Tel Aviv Light Rail
The Tel Aviv Light Rail, also known as Dankal is a mass transit system for Gush Dan, the Tel Aviv metropolitan area in central Israel. The system will include different modes of mass transit, including rapid transit, light rail transit, and bus rapid transit. Overseen by NTA Metropolitan Mass Transit System Ltd., a government agency, the project will complement the intercity and suburban rail network operated by Israel Railways.
As of 2023, two LRT lines are under construction and one available to the public. Work on the Red Line, the first in the project, started on September 21, 2011, following years of preparatory works, and was opened on August 18, 2023, after numerous delays. Construction of the Purple Line started in December 2018; work on the Green Line began in January 2019.
The network was originally planned to be called "MetroTLV" but was changed to "Dankal". The name comes from the metropolitan area of Tel Aviv, Gush Dan, and "light".
History
The first proposals for a tramway in the area were made by the Lebanese engineer George Franjieh in November 1892, about nine weeks after the inauguration of the Jaffa–Jerusalem railway. The plan called for a main line between southern and northeastern Jaffa, with spurs to the harbor and the eastern orchards. The plan was considered uneconomical and was shelved. A later plan called for a light railway from Jaffa to the nearby towns of Rishon LeZion, Petah Tikva and Wilhelma.A Decauville light railway was built in Jaffa and Tel Aviv in World War I, connecting the port with the Yarkon River. It was used for about a decade after the war, and dismantled at a later date.
A light rail line, with a route similar to the current Red Line, was planned in 1921 by Pinhas Rutenberg. An attempt to build the line in 1924-5 was unsuccessful.
A subway system was first planned in the mid-1960s but a station at the Shalom Meir Tower was all that was completed of the project, with no rails laid.
Revised plan: Light Rail
In 2000, the plan for a subway was changed to one for light rail, and more plausible plans for a mass transit system in Tel Aviv were unveiled. After the first Red Line spanning was approved, excavation began in late 2009, with construction of the underground stations starting in August 2015. The Red Line became operational on August 18, 2023.In December 2006, the MTS group was awarded a Build-Operate-Transfer contract for the Red Line of the light rail, by which they are to build and operate the line for its first 32 years. MTS consisted of Africa Israel, Siemens, Egged, China Civil Engineering Construction, Soares da Costa, and HTM. After many years of delays due to MTS financing issues, in December 2010 the government revoked MTS's concession and nationalized the project, putting it under the authority of NTA, the government agency which was in charge of overseeing the overall development of the rapid transit system in Gush Dan.
Further construction
Construction on the Red Line began in August 2015. It opened on August 18, 2023. The preparations for the construction of the Green Line started on February 5, 2017, on Ibn Gabirol Street in Tel Aviv. Infrastructure works for the Purple Line began in December 2018.Lines
| Primary line | Color | Service bullets |
| Red Line | Red | |
| Green Line | Green | |
| Purple Line | Purple |
Red Line is in service; Green and Purple lines are under construction. When complete, they will cover a network of.
| Line | Length | No. of stations | Status | Opening | Passengers | Primary municipalities | Terminals | Rolling Stock |
| ' | 34 | In service | August 18, 2023 | 100,000 daily | Tel Aviv, Petah Tikva, Bnei Brak, Ramat Gan, Bat Yam |
| CRRC Changchun LRV | |
| ' | 62 | Under construction | Southern section est. 2028, northern section est. 2030 | est. 275,000 daily | Tel Aviv, Herzliya, Holon, Rishon LeZion | Alstom Citadis | ||
| 43 | Under construction | est. 2028 | est. 256,000 daily | Tel Aviv, Ramat Gan, Kiryat Ono, Giv'at Shmuel, Or Yehuda, Yehud | CAF Urbos |
Red Line
of the Red Line was built underground, with the remaining overground segment constructed as a light rail/tram. It has 34 stops, 10 of which are underground, with an average distance of about 1000 meters between underground stops and of about 500 metres between overground stops. The line runs from Bat Yam in the southwest, through Jaffa and central Tel Aviv, including at Tel Aviv–Savidor Center railway station, and carries on to Petah Tikva, through Ramat Gan and Bnei Brak. An extension to Rishon LeZion is planned. It has been forecast that 70 million passengers will be using this line annually.Stations : HaKomemiyut, He'Amal, Kaf Tet BeNovember, Yoseftal, Binyamin, Balfour, Jabotinsky, Rothschild, Ha'Atsma'ut, Mahrozet, HaBesht, Isakov, Ehrlich, Bloomfield Stadium, Shalma, Elifelet, Allenby, Carlebach, Yehudit, Sha'ul HaMelekh, Arlosoroff, Abba Hillel, Bialik, Ben-Gurion, Aharonovich. From Aharonovich, one branch continues to Shenkar, Shaham, Beilinson, Dankner, Krol, Pinsker, Petah Tikva Central Bus Station ; another continues to Em HaMoshavot Bridge and Kiryat Arye.
