Temane Thermal Power Station
Temane Thermal Power Station, is a natural gas power plant under construction in Mozambique. When completed, the energy generated will be purchased by Electricidade de Moçambique, the government-owned electric utility company, under a long-term power purchase agreement.
Location
The power station is located in the town of Temane, in Inhambane Province in southern Mozambique. Temane is situated about, by road, north of the city of Inhambane, where the provincial capital is located. This is approximately, by road, northeast of the city of Maputo, the capital of Mozambique.Developers
The power station is under development by a consortium comprising the corporate entities illustrated in the table below:| Rank | Development Partner | Domicile | Relationship |
| 1 | Globeleq | United Kingdom | Equity Investor |
| 2 | eleQtra | United Kingdom | Equity Investor |
| 3 | EDM | Mozambique | Equity Investor |
| 4 | Sasol Africa Limited | South Africa | Equity Investor |
History
This power project was originally owned by EDM of Mozambique and Sasol New Energy Holdings of South Africa. In December 2020, the owner/developers brought on Globeleq and eleQtra. The consortium jointly formed a special purpose vehicle company to develop this power station, which they named Temane Energy Consortium . Financial closure was achieved in December 2020. The power station will be designed and constructed by TSK Electronica y Electricidad S.A., a Spanish electronic and electricity construction company.Funding
The table below illustrates the funding sources for the Temane Thermal Power Station. The list of funders may not be complete.| Rank | Development Partner | Contribution in Euros | Percentage | Notes |
| 1 | The World Bank Group | 420 million | Grant & Guarantees | |
| 2 | U.S. International Development Finance Corporation | 200 million | Loan | |
| 3 | OPEC Fund | 50 million | Loan | |
| 4 | Temane Energy Consortium | Owner/Developer Consortium | ||
| 5 | Government of Mozambique | Equity Investor | ||
| Total | 750 million | 100.00 |
Associated developments
In addition to the natural gas-powered electricity generating plant, as part of the same development, of associated transmission infrastructure will be established to distribute the energy generated to neighboring communities and where possible sell any excess to the Southern Africa Power Pool.It is expected that when this power station comes online in 2022, a portion of the energy generated here, amounting to 100 megawatts, will be sold to Botswana Power Corporation, under a one-year power purchase agreement signed in April 2022, between EDM and BPC, in Gaborone, Botswana.