and assure that the associated costs are covered. At the final shutdown, a final decommissioning plan describes in detail how the decommissioning will take place, how the facility will be safely dismantled, ensuring radiation protection of the workers and the public, addressing environmental impacts, managing radioactive and non-radioactive materials, and termination of the regulatory authorization. In the EU, decommissioning operations are overseen by Euratom. Member states are assisted by the European Commission.
The progressive demolition of buildings and removal of radioactive material is potentially occupationally hazardous, expensive, time-intensive, and presents environmental risks that must be addressed to ensure radioactive materials are either transported elsewhere for storage or stored on-site in a safe manner.

Disposal of nuclear waste

Radioactive waste that remains after the decommissioning is either moved to an on-site storage facility where it still is under control of the plant owner, or moved to a dry cask storage or disposal facility at another location. The problem of long-term disposal of nuclear waste is still unsolved. Pending the availability of geologic repository sites for long-term disposal, interim storage is necessary. As the planned Yucca Mountain nuclear waste repository – like elsewhere in the world – is controversial, on- or off-site storage in the US usually takes place in Independent Spent Fuel Storage Facilities.
In the UK, all eleven Magnox reactors are in decommissioning under responsibility of the NDA. The spent fuel was removed and transferred to the Sellafield site in Cumbria for reprocessing. Facilities for "temporary" storage of nuclear waste – mainly 'Intermediate Level Waste' – are in the UK called Interim Storage Facilities.

Environmental impact assessment

The decommission of a nuclear reactor can only take place after the appropriate licence has been granted pursuant to the relevant legislation. As part of the licensing procedure, various documents, reports and expert opinions have to be written and delivered to the competent authority, e.g. safety report, technical documents and an environmental impact assessment. In the European Union these documents are a precondition for granting such a licence is an opinion by the European Commission according to Article 37 of the Euratom Treaty. On the basis of these general data, the Commission must be in a position to assess the exposure of reference groups of the population in the nearest neighbouring states.

Options

There are several options for decommissioning:
Immediate dismantling

Shortly after the permanent shutdown, the dismantling and/or decontamination of the facility begins. Equipment, structures, systems and components that contain radioactive material are removed and/or decontaminated to a level that permits the ending of regulatory control of the facility and its release, either for unrestricted use or with restrictions on its future use.,p. 50 The operating license is terminated.
Deferred dismantling

The final decommissioning is postponed for a longer period, usually 30 to 50 years. Often the non-nuclear part of the facility is dismantled and the fuel removed immediately. The radioactive part is maintained and monitored in a condition that allows the radioactivity to decay. Afterwards, the plant is dismantled and the property decontaminated to levels that permit release for unrestricted or restrict use. In the US, the decommissioning must be completed within 60 years. With deferred dismantling, costs are shifted to the future, but this entails the risk of rising expenditures for decades to come and changing rules. Moreover, the site cannot be re-used until the decommissioning is finished, while there are no longer revenues from production.
Partial entombment

The US has introduced the so-called In Situ Decommissioning closures. All aboveground structures are dismantled; all remaining belowground structures are entombed by grouting all spaces. Advantages are lower decommissioning costs and safer execution. Disadvantages are main components remaining undismantled and definitively inaccessible. The site has to be monitored indefinitely.
This method was implemented at the Savannah River Site in South Carolina for the closure of the P and R Reactors. With this method, the cost of decommissioning for each reactor was about $73 million. In comparison, the decommissioning of each reactor using traditional methods would have been an estimated $250 million. This resulted in a 71% decrease in cost. Other examples are the Hallam nuclear reactor and the Experimental Breeder Reactor II.
Complete entombment

