National Transmission System


The United Kingdom's National Transmission System is the network of gas pipelines that supply gas to about forty power stations and large industrial users from natural gas terminals situated on the coast, and to gas distribution companies that supply commercial and domestic users. It covers Great Britain, i.e. England, Wales and Scotland.

Ownership

The transmission network is owned by National Gas, which is owned by Macquarie Asset Management. Agreement was reached in July 2024 for Macquarie to buy National Grid’s final 20% stake, giving Macquarie full ownership in the first quarter of 2025.
The changing ownership of the NTS reflects developments and corporate changes in the UK's gas and energy industries.

Origins

The system originated in the construction during 1962–3 of the high-pressure methane pipeline from Canvey Island to Leeds. Imported liquefied natural gas from Algeria was turned into gas at the Canvey terminal and supplied to the pipeline, providing eight of the twelve area gas boards with access to natural gas. The gas was initially used to manufacture town gas, either as a feedstock in gas reforming processes or to enrich lean gases such as that produced by the Lurgi coal gasification process.
The pipeline was in diameter and operated at 1,000 pounds per square inch. The pipeline had of spur lines, supplying gas to area boards.
Area boardSupply toDiameter Length
North ThamesBromley/East Greenwich 'Tee'1415.5
North ThamesBromley102.5
North ThamesSlough
South EasternEast Greenwich123
SouthernReading849
EasternChelmsford1219.9
EasternHitchin87
EasternDunstable68.5
EasternWatford 122.1
West MidlandsColeshill1410.5
East MidlandsSheffield1210
North WesternManchester1424
North EasternLeeds128

The Gas Council was responsible for this £10 million co-operative scheme and the construction details were a joint effort of the distribution engineers of the area boards.
LNG had first been imported to Canvey from Louisiana in February 1959, and piped to Romford gasworks as feedstock to a reforming plant.

UK natural gas

Natural gas was discovered on the UK continental shelf in 1965 and production started in 1967. The development of offshore natural gas fields is shown in the following table. Shore terminals were built to receive, process, blend and distribute the gas.
FieldField typeLicensee or operatorDiscoveredFirst gas onshoreShore terminal
West SoleGasBPSeptember 1965March 1967Easington
LemanGasShell/Esso, Amoco/Gas Council, Arpet Group, MobilApril 1966August 1968Bacton
HewettGasPhillips Petroleum, Arpet groupOctober 1966July 1969Bacton
IndefatigableGasShell/Esso, Amoco/Gas CouncilJune 1966October 1971Bacton
VikingGasConoco/BNOCMay 1968July 1972Viking
RoughGasAmoco/Gas CouncilMay 1968October 1975Easington
FortiesOil + associated gasBPOctober 1970September 1977St Fergus
Frigg GasTotalEnergiesJune 1971September 1977St Fergus
Frigg GasTotalEnergiesMay 1972September 1977St Fergus
PiperOil + associated gasOccidental groupJanuary 1973November 1978St Fergus
TartanOil + associated gasTexacoDecember 1974January 1981St Fergus
BrentOil + associated gasShell/EssoJuly 19711982St Fergus
Morecambe BayGas + condensateHydrocarbons September 19741985Barrow

With the assured availability of natural gas, a government white paper on fuel policy in November 1967 proposed that natural gas should be immediately and more extensively exploited. The Gas Council and area boards began a ten-year programme to convert all users and appliances to operate on natural gas and consequently to discontinue the manufacture of town gas at local gasworks. In a pilot scheme, users on Canvey Island had been converted to natural gas in 1966.

Building the NTS

To exploit the availability of natural gas and to provide for more widespread distribution, construction began of a major new transmission network which became the National Transmission System.

Feeder pipelines – England

Gas from the West Sole field was first dispatched from the Easington terminal on the Yorkshire coast in July 1967, via Feeder No. 1 across the Humber to the East Midland Gas Board's gasworks at Killingholme. It was used to enrich low calorific value manufactured gas. Feeder No. 1 was extended to Totley near Sheffield where it connected to the 18-inch methane pipeline. UK natural gas first entered the NTS in July 1968.
Feeder lines from the North Sea gas terminals to the spine of the NTS were laid and brought into use as the shore terminals were constructed.
Feeder No.DiameterLengthFromToOperational
1Easington terminalScunthorpe and Totley near Sheffield, where it connected to the original methane pipeline.July 1967/ July 1968
2Bacton terminalBrisley, Eye, Peterborough and Churchover near Rugby, where it connected to the original methane pipeline.August 1968
336-inchBacton terminalRoudham Heath, Cambridge, Peters Green, Whitwell near Hitchin, where it connected to the original methane pipeline.October 1969
436-inchBacton terminalGreat Ryburgh, King's Lynn, Audley and Alrewas near Lichfield.Autumn 1970
536-inchBacton terminalYelverton, Diss, Stowmarket, Braintree, Chelmsford and Horndon, where it connected to the original methane pipelineAutumn 1971
6PaullPickering, Westwood and Little Burden near DarlingtonAutumn 1971
736-inchWisbechGosberton, Hatton, Old Warden, Tydd St Giles and Scunthorpe1972
830-inchFormer Viking terminalHattonJuly 1972

The No. 6 feeder runs via Pickering which received gas from a treatment plant for the onshore Lockton gas field.

