Eastern Kanagawa Rail Link


The Eastern Kanagawa Rail Link is a strategic railway project in Japan to improve the railway network connectivity and passenger convenience between the eastern Kanagawa Prefecture and Tokyo Metropolis, as well as access to Tōkaidō Shinkansen at Shin-Yokohama Station.
The new infrastructures of this project are constructed and owned by the Japan Railway Construction, Transport and Technology Agency, which is an Independent Administrative Institution governed by the Ministry of Land, Infrastructure, Transport and Tourism, while operation is divided between Sagami Railway, JR East and Tōkyū Railways.

Services

In its finalized form, this railway project comprises 2 major portions:

Sōtetsu–JR Link Line

Sōtetsu–JR Link Line : Connecting Sōtetsu and JR East by a new railroad, Sōtetsu Shin-yokohama Line, constructed between and for entering the Tōkaidō Freight Line. This enables through service from to via,, and alongside the Yamanote Line. It has entered service since 30 November 2019.
Regarding passenger information, northbound services on the Sōtetsu–JR Link Line continue through to the Saikyō Line via Ōsaki, where they interline with the Rinkai Line, which also offers northbound through service onto the Saikyō Line. It shares tracks with the Shōnan–Shinjuku Line between and Ikebukuro, and with the Yokosuka Line between Musashi-Kosugi and.

Sōtetsu–Tōkyū Link Line

Sōtetsu–Tōkyū Link Line : Connecting Sōtetsu and Tōkyū Railways with a new railroad, which is divided into Sōtetsu Shin-yokohama Line and Tōkyū Shin-yokohama Line, constructed between Hazawa yokohama-kokudai and via Shin-yokohama.
Sōtetsu–Tōkyū Shin-yokohama Station serves as an operational boundary between Sōtetsu and Tōkyū. This enables through services from Ebina or to Shibuya and . Furthermore, the through-running is possible via Fukutoshin Line to, or via Namboku Line to . This has entered service since 18 March 2023.

Background

Similar railway plans which proposed to connect different existing passenger railways for through service around the eastern Kanagawa regions had been devised before the Eastern Kanagawa Rail Link. In 1983, a team of experts of civil engineering, environmental management, railway, etc. proposed numerous public transit plans in a study of Kanagawa transportation infrastructure provision. Among those plans were new railroads which would connect Sōtetsu and/or with the Tōkaidō Freight Line for Haneda Airport, as well as, Yokohama-Hazawa, Shin-yokohama and to allow through service between Sōtetsu and Tōkyū.
The project which is codenamed the "Eastern Kanagawa Rail Link" began its infancy from the in January 2000. In the initial proposal, a new railroad would connect of Sōtetsu to Ōkurayama of Tōkyū Railways via Shin-yokohama. Originally Sōtetsu, which was only operating within Kanagawa Prefecture and did not have any through service with other railway operators, was not interested in this plan, because a through service via Shin-yokohama would divert passengers away from its hub terminus. However, as the population decline led to ridership drop of Sōtetsu, the rail company became more favorable towards the plan which improves connectivity with the Tokyo Metropolis and Saitama Prefecture. In September 2004, the Sōtetsu–JR Link Line plan was formally announced which would provide a more direct access to Shinjuku, Tokyo from areas served by Sōtetsu between and.
In May 2005, the was passed by the parliament of Japan and went into effect on 1 August 2005 with the aim of encouraging many different railway operators of major metropolitan areas of Japan to provide better and more convenient passenger experience via new railroads which would enable through services between different operators. The new law also stipulates a model which separate the construction/maintenance and operation of infrastructure to different entities.
Under this new law, in June 2006, the Ministry of Land, Infrastructure, Transport and Tourism approved the initial maintenance and operation plans of the Sōtetsu–JR Link Line and Sōtetsu–Tōkyū Link Line submitted by the Japan Railway Construction, Transport and Technology Agency. The SJLL was green-lighted on 21 November 2006 and STLL on 11 April 2007.

Financing

The Eastern Kanagawa Rail Link project was funded one-third from the national coffer, one-third from the local governments, and one-third from private loan. The JRTT coordinated the construction of this project, owns the completed rail infrastructure, and is responsible for its maintenance. Sōtetsu and Tōkyū collect the revenues from operating the railways owned by JRTT, and then they pay JRTT a portion of those revenues for maintenance and loan reimbursement for this project.
Both Sōtetsu and Tōkyū Railways applied to the Ministry of Land, Infrastructure, Transport and Tourism for an additional fare charge of using the new railways. This was due to the high cost of construction and the drop in estimated ridership from the initial projection, resulting from the COVID-19 pandemic.