The facility will not be dismantled. Instead it is entombed and maintained indefinitely, and surveillance is continued until the entombed radioactive waste is decayed to a level permitting termination of the license and unrestricted release of the property. The licensee maintains the license previously issued. This option is likely the only possible one in case of a nuclear disaster where the reactor is destroyed and dismantling is impossible or too dangerous. An example of full entombment is the Chernobyl reactor.
In IAEA terms, entombment is not considered an acceptable strategy for decommissioning a facility following a planned permanent shutdown, except under exceptional circumstances, such as a nuclear disaster. In that case, the structure has to be maintained and surveillance continued until the radioactive material is decayed to a level permitting termination of the licence and unrestricted release of the structure.,p. 50

Costs

The calculation of the total cost of decommissioning is challenging, as there are large differences between countries regarding inclusion of certain costs, such as on-site storage of fuel and radioactive waste from decommissioning, dismanting of non-radioactive buildings and structures, and transport and disposal of radioactive waste.,p. 61
Moreover, estimates of future costs of deferred decommissioning are virtually impossible, due to the long period, where inflation and rising costs are unpredictable. Nuclear decommissioning projects are characterized by high and highly variable costs, long schedule and a range of risks. Compared with non-nuclear decommissioning, additional costs are usually related with radiological hazards and safety & security requirements, but also with higher wages for required higher qualified personnel. Benchmarking, comparing projects in different countries, may be useful in estimating the cost of decommissioning. While, for instance, costs for spent fuel and high-level-waste management significantly impacts the budget and schedule of decommissioning projects, it is necessary to clarify which is the starting and the ending point of the decommissioning process.
The effective decommissioning activities begin after all nuclear fuel has been removed from the plant areas that will be decommissioned and these activities form a critical component of pre-decommissioning operations, thus should be factored into the decommissioning plan. The chosen option – immediate or deferred decommissioning – impacts the overall costs. Many other factors also influence the cost. A 2018 KPMG article about decommissioning costs observes that many entities do not include the cost of managing spent nuclear fuel, removed from the plant areas that will be decommissioned.
In 2004, in a meeting in Vienna, the International Atomic Energy Agency estimated the total cost for the decommissioning of all nuclear facilities.
Decommissioning of all nuclear power reactors in the world would require US$187 billion; US$71 billion for fuel cycle facilities; less than US$7 billion for all research reactors; and US$640 billion for dismantling all military reactors for the production of weapons-grade plutonium, research fuel facilities, nuclear reprocessing chemical separation facilities, etc.
The total cost to decommission the nuclear fission industry in the World was estimated at US$1 trillion. Market Watch estimated the global decommissioning costs in the nuclear sector in the range of US$1 billion to US$1.5 billion per 1,000-megawatt plant.
The huge costs of research and development for longterm disposal of nuclear waste are collectively defrayed by the taxpayers in different countries, not by the companies.

Decommissioning funds

The costs of decommissioning are to be covered by funds that are provided for in a decommissioning plan, which is part of the facility's initial authorization, before the start of the operations. In this way, it is ensured that there will be sufficient money to pay for the eventual decommissioning of the facility. There are several types of decommissioning fund models, which differ based on ownership structure and the degree of separation from the nuclear operator or the government. In the United States, this may be through saving in a trust fund or a guarantee from the parent company. In the European Union and other regions, public and segregated models are more common, where the state establishes an independent fund that collects fees and oversees decommissioning activities.
Switzerland has a central fund for decommissioning its five nuclear power reactors, and another one for disposal the nuclear waste. Germany has also a state-owned fund for decommissioning of the plants and managing radioactive waste, for which the reactor owners have to pay. The UK Government will pay most of the costs for both nuclear decommissioning and existing waste.
The decommissioning of all Magnox reactors is entirely funded by the state.
Since 2010, owners of new nuclear plants in the Netherlands are obliged to set up a decommissioning fund before construction is started.

