D11 motorway (Czech Republic)
The D11 motorway is a motorway in the Czech Republic. It is part of European route E67 Via Baltica from Prague in the Czech Republic, to Helsinki in Finland, passing towns and cities in Poland, Lithuania, Latvia and Estonia.
Three lanes in each direction are planned by 2025 between Prague and Jirny and to Poděbrady after 2025. Around Hradec Králové, the D11 runs in parallel with the D35.
History
Plans to build a highway connecting Prague and Hradec Králové date from 1938. Construction began in 1978, with sections 1101 and 1102/I put into operation in October 1984. The second oldest section, 1102/II was put into operation a year later, in October 1985.In 2009, the connecting section of the D35 motorway Sedlice - Opatovice nad Labem was put into operation. This significantly accelerated the connection to Pardubice and the southern parts of Hradec Králové.
In 2017, the motorway was finally brought to Hradec Králové. In 2018 and 2019, there was an expansion to 6 lanes between Horní Počernice and Jirny, but only four lanes are still in use.
Sections between Hradec Králové - Smiřice and Smiřice - Jaroměř, which construction started in 2018, were opened in December 2021.
Future plans
As the [Expressway Expressway S3 (Poland)|S3 (Poland)|S3] expressway connecting the Polish side was finished before the Czech D11, further postponement of completion of the motorway to the Polish border is undesirable. Almost all the land for section 1109 has already been purchased. Construction was originally scheduled to start at the end of 2023, and the contractor was selected in November 2023. However, a month later, an objection was filed against the selection of the most advantageous bid. This final section is yet to be started, with completion expected in 2027 at earliest.Section 1108 Jaroměř – Trutnov; a segment is planned. The construction should commence in 2025, in order to be put into operation in time for 2028.
With the completion of the Polish S3, and after completion of the border section of D11 and the transfer of international traffic for E65 and E67 from Harrachov and Náchod to Královec, congestion is expected on road 37.