Feeder pipelines – Scotland

North Sea gas first reached Scotland in Spring 1970 at Coldstream via an extension of the Leeds-Newcastle pipeline. This pipeline was then extended to Glenmavis near Coatbridge Lanarkshire where a natural gas liquefication plant was constructed.
A major set of pipelines were constructed in Scotland in preparation for arrival of gas from the Frigg gas field in 1977. From the St Fergus terminal in Scotland, two pipelines were laid via Bathgate to Partington and Bishop Auckland to connect to the NTS in England, a total pipeline length of. These lines were commissioned in 1976 and cost £140 million. Initially they carried gas from southern England into Scotland until the Frigg field began production via St Fergus in September 1977. Compressor stations are provided at intervals along the pipelines. A third 36-inch pipeline from St Fergus was completed in 1978, and a fourth pipeline in 1982.

Growth of the NTS

The NTS was extended from Leeds to Newcastle upon Tyne in early 1969. This line was extended to Coldstream in spring 1970 and then to Glenmavis, near Coatbridge, Lanarkshire.
The Wales Gas Board received natural gas supplies in 1969 through a 24-inch line from Churchover to Swansea via Wormington. North Wales was also connected in 1969 via a 24-inch/18-inch pipeline from Audley Cheshire to Maelor near Wrexham.
The South Western Gas Board received natural gas at the end of 1970 from a 24-inch/20-inch pipeline from Wormington to Exeter.
A 30-inch/24-inch extension of Feeder No. 3 runs to the west of London via Slough to Mogador, Surrey, and was commissioned in 1970. An extension of Feeder No. 5 runs from Horndon-on-the Hill, crosses the Thames at Tilbury and runs via Shorne to connect to Mogador, completing the South London ring main which became operational in early 1972.
In addition to these distribution pipelines, in 1971 the area boards began to supply natural gas directly to major consumers. For example, a 24-inch 17 mile 'spine' pipeline was constructed to ICI Ltd at Billingham, and the West Midlands Gas Board laid six similar 'spine' mains into industrial districts of Birmingham and the Black Country.
Most of the NTS was built from the late 1960s to the early 1980s.
YearsNTS mileageOperational gas terminalsCompressor stations
1966/7320Canvey0
1968/9688Canvey Easington Bacton0
1970/11898Canvey Easington Bacton1
1972/32199Canvey Easington Bacton Theddlethorpe4
1974/52308Canvey Easington Bacton Theddlethorpe9
1976/72915Canvey Easington Bacton Theddlethorpe St. Fergus10
1978/93047Canvey Easington Bacton Theddlethorpe St. Fergus11
19833200Canvey Easington Bacton Theddlethorpe St. Fergus14

Later feeder mains not described above include:
Feeder No.FromToYear commissioned
9EasingtonEast Ilsley1983–86
9BrocklesbyStallingborough
10BathgateGlenmavis
10ThruntonSaltwick
11BathgateLongtown
12KirriemuirLongtown via Bathgate
12St FergusAberdeen
14BarringtonKenn South
15LongtownWarburton1984
16BarrowLupton1983
16Stapleford TawneyStanford Le Hope
17TheddlethorpeHatton1988
18PeterboroughCambridge 1988–94
18Isle of GrainGravesend2008
18Matching GreenRye House
18Matching GreenTilbury1990
18St NeotsLittle Barford
19EasingtonPaull1991
20IlchesterChoakford1989
21MawdesleyAlrewas1992–2001
21CarnforthBurscough1992
21ElworthDeeside power station1994
22Goxhill and HattonPeterborough1993
23ChurchoverHoneybourne1998–2001
23PeterstowGilwern2000
23WormingtonCorse2000
24St FergusLochside2001
24EasingtonPaull2010
24HattonSilk Willoughby2001
25Bridge FarmMickle Trafford2001
26HuntingdonSteppingley2001
27BactonKing's Lynn2003
27CambridgeMatching Green2002
28HerbrandstonCorse2007
29EasingtonNether Kellett2006–08

The NTS now comprises over 7,600 km of welded steel gas pipelines. The Canvey to Leeds line is no longer part of the NTS.