Electricity billing in the UK
In the United Kingdom, an electricity supplier is a retailer of electricity. For each supply point the supplier has to pay the various costs of transmission, distribution, meter operation, data collection, tax etc. The supplier then adds in energy costs and the supplier's own charge. Regulation of the charging of customers is covered by the industry regulator Ofgem.
MSP, GSP and NBP
MSP kWh is the amount of electricity consumed at the 'meter supply point', which is the customer's meter. GSP kWh is obtained by multiplying the MSP kWh by the Line Loss Factor to include the amount of electricity lost when it is conducted through the distribution network, from the 'grid supply point' to the customer's meter. Some kWh elements of the bill are charged at MSP and some at GSP. The LLF for a particular supply depends on the distribution network operator and the supply's characteristics and the time and date. Some electricity bills may refer to GSP charges as being at a Notional Balancing Point - not to be confused with the National Balancing Point (NBP) of the gas network - and may also include losses at transmission level.The bill
The consumer pays the supplier according to an agreed tariff, or a default rate known as the "standard variable tariff". The tariff may include pass-through costs, which are amounts charged to the energy supplier and then "passed through" directly to the consumer.Transmission charges
Transmission charges, known as "Transmission Network Use of System", are paid to National Grid to cover the expense of running the grid. The charge is calculated annually using the TRIAD method for large levels of demand, or based on usage between 4pm and 7pm for smaller demand levels.RCRC
Residual Cashflow Reallocation Cashflow, also known as the 'beer fund', is the net remainder of Balancing & Settlement Code Trading Charges for a given half-hour, which is payable to or by Trading Parties based on their market share of energy volume. These Trading Charges consist of:- Information Imbalance Charges – A charge per MWh on the difference between a BM Unit's Metered Volume and its Expected Metered Volume. Due to a zero price, this charge is always zero
- System Operator BM Cashflow – A cashflow payable to or by the System Operator depending on whether BM Unit Cashflow plus Non-Delivery Charges is positive or negative, and is intended to keep BSCCo cash neutral
- Non-Delivery Charges – A charge levied on the Lead Parties of BM Units that fail to satisfy a Bid-Offer Acceptance on the Balancing Mechanism
- BM Unit Cashflow – A cashflow payable to or by Lead Parties of BM Units with Bid-Offer Acceptances
- Imbalance Charges – A cashflow payable to or by Trading Parties with an Imbalance Volume
Distribution charges
The distribution charges, known as the "distribution use of system" charges, are paid to suppliers and passed on to the distribution network operator on whose network the meter point is located. The charges cover:Availability
Supply availability, otherwise known as "supply capacity" or "kVA", if represented by its measured units, is the maximum kVA power allowed for a particular supply in a particular network and is set before the supply is energised. It is a figure agreed between the consumer and the supplier at the start of the contract. This supply availability is charged for every month, in effect as a standing charge, despite the fact that the maximum demand recorded in the month may be lower. If the kVA supply availability figure is exceeded by the value of the measured monthly maximum demand, also in kVA for this purpose, the higher figure of kVA from the maximum demand may be charged instead of the supply capacity. The new elevated kVA charge figure may stay as the chargeable figure for twelve months depending on the electricity distribution area. This can cause temporary unnecessary high billing, as if a penalty, if the breach was avoidable. Alternatively, the capacity charge can just return to the original availability figure in the subsequent month's bill. Determining the correct capacity figure to allow for the maximum demand required for the supply can be a fine judgement if the capacity charge is to be kept to a minimum, and vigilance of maximum demand and efforts to keep the power demand lower than the agreed capacity can be required to avoid triggering a higher capacity charge during the contract.Unit rates