Underfunding

The economic costs of decommissioning will increase as more
assets reach the end of their life, but few operators have put aside sufficient funds.
In 2016 the European Commission assessed that European Union's nuclear decommissioning liabilities were seriously underfunded by about 118 billion euros, with only 150 billion euros of earmarked assets to cover 268 billion euros of expected decommissioning costs covering both dismantling of nuclear plants and storage of radioactive parts and waste.
In Feb 2017, a committee of the French parliament warned that the state-controlled EDF has underestimated the costs for decommissioning. France had set aside only €23 billion for decommissioning and waste storage of its 58 reactors, which was less than a third of 74 billion in expected costs, while the UK's NDA estimated that clean-up of UK's 17 nuclear sites will cost between €109-€250 billion. EDF estimated the total cost at €54 billion. According to the parliamentary commission, the clean-up of French reactors will take longer, be more challenging and cost much more than EDF anticipates. It said that EDF showed "excessive optimism" concerning the decommissioning. EDF values some €350 million per reactor, whereas European operators count with between 900 million and 1.3 billion euros per reactor. The EDF's estimate was primarily based on the single historic example of the already dismantled Chooz A reactor. The committee argued that costs like restoration of the site, removal of spent fuel, taxes and insurance and social costs should be included.
Similar concerns about underfunding exist in the United States, where the U.S. Nuclear Regulatory Commission has located apparent decommissioning funding assurance shortfalls and requested 18 power plants to address that issue. The decommissioning cost of Small modular reactors is expected to be twice as much respect to Large Reactors.

Examples by country

In France, decommissioning of Brennilis Nuclear Power Plant, a fairly small 70 MW power plant, already cost €480 million and is still pending after 20 years.
Despite the huge investments in securing the dismantlement, radioactive elements such as plutonium, caesium-137 and cobalt-60 leaked out into the surrounding lake.
In the UK, the decommissioning of civil nuclear assets were estimated to be £99 to £232 billion, earlier in 2005 under-estimated to be £20-40 billion. The Sellafield site alone accounts for most of the decommissioning cost and increase in cost;
as of 2015, the costs were estimated £53.2 billion. In 2019, the estimate was even much higher: £97 billion. A 2013 estimate by the United Kingdom's Nuclear Decommissioning Authority predicted costs of at least £100 billion to decommission the 19 existing United Kingdom nuclear sites.
In Germany, decommissioning of Niederaichbach nuclear power plant, a 100 MW power plant, amounted to more than €143 million.
Lithuania has increased the prognosis of decommissioning costs from €2019 million in 2010 to €3376 million in 2015.

United States

The decommissioning can only be completed after the on-site storage of nuclear waste has been ended. Under the 1982 Nuclear Waste Policy Act, a "Nuclear Waste Fund", funded by tax on electricity was established to build a geologic repository. On 16 May 2014, collection of the fee was suspended after a complaint by owners and operators of nuclear power plants. By 2021, the Fund had a balance of more than $44 billion, including interest. Later, the Fund has been put back into the general fund and is being used for other purposes. As the plan for the Yucca Mountain nuclear waste repository has been canceled, DOE announced in 2021 the establishing of an interim repository for nuclear waste.
Because the government has failed to establish a central repository, the federal government pays about half-a-billion dollars a year to the utilities as penalty, to compensate the cost of storage at more than 80 ISFSI sites in 35 states as of 2021. As of 2021, the government had paid $9 billion to utility companies for their interim storage costs, which may grow to $31 billion or more.
Nuclear waste costed the American taxpayers through the Department of Energy budget as of 2018 about $30 billion per year, $18 billion for  nuclear power and $12 billion for waste from nuclear weapons programs.
KPMG estimated the total cost of decommissioning the US nuclear fleet as of 2018 to be greater than US$150 billion. About two-thirds can be attributed to costs for termination of the NRC operating licence; 25% to management of spent fuel; and 10% to site restoration. The decommissioning of only the three uranium enrichment facilities would have an estimated cost of US$18.7 to 62 billion, with an additional US$2 to 6 billion for the dismantling of a large inventory of depleted uranium hexafluoride. A 2004 GAO report indicated the "costs will have exceeded revenues by $3.5 billion to $5.7 billion " for the 3 enrichment facilities slated for decommissioning.

