Golden Hills Wind Project is a electricity generating wind farm facility in Sherman County, Oregon. The original plan in 2009 by BP Alternative Energy was to generate a peak of 400 megawatts, with an average of 133 MW of wind power across using up to 267 wind turbines. A new plan with 51 turbines generating 200 MW was expected to begin construction in 2021. It began operation in 2022.