Unit rates are split into 3 time periods: Red, Amber and Green. Costs and periods vary per distribution company. The chart below shows the applicable time bands for each company.| DNO | Band | Weekday | Weekend |
| National Grid Electricity Distribution – Midlands | Red | 16:00 – 19:00 | |
| National Grid Electricity Distribution – Midlands | Amber | 07:30 – 16:00 & 19:00 – 21:00 | |
| National Grid Electricity Distribution – Midlands | Green | 00:00 – 07:30 & 21:00 – 24:00 | all day |
| National Grid Electricity Distribution – South Wales | Red | 17:00 – 19:30 | |
| National Grid Electricity Distribution – South Wales | Amber | 07:30 – 17:00 & 19:30 – 22:00 | 12:00 – 13:00 & 16:00 – 21:00 |
| National Grid Electricity Distribution – South Wales | Green | 00:00 – 07:30 & 22:00 – 24:00 | 00:00 – 12:00 & 13:00 – 16:00 & 21:00 – 24:00 |
| National Grid Electricity Distribution - South West | Red | 17:00 – 19:00 | |
| National Grid Electricity Distribution - South West | Amber | 07:30 – 17:00 & 19:00 – 21:30 | 16:30 – 19:30 |
| National Grid Electricity Distribution - South West | Green | 00:00 – 7:30 & 21:30 – 24:00 | 00:00 – 16:30 & 19:30 – 24:00 |
| Northern Powergrid - Northeast & Yorkshire | Red | 16:00 – 19:30 | |
| Northern Powergrid - Northeast & Yorkshire | Amber | 08:00 – 16:00 & 19:30 – 22:00 | |
| Northern Powergrid - Northeast & Yorkshire | Green | 00:00 – 08:00 & 22:00 – 24:00 | all day |
| UK Power Networks - London | Red | 11:00 – 14:00 & 16:00 – 19:00 | |
| UK Power Networks - London | Amber | 07:00 – 11:00 & 14:00 – 16:00 & 19:00 – 23:00 | |
| UK Power Networks - London | Green | 00:00 – 07:00 & 23:00 – 24:00 | all day |
| UK Power Networks - Eastern and South Eastern | Red | 16:00 – 19:00 | |
| UK Power Networks - Eastern and South Eastern | Amber | 07:00 – 16:00 & 19:00 – 23:00 | |
| UK Power Networks - Eastern and South Eastern | Green | 00:00 – 07:00 & 23:00 – 24:00 | all day |
| Electricity North West | Red | 16:00 – 19:00 | |
| Electricity North West | Amber | 09:00 – 16:00 & 19:00 – 20:30 | 16:00 – 19:00 |
| Electricity North West | Green | 00:00 – 09:00 & 20:30 – 24:00 | 00:00 – 16:00 & 19:00 – 24:00 |
| Scottish and Southern Electricity Networks - Scottish Hydro | Red | 16:00 – 19:00 | |
| Scottish and Southern Electricity Networks - Scottish Hydro | Amber | 07:00 – 16:00 & 19:00 – 21:00 | 12:00 – 20:00 |
| Scottish and Southern Electricity Networks - Scottish Hydro | Green | 00:00 – 07:00 & 21:00 – 24:00 | 00:00 – 12:00 & 20:00 – 24:00 |
| Scottish and Southern Electricity Networks - Southern Electric | Red | 16:30 – 19:30 | |
| Scottish and Southern Electricity Networks - Southern Electric | Amber | 07:00 – 16:30 & 19:30 – 22:00 | 09:30 - 21:30 |
| Scottish and Southern Electricity Networks - Southern Electric | Green | 00:00 – 07:00 & 22:00 – 24:00 | 00:00 - 09:30 & 21:30 - 24:00 |
| SP Energy Networks - Manweb and ScottishPower | Red | 16:30 – 19:30 | |
| SP Energy Networks - Manweb and ScottishPower | Amber | 08:00 – 16:30 & 19:30 – 22:30 | 16:00 – 20:00 |
| SP Energy Networks - Manweb and ScottishPower | Green | 00:00 – 08:00 & 22:30 – 24:00 | 00:00 – 16:00 & 20:00 – 24:00 |
Reactive power
Reactive power charges are applied to non-domestic electricity connections with half-hourly meters when the power factor falls below 0.95. Charges are based on the volume of excess reactive energy consumed below this threshold.Fixed charge
The fixed charge is in units of pence / MPAN / day.New DUoS charges came into effect on 1 April 2018 under a proposal known as DCP228. Green and amber rates were raised and red rates fell. Further changes came into effect in 2025, with:
- increases in capacity charges
- reductions in daily charges
- higher unit rates.