International collaboration

Organizations that promote the international sharing of information, knowledge, and experiences related to nuclear decommissioning include the International Atomic Energy Agency, the Organization for Economic Co-operation and Development's Nuclear Energy Agency and the European Atomic Energy Community. In addition, an online system called the Deactivation and Decommissioning Knowledge Management Information Tool was developed under the United States Department of Energy and made available to the international community to support the exchange of ideas and information. The goals of international collaboration in nuclear decommissioning are to reduce decommissioning costs and improve worker safety.

Decommissioning of ships, mobile reactors, and military reactors

Many warships and a few civil ships have used nuclear reactors for propulsion. Former Soviet and American warships have been taken out of service and their power plants removed or scuttled. Dismantling of Russian submarines and ships and American submarines and ships is ongoing. Russia has a fleet of nuclear-powered vessels in decommissioning, dumped in the Barents Sea. Estimated cost for the decommissioning of the two K-27 and K-159 submarines alone was €300 million, or $330 million. Marine power plants are generally smaller than land-based electrical generating stations.
The biggest American military nuclear facility for the production of weapons-grade plutonium was Hanford site, now defueled, but in a slow and problematic process of decontamination, decommissioning, and demolition. There is "the canyon", a large structure for the chemical extraction of plutonium with the PUREX process. There are also many big containers and underground tanks with a solution of water, hydrocarbons and uranium-plutonium-neptunium-cesium-strontium. With all reactors now defueled, some were put in SAFSTOR. Several reactors have been declared National Historic Landmarks.

List of inactive or decommissioned civil nuclear reactors

A wide range of nuclear facilities have been decommissioned so far. The number of decommissioned nuclear reactors out of the List of nuclear reactors is small. As May 2022, about 700 nuclear reactors have been retired from operation in several early and intermediate stages, but only about 25 have been taken to fully "greenfield status". Many of these sites still host spent nuclear fuel in the form of dry casks embedded in concrete filled steel drums.
As of 2017, most nuclear plants operating in the United States were designed for a life of about 30–40 years and are licensed to operate for 40 years by the US Nuclear Regulatory Commission. As of 2020, the average age of these reactors was about 39 years. Many plants are coming to the end of their licensing period and if their licenses are not renewed, they must go through a decontamination and decommissioning process.
Generally are not included the costs of storage of nuclear waste, including spent fuel, and maintenance of the storage facility, pending the realization of repository sites for long-term disposal,p. 246. Thus many entities do not include the cost of managing spent nuclear fuel, removed from the plant areas that will be decommissioned. There are, however, large differences between countries regarding inclusion of certain costs, such as on-site storage of fuel and radioactive waste from decommissioning, dismanting of non-radioactive buildings and structures, and transport and disposal of radioactive waste.,p. 61

The year of costs may refer to the value corrected for exchange rates and inflation until that year.
The stated power in the list is preferably given in design net capacity in MWe, similar to the List of commercial nuclear reactors.
CountryLocationReactor typeOperative lifeDecommissioningDecommissioning costs
AustriaZwentendorfBWR 723 MWeNever activated due to referendum in 1978Now a technics museum
BelgiumSCK•CEN – BR3,
located at Mol, Belgium
PWR 1962–1987
2002-Still unknown
BulgariaKozloduy
Units 1, 2, 3, 4
PWR VVER-440
Reactors 1,2 closed in 2003,
reactors 3,4 closed in 2006
OngoingStill unknown
CanadaGentilly
Unit 1
CANDU-BWR
250 MWe
180 days
Ongoing
"Static state" since 1986
Still unknown
stage two:
$25 million
CanadaGentilly-2CANDU-BWR
675 MWe
1 October 1983 to 28 December 2012Ongoing$1.8 billion
CanadaPickering NGS
Units A2, A3
CANDU-PWR
8 x 542 MWe
30 years
Ongoing
Two units currently in "cold standby"
Decommissioning to begin in 2020
Still unknown
calculated: $270–430/kWe
ChinaBeijing HWWR 10 MWe 49 years
SAFSTOR until 2027Still unknown
proposed: $6 million for dismantling
$5 million for fuel remotion
FranceBrennilisHWGCR 70 MWe12 years
Ongoing
Phase 3
Still unknown
already spent €480 million
FranceBugey
Unit 1
UNGG
Gas cooled, graphite moderator
1972–1994Ongoing
postponed
Still unknown
FranceChinon
Units 1, 2, 3
Gas-graphite
Ongoing
postponed
Still unknown
FranceChooz-APWR 300 MW24 years
2007-
Ongoing
Deferred dismantling;

