Haiyang Nuclear Power Plant
Haiyang Nuclear Power Plant is a nuclear power plant in Haiyang, Shandong province, China. It is the second site to house AP1000 units, after the Sanmen Nuclear Power Station.
History
Groundbreaking happened one month ahead of schedule on July 30, 2008. Construction of the first unit began in September 2009. Civil construction of Unit 1 was completed 29 March 2013. Fuel loading at Haiyang 1 began on June 22, 2018. First grid connection was on 17 August 2018.Unit 1 began commercial operation on 22 October 2018.
Construction of unit 2 started in June 2010, at that time the fourth Chinese AP1000 project together with the two units of the Sanmen NPP. Commercial operation began in January 2019, after having completed a full-power test run for a week. Both units will provide together about 20 TWh of electricity to the grid of Shandong province.
On July 7, 2022, construction began on unit 3 after authorization had been granted.