National Highway 10 (India, old numbering)
National Highway 10 was a National Highway, length, in North India that originated at Delhi and ended at the town of Fazilka in Punjab near the Indo-Pak Border.
New numbering
Due to Rationalization of Numbering Systems of National Highways by Ministry of Road Transport and Highways, old NH 10 has been renumbered as follows.- Fazilka - Abohar - Malout section is part of new National Highway No. 7
- Malout - Sirsa - Hisar - Delhi section is part of new National Highway No. 9
Upgrades
Four-laning between Hissar and Rohtak
As of 2016 June, a special purpose vehicle, Rohtak-Hissar Tollway Pvt Ltd, completed the widening of the stretch from Hissar to Rohtak to four lanes. The concession period for the project, including the construction period, is 22 years.The National Highways Authority of India's National Highways Development Project NHAI NHDP Phase-3 project has acquired additional 591.84 hectares of land for road widening and building:
- 2 toll road plazas:
- * Near Hansi, towards Hisar
- * Between Maham and Rohtak
- 3 overbridges:
- * Hisar-Jakhal Railway line near Hisar
- * Foot over-bridge near Hisar Cantt.)
- * Jind-Rohtak railway line near Rohtak
- 13 underpasses
- * 6 pedestrian underpasses in the connecting villages
- * 7 vehicular underpasses in the connecting villages
- 5 bypasses
- * Hansi bypass
- * Maham bypass
- * Kharkada bypass
- * Madina bypass
- * Rohtak South-West NH10 bypass across NH 71
Four-laning between Hisar to Sirsa and Dabwali">Mandi Dabwali">Dabwali
The project for widening Hisar-Sirsa-Dabwali segments in Haryana to four lanes on Build–operate–transfer toll road mode is on a design, built, finance, operate and transfer pattern with a concession period of 24 years including a 2.5 years construction period. The project was started in 2015. It also covers the following:- 1 railway over-bridge
- 10 flyovers
- 1 major bridges
- 11 minor bridge
- Sirsa bypass