dismantling to finish by 2025
Still unknown
FranceSaint-LaurentGas-graphite1969–1992Ongoing
Postponed
Still unknown
FranceRapsodie at
Cadarache
Experimental
Fast breeder nuclear reactor

40 MWe
15 years
1983- Ongoing
dismantling planned by 2005; general decontamination planned by 2020
Still unknown
FrancePhénix at
Marcoule
Experimental
Fast breeder nuclear reactor

233 MWe
36 years
2005-
Ongoing
non-nuclear dismantling finished in 2011; finalising expected between 2031 and 2043.
Still unknown
FranceSuperphénix at
Creys-Malville
Fast breeder nuclear reactor
11 years
Ongoing
1) Defuelled
2) Extraction of Sodium
Pipe cutting with a robot
Still unknown
East GermanyGreifswald
Units 1, 2, 3, 4, 5, 6
VVER-440
5 x 408 MWe
Reactors 1–5 closed in 1989/1990,
reactor 6: finished but never operated
Ongoing
Immediate
dismantling
Still unknown
East GermanyRheinsberg
Unit 1
VVER-210
70–80 MWe
24 years
Ongoing
In dismantling
since 1996
Safstor
Still unknown
East GermanyStendal
Units 1, 2, 3, 4
VVER-1000
Never activated
Not radioactive
Still unknown
West GermanyGundremmingen-ABWR
250 MWe

11 years
Ongoing
Immediate
dismantling
pilot project
Still unknown
IndiaRajasthan Atomic Power Station
Unit 1
PHWR 100 MWe 44 years
OngoingStill unknown
ItalyCaorsoBWR
840 MWe
9 years
1999-2031 €450 million
+ €300 million
ItalyGarigliano BWR
150 MWe
18 years 1999-2031 Still unknown
ItalyLatina Magnox
210 MWe Gas-graphite
24 years
1999-2035 Still unknown
ItalyTrino VercellesePWR Westinghouse,
270 MWe
25 years
1999-2030 Still unknown
JapanFukushima Dai-ichi
Unit 1
BWR 439 MWe17 November 1970 – 11 March 2011Ongoing
Since 2011 Tōhoku earthquake and tsunami of 11 March

Hydrogen explosion
Estimated at ¥10 trillion for decontaminating Fukushima and dismantling all reactors in Japan and considering long time damage to environment and economy, including agriculture, cattle breeding, fishery, water potabilization, tourism, loss of reputation in the world
.
JapanFukushima Dai-ichi
Unit 2
BWR 760 MWe24 December 1973 – 11 March 2011OngoingStill unknown
JapanFukushima Dai-ichi
Unit 3
BWR 760 MWe26 October 1974 – 11 March 2011OngoingStill unknown
JapanFukushima Dai-ichi
Unit 4
BWR 760 MWe24 February 1978 – 11 March 2011Ongoing
Since 11 March 2011 Reactor defueled when tsunami hit
Damage to spent fuel cooling-pool
Still unknown
JapanFukushima Dai-ichi
Unit 5
BWR 760 MWe22 September 1977 – 11 March 2011Planned decommissioning
Cold shutdown since March 11, 2011
Still unknown
JapanFukushima Dai-ichi
Unit 6
BWR 1067 MWe4 May 1979 – 11 March 2011Planned decommissioning
Cold shutdown since 11 March 2011
Still unknown
JapanFukushima Daini
Unit 1
BWR 1067 MWe31 July 1981 – 11 March 2011Planned decommissioning
Cold shutdown since 11 March 2011
Still unknown
JapanFugenAdvanced thermal reactor

