Dwarka Expressway
NH 248-BB, also known as Dwarka Expressway, is an existing long opertional, 16-lane, including 8-lane elevated grade separated and 8-lane service road, expressway connecting Dwarka in Delhi to Kherki Daula Toll Plaza at Gurgaon in Haryana. The expressway takes off from km 20 milestone of NH-48 at Shiv Murti in Mahipalpur adjacent to the IGI Airport in Delhi and terminate at km 40 of NH-48 near Kherki Daula Toll Plaza in Gurgaon in Haryana. The Dwarka Expressway serves as an alternate road link between Delhi and Gurgaon to ease the traffic congestion on the Delhi–Gurgaon Expressway section of NH-48.
History
Conception
Entire project, costing ₹7,500 crore was planned in 2006. After the land acquisition started in 2007-08, the construction contract was awarded to JSR Construction Private Ltd and India Bulls Private Ltd in April 2011 with the completion date of 31 March 2012. Contract was awarded in 2011 and 14 km out of the original 18 route were completed by 2016. Several more kilometre project routes was added to the scope of the project as an extension, by altering the originally planned route to the current alignment.Land acquisition issues delayed the project for several years. After the Punjab and Haryana High Court disposed of the petitions by the land owners in May 2015, the partially completed project was acquired by National Highways Authority of India and road was renamed National Highway 248-BB in June 2016, and the scope of the project was expanded by including the proposed Central Peripheral Road and 6.3 km long section of Urban Extension Road-II as part of the expressway. But construction couldn't be started immediately as HUDA was not able to hand over land to NHAI due to the matter of allotment of alternate plots to oustees being heard in Punjab and Haryana High Court. On 28 May 2018, the High Court directed HUDA to allot alternate houses to 72 oustees, holding General Power of Attorney or Special Power of Attorney, within two weeks and thus allowing the authority to demolish remaining houses and hand over the land to NHAI. Still, various parts of the project remained delayed due to land acquisition and tree transplantation hurdles, resulting in the intervention from the Prime Minister's office in November 2018 to resolve the pending issues, and all the land related issues were resolved within 2018.
Having resolved the land issues, on 08-March-2019 Union Minister Nitin Gadkari laid the foundation stone having already awarded most of the construction contracts. In March 2024, Prime Minister Narendra Modi inaugurated the partially-completed 18.9 km stretch in Haryana, and the entire route of the completed expressway became operational in June 2025.
Construction
Construction packages awarded, from north to south, are as follows:- Package 1 - in Delhi: Mahipalpur Shiv Murti cloverleaf interchange to Bijwasan railway station underpass, 5.3km including 3.6 km deep tunnel:
- Package 2 - in Delhi: Bijwasan rail underpass to Delhi–Haryana border, 4.2 km elevated: from km 5.3 at the Bijwasan rail underbridge till km 9.5 at the Delhi–Haryana border on the expressway.
- Package 3 - in Gurugram: Delhi–Haryana border to approach of Basai railway overbridge, 10.2 km elevated:
- Package 4 - in Gurugram: Basai rail overbridge to Kherki Daula Toll Plaza, 8.77 km elevated, cost INR 1,333 crore:
- Package 5 - in Delhi: Mahipalpur Shiv Murti to IGI Airport T3 Tunnel, 2.3 km shallow tunnel to T3:
Route
Existing
The route alignment to the west of Gurgaon is as follows:- In Delhi
- * Mahipalpur, commences at Shiv Murti on 20 km milestone of NH 48
- * Along Indira Gandhi International Airport southern perimeter
- * Under Delhi–Rewari railway line near new terminus of Bijwasan railway station
- * Dwarka Sectors 21, 22, 25, 27, 28
- * Najafgarh-Bijwasan Road
- In Haryana
- * Bajghera village in Gurgaon
- * Road bridge over Delhi-Rewari railway line at Sectors 99 x 37D in Gurgaon
- * National Highway 352W near Harsaru in Gurgaon
- * Kherki Daula Toll Plaza, terminates here to Delhi–Mumbai Expressway and Southern Peripheral Road
Planned extensions
- Shiv Murti-Vasant Kunj Tunnel : 6-lane expressway from Shiv Murti on Dwarka Expressway & NH-48 intersection to Nelson Mandela Marg in Vasant Kunj with interchanges at Andheria Mor and NH148A Anuvrat Marg-Mehraul intersection, then Mehrauli to Badarpur at NH19.
- Shiv Murti-Sarai Kale Khan Tunnel: The northern end of the tunnel at Mahipalpur in Delhi from the existing Shiv Murti is planned to be extended another 18 to 20 km to Sarai Kale Khan multi-model transport hub where the bus station, suburban metro, NCR regional RRTS, long-distance national rail, etc are co-located.
Related connectivity
Existing connectivity
- Northern end of Dwarka Expressway in Delhi: connects to the UER II, IGI Airport, Delhi–Gurgaon Expressway, and Delhi Metro NCR suburban rail.
- Southern end of Dwarka Expressway in Gurugram: connects to the NH-48 which in turn connects to the Western Peripheral Expressway, RRTS Delhi NCR regional rail, and Kherki Daula ISBT bus terminal. The WPE in turn connects to the Haryana Orbital Rail Corridor, Eastern Peripheral Expressway, Delhi–Mumbai Expressway, Delhi–Amritsar–Katra Expressway, Delhi–Faridabad Skyway and DND Flyway.
Future connectivity
- 11 Murti-INA-Vasant Kunj-Bandhwari-Gurugram Elevated Highway: The route from 11 Murti Circle, to INA Colony and Nelson Mandela Marg in Vasant Kunj in New Delhi to Gurugram-Faridabad Road will be upgraded to the elevated expressway. In addition to the existing NH-48 and Dwarka Expressway, it will serve as the third major highway between Delhi and Gurugram.
- Delhi–Jaipur SuperExpressway, is a greenfield expressway which is under construction of ₹6,530 crore 6-lane 195-km-long from Kherki Daula to Chandwaji runs parallel to western side of NH48. It cuts down Delhi–Jaipur distance by 40 km and travel time from 3–4 hours to 2 hours. It passes through Haryana and Rajasthan. In April 2023, the earthworks had already started and expected completion date is 2025.
- Gurugram Heli Hub: In FY2025-26 Haryana Budget, funds were allocated to develop 16-acre heliport off Dwarka Expressway in Sector 84 near Global Cit, which will provide direct helicopter rides to IGI Delhi Airport, Salasar Balaji Temple, Khatu Shyam Temple, Pitambari Mata Temple Pehowa, Chandigarh, and other regions.
Current status
- June 2025: The entire route of the expressway, from Kherki Daula to Shiv Murti at Mahipalpur, was completed and made operational in June 2025. There is plan to further extend this route by building 18 to 20 km long tunnel from Shiv Murti to Serai Kale Khan multi-model transport hub.