White Rock Wind Farm


White Rock Wind Farm is a wind farm in the Australian state of New [South Wales]. It is in the New England region of northern New South Wales, east of Inverell, [New South Wales|Inverell] and west of Glen Innes. It is south of the Gwydir Highway. The Sapphire [Wind Farm] is north of the highway and Glen Innes Wind Farm is south of the highway closer to Glen Innes. It is approved for up to 119 wind turbines, and stage 1 has been completed with 70 turbines. In 2011 it had an estimated construction cost of A$450m.

Operations

The wind farm began increasing output grid power in July 2017, was fully commissioned in February 2018 and has operated since then. The generation table uses to obtain generation values for each month.
YearTotalJanFebMarAprMayJunJulAugSepOctNovDec
201780,622N/AN/AN/AN/AN/AN/A1,563*15,204*10,029*17,452*18,473*17,901*
2018520,68630,826*47,075*51,72047,18439,87446,46243,34349,25940,78040,16039,692*44,311
2019525,37330,78656,92244,35550,95943,41344,34249,50337,38945,09034,49742,63445,483
2020501,09533,44943,15954,14629,95144,30236,75845,32751,72448,54432,17932,37149,185
2021492,98843,13845,91247,52538,16830,66741,47949,61136,05230,62343,13848,02138,654

Note: Asterisk indicates power output was limited during the month.