Bankside at Colliers Yard


Bankside at Colliers Yard is a residential high-rise building in the Greengate area of Salford, England. At and 43 storeys, it is the third-tallest building in Salford and the 15th-tallest in Greater Manchester as of January 2026. It was designed by Denton Corker Marshall.
The building is part of developer Renaker's Greengate masterplan called Colliers Yard, which consists of three adjacent towers, the others being Cortland which was completed in 2023, and Parkside which was granted planning permission in March 2023.

History

Planning

A hybrid planning application, which included the tower ultimately named Bankside at Colliers Yard, was submitted to Salford City Council in 2019, with reserved matters consent obtained in March 2022.

Construction

Construction of Bankside at Colliers Yard commenced in March 2022 and completed in 2025. The tower contains 444 apartments.