Line 3 (Harbin Metro)


Line 3 of the Harbin Metro is a rapid transit ring line in Harbin.

History

Phase 1

The first phase of the line, from to, commenced operations on 26 January 2017. It is 5.45 km long with 5 stations, all of which are underground.
Harbindajie station opened as an infill station on June 16, 2017. Harbindajie station renamed to station on March 20, 2019.

Phase 2 (initial section)

The section from to, and the section from to opened on November 26, 2021.

Phase 2 (remaining section)

The remaining section, comprising 9 stations, opened on 25 November 2024.

Stations

;Legend:
- Stations in operation
- Under construction, opening in 2023 & 2024

Rolling stock

Services on the line are provided by six-car Type B trains, which have a total capacity of 1440. These trains are the same as those which run on Line 1.