Hongping Pumped Storage Power Station


The Hongping Pumped Storage Power Station is a 1,200 MW pumped-storage hydroelectric power station located at about northwest of Hongping in Jing'an County of Jiangxi Province, China. It was the first pumped-storage hydroelectric power station constructed in Jiangxi.
It is operated by Jiangxi Hongping Pumped Storage Ltd.

Construction

The project was split into two phases, with first phase resulting in 1,200MW of installed capacity. Construction on the project's first phase began in June 2010. The first generator was commissioned in June 2014 and by December 2016, all the four 300MW generators were commissioned, marking the end of the first phase.
In 2021, a feasibility study on the second phase of the project was begun. The study completed in November 2022 and the second phase project, which plans to add an additional total capacity of 1,800 MW to the power station, was deemed feasible. When fully operational, the power station will have an installed capacity of 3,000 MW.

Reservoirs

The lower reservoir is created by a tall and long roller-compacted concrete gravity dam on the Hebei River. It can withhold up to of water, of which can be pumped to the upper reservoir. The upper reservoir is created by a tall and long concrete gravity dam. It can withhold up to of water, of which can be used for power production. Water from the upper reservoir is sent to the underground power station down near the lower reservoir through two long headrace/penstock pipes. The power station contains four 300 MW Francis pump turbines. The difference in elevation between the upper and lower reservoir affords a hydraulic head of.