National Highways Development Project


The National Highways Development Project was a project of four laning of existing national highways and six laning of selected major national highways of India. The project was started in 1998 under the leadership of Prime Minister, Atal Bihari Vajpayee. National Highways account for only about 2% of the total length of roads, but carry about 40% of the total traffic across the length and breadth of the country. This project is managed by the National Highways Authority of India under the Ministry of Road, Transport and Highways. The NHDP represents 49,260 km of roads and highways work and construction in order to boost economic development of the country. The government has planned to end the NHDP program in early 2018 and subsume the ongoing projects under a larger Bharatmala project.

Project phases

The project is composed of the following phases:
  • Phase I: The Golden Quadrilateral connecting the four major cities of Delhi, Mumbai, Chennai and Kolkata. This project, connecting four metro cities, is. Total cost of the project is Rs.300 billion, funded largely by the government’s special petroleum product tax revenues and government borrowing. In January 2012, India announced the four-lane GQ highway network as complete.
  • Phase II: North-South and East-West corridors comprising national highways connecting four extreme points of the country. The North–South and East–West Corridor connecting Srinagar in the north to Kanyakumari in the south, including spur from Salem to Kanyakumari and Silchar in the east to Porbandar in the west. Total length of the network is . As of 31 October 2016, 90.99% of the project had been completed, 5.47% of the project work is under Implementation and 3.52% of the total length is left. It also includes Port connectivity and other projects —. The final completion date to 28 February 2009 at a cost of Rs.350 billion, with funding similar to Phase I.
  • Phase III: The government on 12 April 2007 approved NHDP-III to upgrade of national highways on a Build, Operate and Transfer basis, which takes into account high-density traffic, connectivity of state capitals via NHDP Phase I and II, and connectivity to centres of economic importance.
  • Phase IV: The government on 18 June 2008 approved widening of highway that were not part of Phase I, II, or III. Phase IV will convert existing single-lane highways into two lanes with paved shoulders.
  • Phase V: As road traffic increases over time, a number of four-lane highways will need to be upgraded/expanded to six lanes. On 5 October 2006 the government approved for upgrade of about of four-lane roads.
  • Phase VI: The government is working on constructing expressways that would connect major commercial and industrial townships. It has already identified of Vadodara -Mumbai section that would connect to the existing Vadodara -Ahmedabad section. The World Bank is studying this project. The project will be funded on BOT basis. The Expressway between Chennai—Bangalore and Expressway between Kolkata—Dhanbad has been identified and feasibility study and DPR contract has been awarded by NHAI.
  • Phase VII: This phase calls for improvements to city road networks by adding ring roads to enable easier connectivity with national highways to important cities. In addition, improvements will be made to stretches of national highways that require additional flyovers and bypasses given population and housing growth along the highways and increasing traffic. The government has planned to invest Rs. 16,680 Cr for this phase. The long Chennai Port—Maduravoyal Elevated Expressway is being executed under this phase.
NHDP PhaseParticularsLengthIndicative cost ₹
NHDP-I & IIBalance work of GQ and EW-NS corridors42,000
NHDP-III4-laning55,000
NHDP-IV2-laning25,000
NHDP-V6-laning of selected stretches17,500
NHDP-VIDevelopment of expressways15,000
NHDP-VIIRing Roads, Bypasses, Grade Separators, Service Roads etc.15,000
Total1,690,500

Note: 1 crore= 10 million
PriorityNHDP PhaseLength StatusApprovalCompletion Target
1Phase ICompleteDecember 2000December 2006
2Phase IIAward in progressDecember 2003December 2009
3Phase III AAlready identifiedMarch 2005December 2009
4Phase V5700 km of GQ + 800 km to be identifiedNovember 2005December 2012
5Phase III BAlready identifiedMarch 2006December 2012
6Phase VII ARing roads to be identifiedDecember 2006December 2012
7Phase IV ATo be identifiedDecember 2006December 2012
8Phase VII BRing roads to be identifiedDecember 2007December 2013
9Phase IV BTo be identifiedDecember 2007December 2013
10Phase VI AAlready identifiedDecember 2007December 2014
11Phase VII CRing roads to be identifiedDecember 2008December 2014
12Phase IV CTo be identifiedDecember 2008December 2014
13Phase VI BTo be identifiedDecember 2008December 2015
14Phase IV DTo be identifiedDecember 2009December 2015

Status from NHAI website

National Highways Development Project is being implemented in all phases. The present phases are improving more than 49,260 km of arterial routes of NH network to international standards. The project-wise details of NHDP all phases is below as of 18 May 2021:

Subsummation in Bharatmala project

National Highway Development Project will close by first half of 2018, with the launch of Bharatmala project. 10,000 km of highway construction left under NHDP will be merged with Phase I of the Bharatmala.