165 MWe
1979–2003Ongoing
Since March 11, 2011 Cold shutdown
Still unknown
JapanTokai
Unit 1
Magnox 160 MWe1966–1998deferred dismantling: 10 years
then decon
until 2018

¥93 billion
North KoreaYongbyonMagnox-type
1985–2005

Deactivated after a treaty
deferred dismantling; cooling tower dismantledStill unknown
NetherlandsDodewaardBWR Westinghouse
55 MWe
1968–1997
2002-2100+
safe-storage; start dismantling in 2045;
separate interim storage of high-level waste at COVRA for 100 years or longer,p. 171
estimated cost €134 million ; €180 million ,p. 174
RussiaMayak
PUREX plant for
uranium enrichment
1946–1956
OngoingStill unknown
RussiaSeversk
Three plutonium reactors
Plant for uranium enrichment
Two fast-breeder reactors closed,
after disarmaments agreements with USA in 2003.
OngoingStill unknown
SlovakiaJaslovské Bohunice
Units 1, 2
VVER 440/230
2 X 440 MWe

OngoingStill unknown
SpainJosé CabreraPWR
1 x 160 MWe
38 years
2010-2023Still unknown
Estimation increased from 135 mln in 2003 to 217.8 mln in 2014
SpainSanta María de Garoña
BWR/3
1 x 466 MWe
1966–2013Ongoing
Defueled
Still unknown
SpainVandellós
Unit 1
UNGG
480 MWe
18 years
Incident:
fire in a turbogenerator
SAFSTOR: 30 years
Still unknown
Phases 1 and 2: €93 million
SwedenBarsebäck
Units 1, 2
BWR 2 x 615 MWReactor 1: 24 years 1975–1999
Reactor 2: 28 years 1977 – 2005
SAFSTOR: demolition will begin in 2020The Swedish Radiation Safety Authority has assessed that the costs for decommissioning and final disposal for the Swedish nuclear power industry may be underestimated by SKB by at least 11 billion Swedish kronor
SwedenOskarshamn
Units 1, 2
BWR 1 x 473 MW
BWR 1 x 638 MW
Reactor 1: 45 years 1972–2017
Reactor 2: 41 years 1975 – 2016
OngoingStill unknown
SwedenRinghals
Units 1, 2
BWR 1 x 881 MW
PWR 1 x 904 MW
Reactor 1: 44 years 1976–2020
Reactor 2: 44 years 1975 – 2019
OngoingStill unknown
SwitzerlandDIORITMWe CO2-Gas-heavy water
DecommissionedStill unknown
SwitzerlandLUCENS8,3 MWe CO22-Gas-heavy water

Incident: fire in 1969
DecommissionedStill unknown
SwitzerlandSAPHIR0,01–0,1 MWe
39 years

DecommissionedStill unknown
UkraineChernobyl-4
RBMK-1000
1000 MWe
hydrogen explosion,
then graphite fire (1986)

Ongoing
ENTOMBMENT
Still unknown

United Kingdom">Nuclear power in the United Kingdom">United Kingdom

LocationReactor typeOperative lifeDecommissioningDecommissioning
costs
BerkeleyMagnox
1962–1989
save storageStill unknown
BradwellMagnox
2 x 121 MWe
1962–2002
2002-2083 or later
save storage
Still unknown
Calderhall
Sellafield
Magnox
4 x 60 MWe
1956-2003
save storageStill unknown
ChapelcrossMagnox
4 x 60 MWe
1959–2004
save storageStill unknown
Dounreay: DMTR
Fast-neutron reactor1958–1969Ongoing
Demolition contract awarded December 2018
Still unknown
Dounreay: DFR
Loop-type fast breeder.
14 MWe.
1959–1977OngoingStill unknown
Dounreay: PFR
Pool-type fast breeder cooled by liquid sodium, fueled with MOX.250 MWe.1974–1994