The work on Allenby station began on February 8, 2015.
In May 2021, a test run of the red line began in Petah Tikva. The Red Line was opened to the public in August 2023.
Green Line
The second or Green Line, in the tender phase, is a with of them underground. It will have 62 stops that would run from the west of Rishon LeZion northwards through Holon through central Tel Aviv splitting into two branches: one to Herzliya in the north and the other one to Ramat HaHayal neighborhood in Tel Aviv in the northeast. Only its central Tel Aviv segment, four of the 62 stations, will be underground, from Levinski Street through Ibn Gabirol Street until the Yarkon River. The expected annual passenger forecast is 65 million. NTA included the design and boring of the Green Line's tunnels as part of Red Line's tunnels overall contract so that work on the Green Line's underground portion could commence immediately following the completion of the Red Line tunnels.Purple Line
The third, or Purple Line, is envisaged as a line with 43 stops and will connect Sheba Hospital through Giv'at Shmuel and Kiryat Ono, and will connect the Arlozorov bus terminal and Tel Aviv–Savidor Central railway station to Yehud and Or Yehuda through Ramat Gan. It will follow a semi-circular route in central Tel Aviv, between Tel Aviv–Savidor Central railway station in the north and Tel Aviv–HaHagana railway station in the south, looping westwards through the heart of the city, and will interchange with the Red Line and the Green Line twice each. This line will be over-ground for its entire route.Cancelled lines
Yellow Line
This line would have begun in Kfar Saba then continued on to Hod Hasharon, Herzliya, Ramat Hasharon on Sokolov Street, before joining Ben-Gurion Street in Ramat Gan, then Yitzhak Rabin Street in Givatayim, then Moshe Dayan Street in Tel Aviv, Mikveh Israel, it would end in Holon after crossing Ariel Sharon Park. Parts of it were superseded by the M1 metro line.As of December 2024, the plan is to run the line as a BRT line.
Other mass transit systems
Metro
The rapid transit plan for Gush Dan, conceived and approved in 2016, called for three underground metro lines, centered on Tel Aviv: a north–south line, an east–west line, and a circular line. The system is currently under construction.| Line | Length | No. of stations | Status | Opening | Primary municipalities | Terminals |
| M1 | 62 | M1S – Approved M1C – Approved M1N – Planned | 2032 | Tel Aviv, Lod, Ramle, Be'er Ya'akov, Rehovot, Nes Ziona, Rishon LeZion, Holon, Ramat HaSharon, Herzliya, Ra'anana, Hod HaSharon, Kfar Sava | ||
| M2 | 22 | Approved | NET 2032 | Tel Aviv, Bat Yam, Giv'atayim, Ramat Gan, Bnei Brak, Petah Tikva | Petah Tikva | |
| M3 | 25 | Approved | NET 2032 | Tel Aviv, Herzliya, Petah Tikva, Kiryat Ono, Or Yehuda, Azor, Holon, Bat Yam | Herzliya Pituah Bat Yam |
Bus rapid transit
Most BRT lines planned for Gush Dan were cancelled in 2016 and replaced with metro lines. Only plans for the Brown Line were retained, however, no date for start of construction has been announced.| Line | Length | No. of stations | Status | Opening | Primary municipalities | Terminals |
| ' | 46 | Planned | 2028 | Rishon LeZion, Be'er Ya'akov, Ramle, Lod | ||
| ' | 44 | Planned | 2028 | Rehovot, Ness Ziona, Rishon LeZion, Azor, Holon | Bilu Junction Holon Junction |