Tagansko-Krasnopresnenskaya line
The Tagansko-Krasnopresnenskaya line formerly Zhdanovsko-Krasnopresnenskaya is the busiest line of the Moscow Metro system in Moscow, Russia. Built in 1966–1975 and extended in 2013–15, it cuts Moscow on a northwest-southeast axis and contains 23 stations.
History
The Tagansko-Krasnopresnenskaya line is a classic example of Soviet urban planning, sometimes referred to as the seventh stage of the Moscow Metro. Construction began in the early 1960s, and in 1966 the first complete segment was opened. In the practice of Moscow radial line openings, it began at the ring and left through to the new housing massifs on the southeast of Moscow, originally called the Zhdanovskaya line. The construction of the new radius was designed to maximize the efficiency of it with the land-based transportation. All the stations were built on major transport links and the stations Tekstilshchiki and Vykhino were integrated into a single transport complex with the railroad stations.The first segment of the line, originally constructed in 1966, begins at the Taganka Square and follows Volgogradsky avenue through the neighbourhoods of Pechatniki, Kuzminki and Tekstilshchiki. On its final stretch, the line deviates from the Volgogradsky prospect and stretches northeast onto the Ryazansky avenue, terminating at a combined cross-platform transfer to Vykhino railway station. The newly opened radial line was named Zhdanovskaya by the name of its southeastern terminus.
As the line past through the areas with highly complex soil geology, the builders had to use cut-and-cover method for tunnel construction to cut down the costs. In some cases, specifically on the segment between Volgogradsky prospekt and Tekstilshchiki stations and on the approach to Vykhnino station, the track was brought up to the surface in lieu of constructing underground tunnels in the unstable soil.
In a similar logic that was used when building the Kaluzhsko-Rizhskaya line, it was decided to postpone the construction of central section in favour of building the new radial line. However after the opening of the new Zhdanovskaya line in late 1966, the increasing passenger traffic between it and the former Kaluzhskaya line put too much pressure the capacity of the stretch of Koltsevaya line between Oktyabrskaya and Taganskaya that connected the two radii. It was decided to extend both lines northwards and have them meet close to the Kremlin, which was realized in 1970 when Kitay-Gorod, the first cross-platform station in Moscow metro, was constructed.
The construction of the northwestern Krasnopresnensky radius was undertaken under exceptionally challenging conditions. Designed to provide access to the new residential areas of northwestern Moscow, the construction of the northwestern radius faced numerous obstacles, including dense urban regions, underground fortifications, and communication lines. Starting at the intersection with Koltsevaya line at Krasnopresnenskaya, where the only deep-level station was located, the route was to follow Krasnaya Presnya Street before turning north along 1905 Goda Street, diving under the railway to continue along Khoroshevskoye shosse and crossing another railway to terminate in Shchukino district.
However, right from the beginning, the progress in the construction was hindered by the need to dig a tunnel beneath the sorting yard of the Belorussky Rail Terminal, which consisted of 27 individual railway tracks. The boring of the final section between Polezhayevskaya and Oktyabrskoye Pole also presented additional challenges, as the soil had a heavy concentration loose sand typically used to elevate railways. These peroblems made conventional boring methods impossible. Instead, builders had to first stabilize the soil using chemical adhesives to prevent collapse when drained. To ensure safety, a horizontal platform had to be installed above the tunnel shield, which operated at maximum pressure without temporary reinforcements in the sand. In the end, after its opening in 1972, the Krasnopresnensky radius helped to relive major transport arteries and traffic congestion and provided a crucial link to a railway platform via Begovaya station just like its southern counterpart.
As four of the five stations were sub-surface, an attempt was made to modernise the existing centipede design. The volume of the station space was increased, and to support the larger roof, the size of the pillars was raised, but so was their spacing, from. In the end, the number of columns per row was reduced from 40 to 26 to streamline the design. The new design became very widespread in the rest of the system. The architecture also made a comeback with new stations. For the first time in nearly 20 years, marble was used to decorate the station walls.
Shortly after the Krasnopresnensky radius was commenced in 1972, the construction of the line's two final segments began – the crucial central link and the norther extension to Tushino. The former was built with two deep level column stations, where one of the centrepieces was the increased diameter of the central vault of. After opening in 1975, these stations later became crucial transfer hubs, linking the Zhdanovsko-Krasnopresnenskaya line to Gorkovsko-Zamoskvoretskaya, Serpukhovsko-Timiryazevskaya and Kirovsko-Frunzenskaya lines.
The latter section, which was set to run further west through the Shchukino district and then turn north towards the end Severnoye Tushino, encountered a significant difficulty when building under the Moscow Canal. To avoid flooding, boring had to be done in the winter, and a three-metre thick plane of ice had to be placed on the canal bed. Opened in 1975, the line stretched into the northern districts of Shchukino and Tushino, including another transfer to a railway station at Tushinskaya. The station Skhodnenskaya was another pioneering design, as it was built using the single-vault technology initially developed for the Kharkiv Metro; this technology, with some modifications, was later widely implemented for other construction projects both in Moscow metro and elsewhere in Soviet Union. One station on this stretch was left unfinished because of the lack of need for it and remained derelict for several decades. The unfinished ghost station was finally completed and inaugurated forty years later, in August 2014 under the name Spartak.
Because the line is the busiest on the system, there are significant problems that overstretch its capabilities. In particular is the station Vykhino, which was built with too small a capacity to handle the congestion, making it the busiest on the system. In 2004 a severe reconstruction increased the area of the platforms and gave the station a desirable facelift. Nonetheless, that was insufficient to solve the problem, and in 2013 the line was extended to the south-eastern districts of Moscow outside the Ring Road with the opening of Zhulebino and Lermontovsky Prospekt stations. By September 2015, the line had reached a neighboring city of Kotelniki with the opening of an eponymous metro station and the line's new southeastern terminus there on 21 September.
Rolling stock
The line is served by two depots, Planernoe and Vykhino. Respectively 36 and 34 eight carriage trains are assigned to them. Most of the trains are Ezh3 and Em-508T models which were received new from 1974, currently all of the trains were modernized between 2003 and 2011 extending the service life by another 15 years. From 2012 to 2017, the line was also served by 10 81-717/714 trains, which were transferred here from other lines. As of 2019 the line is only served by Ezh and 81-765/766/767 trains.Mocsow department of transportation entrusted TMH to build different rolling stocks for Moscow metro. THM factory in Mytishchi commenced production of the 81-765, 81-766, and 81-767 cars. In April 2017, they were introduced on Line 7.THM is also contracted to the maintenance of cars for 30 years.
Subway car types used on the line over the years:
| Type | Dates |
| Series E | 1966–1974 |
| Series Ezh/Em-508/Em-509 | 1971–1980 |
| Series Ezh3 | 1974–2020 |
| Series 81-717 | 2012–2017 |
| Series 81-760/761 | 2015–2018 |
| Series 81-765/766/767 | 2017–present |