Varanasi–Kolkata Expressway
Varanasi–Ranchi–Kolkata Expressway ',' is an under-construction long, six-lane, greenfield access-controlled expressway, which will connect the spiritual city of Varanasi in Uttar Pradesh with the capital of West Bengal, Kolkata, through the capital of Jharkhand, Ranchi. It will run almost parallel to the Grand Trunk Road or the Asian Highway 1, and will pass through four states–Uttar Pradesh, Bihar, Jharkhand and West Bengal. The expressway is a part of Bharatmala Pariyojana, and it will reduce both travel time and distance, from 14-15 hours to only 10-11 hours. It will start from Revasa village near Mughalsarai, Chandauli district in Uttar Pradesh, and will terminate near Sarisha, near Diamond Harbour, West Bengal.
The foundation stone for the expressway's construction was laid by Prime Minister Narendra Modi on 23 February 2024. To be built at a cost of about, it is expected to be completed by 2026/27.
History
The Government of India has given special emphasis on infrastructure development in FY 2022–23. To improve connectivity, tourism, development and economic growth in eastern India, the Government of India planned to build a new expressway from Varanasi to Kolkata through Ranchi. The expressway is expected to cut travel time from 12 to 14 hours to 6–7 hours, and from to. It will pass through four states–Uttar Pradesh, Bihar, Jharkhand and West Bengal. Once completed, these states will see exponential growth with the growth of industries and socio-economic development by promoting employment among people living in the regions, which the regions currently mostly lack altogether. The expressway was earlier slated to be eight-lane, but was reduced six lanes due to lack of space. It was initially planned to be built at a cost of, and will be completed by 2027, which was earlier scheduled in the first quarter of 2026. On 23 February 2024, the foundation stone for the construction was laid by Prime Minister Narendra Modi for its first package till Bihar, to be built at a cost of about.Route
Uttar Pradesh
The western terminus of the expressway will be located in Chandauli district near Varanasi in Uttar Pradesh. The western end of the expressway near Barhuli village will be connected with the National Highway 19 and the Varanasi Ring Road. The expressway will cover a total distance of within Uttar Pradesh.Bihar
The expressway will cross the Uttar Pradesh-Bihar border and will enter through Kaimur district of Bihar. It will cross the state through the districts of Kaimur, Aurangabad, Rohtas and Gaya. The expressway will cover a total distance of within Bihar.Jharkhand
The expressway will cross the Bihar-Jharkhand border and will enter the Chatra district of Jharkhand. It will cross the state through the districts of Chatra, Hazaribagh, Ramgarh and Bokaro. The expressway will cover a total distance of within Jharkhand.West Bengal
The eastern terminus of the expressway will be located at Haldia, West Bengal with an extended route including a Vertical Lift Bridge on Hooghly River to connect Sarisha near Diamond Harbour. It will cross the state through the districts of Purulia, Bankura, Paschim Medinipur, Hooghly and Purba Medinipur. The expressway will cover a total distance of within West Bengal.Construction
The expressway will be fully six-lane and a greenfield project, and will be built using the Engineering, Procurement and Construction construction model, which provides and ensures security, liability caps, and a performance guarantee for an infrastructure. For the project, the soil testing work in Jharkhand was conducted in June 2022. It will run almost parallel with the National Highway 19, or the Asian Highway 1 or the Grand Trunk Road. The land acquisition process started in January 2022 on an 80-km section of the expressway, from Tilouthu to Imamganj in Bihar. The National Highways Authority of India released tenders and invited bids in November 2022 for the construction of the expressway. As of March 2023, the project has been divided into 13 packages, and the package division for the West Bengal section is still underway. In Package-1, NHAI issued global tenders, and allocated ₹ 988 crore for the construction of the 27 km stretch from Varanasi Ring Road in Uttar Pradesh to Khainti village in Bihar, and in Package-2, ₹ 945 crore has been allocated for the construction of another 27 km stretch from Khainti village to Palka village in Bihar, wherein it will be built using the Hybrid Annuity Model mode of construction. In the West Bengal section, the Government of West Bengal has directed 6 districts of the state to carry out land acquisition for the project, and is underway. Currently, the project is under Detailed Project Report preparation and land acquisition. The foundation stone for the expressway's construction by starting from the first package was laid by Prime Minister Narendra Modi in February 2024. The following table list the project's packages, contractors and their statuses.Jharkhand
The remaining stretch till Kolkata is under package division, land acquisition may start soon as DPR preparation is finished.Benefits
The expressway will benefit eastern India along with the entire country as follows:- Trade: The expressway will help to boost trade, increase exports and reduce dependency on imports, as it will result in the growth of industries in Eastern India, along the route through which the expressway will pass, especially in the adjoining regions of Kolkata further, and due to its location near the sea with two major ports–Kolkata and Haldia, resulting in a huge benefit for transporting steel and coal to the ports from the famous steel plants and coal mines located in the mineral-rich state of Jharkhand, the Bokaro Steel Plant and coal mines of Dhanbad, thus accelerating economic growth and development in the four states.
- Tourism: It will help to boost tourism by promoting it in places which currently lack, along its route. The alignment of the expressway has been specially made through the backward areas to help facilitate tourism and development, due to a high presence of small tourist spots, dotted across the four states, especially in Jharkhand and the western part of West Bengal, but remain relatively unknown to most people because of lack of accessibility to those areas.
- Connectivity: The expressway will create a direct 710 km route between Varanasi and Kolkata, by reducing both travel time and distance from 14 to 11 hours It will not only connect Varanasi, but will also connect Kolkata directly with the national capital, as well as Jammu and Kashmir, through a series of expressways, along with this–Purvanchal Expressway, Agra–Lucknow Expressway and Yamuna Expressway to Delhi, and to Jammu and Kashmir via the Delhi–Katra Expressway. In the coming years, instead of Purvanchal and Agra–Lucknow Expressways, the Ganga Expressway will connect Kolkata more faster, as well as with Haridwar. This expressway till Varanasi will also connect Rajasthan via the Chambal Expressway through the Agra–Lucknow Expressway. This series of expressways will result in faster, better and safer commute for both the transport of goods and people, with the rest of the country, from Eastern India.
- Protection of the Environment: To protect the green cover, plants and trees will be planted between and on both sides along the entire route of the expressway. In the Kaimur district section of Bihar, a 5 km-long tunnel will be built along the hilly region to avoid deforestation.
- Employment: Due to increase in industrial activities along the expressway's route, various agricultural and industrial initiatives will help in the economy and growth of Eastern India. The establishment of these numerous centres will result in multiple job possibilities for thousands of people living in the four states.
Status updates
- 2019: The expressway's plan was proposed by the Ministry of Road Transport and Highways.
- 2023 Jan: Land acquisition began for the project.
- 2023 Mar: 15 bidders participated to construct 8 packages of the expressway.
- 2023 Apr: The bidding process has been entirely completed for the Jharkhand section, and land acquisition has started. Bids have been received for Jharkhand-West Bengal border section in March 2023 and will be awarded by April-May.
- 2024 Feb: The foundation stone was laid by Prime Minister Narendra Modi for the construction of the expressway.
- *2025 Dec: On 413-km Jharkhand –Varanasi section the construction work is in varying stages of physical progress and work on 41 is stalled due to delay in forests clearances, i.e. Khajuri–Wyndhamganj 92% complete on UP section, Bhogu–Sankha 75% complete in Jharkhand, Udaipura–Bhogu in Jharkhand 20% complete in 2024, and Kuru–Udaipura section 16 km out of 39 km stalled and no work has started due to delay in forest clearance by Jharkhand government.