Delays and reliability problems before reaching full power.
Remotely operated robot 'Reactorsaurus' will be sent in to decontaminate equipment as too dangerous a task for a human. Control panel has been earmarked for an exhibition at London Science Museum.Still unknown
Winfrith
Dorset
SGHWR
92 MWe
1968 to 1990
1995-
dismantled;
off-site storage of waste
Still unknown

United States">Nuclear power in the United States">United States

LocationReactor typeOperative lifeDecommissioningDecommissioning
costs
Connecticut Yankee
Connecticut
PWR
619 MWe
1968–1996
1998-2007
DECON; on-site ISFSI waste storage
931 mln;
additional $575.5 mln in court awarded from DOE for waste storage at 3 plants
Crystal River 3
Florida
PWR
825 MWe
1977–2009
2013-2037
DECON; on-site
ISFSI waste storage
In 2013 estimated ~$1,2 bln
Dresden
Unit 1
BWR
207 MWe
1960–1978
Defueled in safety in 1998
now in SAFSTOR
Fuel in on-site dry-casks.
Still unknown
Ft. Calhoun
PWR
484 MWe
1973-2016
2016-2026
DECON; off-site waste storage
$980M
Fort St. Vrain
HTGR

330 MWe
1979–1989
1989-1992

dismantled; off-site ISFSI waste storage;
replaced by conventional station
$283 million
Pacific Gas & Electric
Humboldt Bay
Unit 3
BWR 63 MWe1963–1976
1988-2021

License terminated in Oct 2021;
site released for unrestricted use;
New license for on-site storage facility for the spent fuel.
Unknown

Fund for $53.3 million required for decommissioning of storage alone.
Maine YankeePWR
860 MWe
24 years
DECON; on-site ISFSI waste storage$635 million
Piqua NGS
OCM reactor 46 MWe2 years
ENTOMB
Still unknown
Rancho Seco NGS
PWR 913 MWe12 years
SAFSTOR: 5–10 years
completed in 2009

Fuel in insite long-term dry-cask storage
$538.1 million
San Onofre NGS Unit 1
PWR 436 MWe Westinghouse Electric Corporation1967–1992
1993-2032
dismantled; on-site ISFSI waste storage for whole plant
Still unknown
San Onofre NGS Units 2, 3
PWR
1070 MWe
1080 MWe
Unit 2: 1983–2013
Unit 3: 1984–2013

In 2011, Edison finished replacing the steam generators in both reactors with improved Mitsubishi ones, but the new design had several problems, cracked, causing leaks and vibrations.
in defueling.Permanent shutdown – DECON
soon defueling
Still unknown
2014 cost forecast:
$3.926 billion
to $4.4 billion
Shippingport
BWR 60 MWe25 years
Decon completed
dismantled in 5 years
$98.4 million
Three Mile Island Nuclear Generating Station
Unit 2
PWR 913 MWe1978–1979
Core meltdown incident
Post-Defuelling
Phase 2
$805 million
Trojan
PWR 1,180 MWe16 years
SAFSTOR
Vermont YankeeBWR 620 MWe
1972–2014
Ongoing
2015–
~$1.24 billion
Yankee Rowe
PWR 180 MWe1961–1991

Construction cost was $45 million
completed in 2007
on-site ISFSI waste storage
$608 million
Zion
Units 1, 2
2 x PWR 1040 MWe
1973/1974–1998
1998-2020
after SAFSTOR full dismantling;
New on-site for spent fuel storage
Costs for SAFSTOR unknown;
for dismantling & decontamination estimated in 2010 $1 billion
+ demolition city fees millions;
for remaining waste unknown