A2 autostrada (Poland)
The A2 motorway in Poland, officially named the Motorway of Freedom, is a motorway which runs from the Polish-German border, through Poznań and Łódź to Warsaw and, in the future, to the Polish-Belarusian border. It is a part of European route E30.
The motorway between the German border and Warsaw was constructed between 2001 and 2012. Most of the stretch from the border to Konin is tolled.
Eastwards from Warsaw, A2 is being gradually extended. The first segment of this section was the bypass of Mińsk Mazowiecki, which opened in August 2012. The second segment between Warsaw and Mińsk Mazowiecki was completed in 2020, followed by the section from Mińsk Mazowiecki to Siedlce completed in 2024. The section from Siedlce to Biała Podlaska is under construction and is planned to get completed by 2025. The section from Biała Podlaska to Małaszewicze Cargo Terminal is under tender, expected to be finished by 2029. The last segment to the Belarusian border is under design, but its planned construction has been postponed due to the Russian invasion of Ukraine.
A2 does not formally run through Warsaw itself, instead turning into expressway S2. The motorway also does not technically reach the border with Germany as its endpoint is marked near the Świecko interchange ca. away from the border, although the remaining section is also a dual-carriageway road mostly up to the motorway standard.
Route
| Motorway section | Length | Construction dates | Notes |
| 2009 – 2011 | opened 1 December 2011; toll motorway except for its westernmost fragment | ||
| Nowy Tomyśl – | 2001 – 2004 | opened 27 October 2004; toll motorway | |
| Poznań bypass | 2001 – 2003/2004 | opened 13 September 2003 and 27 October 2004; main part widened to 2x3 lanes in 2019, eastern part currently under reconstruction to 2x3 | |
| Poznań Wschód – Września | 2001 – 2003 | opened 27 November 2003; toll motorway | |
| Września – Golina | 1977 – 1985 | opened 9 October 1985; reconstructed 2001–2002; toll motorway since 2002 | |
| Golina – Modła | 1986 – 1988 | opened 10 November 1988; reconstructed 2001–2002 | |
| Modła – Stryków | 2004 – 2006 | opened 26 July 2006 | |
| Stryków – | 2008 | opened 22 December 2008; 2x3 lanes | |
| Łódź Północ – | 2010 – 2012 | opened to traffic in May and June 2012, the last parts of it one day before the opening ceremony of UEFA Euro 2012; fully completed in the fall of 2012; planned widening to 2x3 lanes from Łódź to Pruszków and 2x4 lanes from Pruszków to Konotopa | |
| Warsaw southern bypass | 2010 – 2013 2017 – 2021 | Expressway | |
| – Mińsk Mazowiecki | 2018 – 2020 | Opened on 14. August 2020, Lubelska interchange fully completely in 2021. | |
| Mińsk Mazowiecki - Kałuszyn | 2009 – 2012 | Opened 29 August 2012 | |
| Kałuszyn – | 2021 – 2024 | ||
| Siedlce Południe – | 2023 – 2025 | Opened 23 December 2025 | |
| Siedlce Wschód – | 2023 – 2026 | Under construction, planned to get opened in 2026. | |
| Biała Podlaska – Małaszewicze Cargo Terminal | 2026 – 2029 | Under tender. | |
| Małaszewicze – Kukuryki | postponed | Design ongoing. Planned construction of this section has been postponed as a result of the Russian invasion of Ukraine. |
History of construction
The first highway planned along part of this route was a Reichsautobahn initiated by Nazi Germany to connect Berlin with Poznań. The construction of this highway, accelerated after Poznań was incorporated into Germany following the Invasion of Poland in 1939, was interrupted by the war and never finished, but traces of its earthworks were clearly visible on satellite photographs for decades afterwards, especially between the border with Germany and Nowy Tomyśl. Most of these traces have now disappeared as the modern motorway was built largely following the same route. A short stretch of the uncompleted highway between the border and Rzepin was finished as a dual carriageway road after 1945, in effect forming an extension of the German A 12 highway. Except for this stretch, the construction work was not continued in the decades after the war.New plans to build the A2 motorway were seriously formulated in communist Poland in the 1970s, possibly with the goal of completing it in time for the Moscow Olympics in 1980. Because of the economic crisis which hit the country in the late 1970s and continued throughout the 1980s, only a section from Września to Konin was opened in the 1980s. Construction of another stretch was started and then abandoned, leaving an interesting ruin informally named Olimpijka, which was in turn demolished around 2010 when building of the motorway resumed.
Intensive construction of the motorway started only in 2001 after the fall of communism in Poland in 1989. Out of the planned total length of, have been completed. A section of about has been fully open since 2004. This section is a toll road, with the exception of a short stretch through Poznań which serves as that city's bypass. An additional section from Konin to Stryków near Łódź was opened on 26 July 2006. A short bypass of Stryków, consisting of a 2 km extension of the A2 and a provisional single carriageway section of the future A1 motorway, was opened in December 2008, to ease the heavy traffic in that town generated when the motorway reached it.
As of the winter of 2009/2010, the plan was to finish the whole section between the border with Germany and Warsaw by the spring of 2012, giving the Polish capital its first motorway connection to the European motorway network in time for the Euro 2012 football championships. That ambitious goal was jeopardized due to various difficulties encountered in finalizing the construction contracts and the delays that resulted. The section from Stryków to Warsaw was to be built in a public-private partnership, but the negotiations between the government and private companies interested in participating collapsed in February 2009 due to disputes over financing terms. It was then decided that this section of the motorway would be built using public funds alone. The new bidding process was started on 27 March, and the contracts for design and construction of the road were signed on 28 September. The section had been divided into 5 parts and so construction work began in 2010. The contractors were required to have the motorway open to traffic in time for Euro 2012. This goal was an ambitious one and ultimately proved challenging, given the possibility of unexpected delays during construction and the fact that the Chinese consortium abandoned the project less than a year later, so that new contractors had to be selected to replace it. The goal was to have this motorway stretch provisionally opened to traffic in time for Euro 2012, even if it is not fully completed, with various restrictions such as a lower speed limit to ensure safety. For a while it was not clear whether even this limited goal would be reached, but the motorway opened to traffic in June 2012 after very intensive construction work in the final few months.
In November 2011, construction of the stretch from the German border to Nowy Tomyśl had been completed. The road was opened to public traffic on 1 December. Toll plazas on this stretch of the highway weren't opened until May 2012 so use of the western section of the A2 was free of charge until then.
In May 2013, the interchange with the S3 was opened to traffic. First stretch is between the interchange with the A2 motorway and the Świebodzin North interchange. In June 2013, the S3 was extended further and opened to traffic to reach from the Świebodzin South interchange to the existing stretch of the S3 expressway at Sulechów. In July 2013, the elevated bypass of Świebodzin between the interchanges of Świebodzin North and Świebodzin South fully opened to traffic thus fully extending the S3 from Szczecin to Sulechów.
Guarantee scandal
After COVEC withdrew from completing its construction of the A2, Bank of China was to pay a performance guarantee to the Polish government's roads organization GDDKiA. However, with Export-Import Bank of China, they refused to pay this; only Deutsche Bank honored its obligations under the court decision.Plans
The eastern section from Warsaw to the border crossing with Belarus at Kukuryki near Brest, about in length, is largely under construction. The decision finalizing the route of this section was announced in December 2011, the exception having been a short section of A2 forming the bypass of Mińsk Mazowiecki which was constructed between August 2009 and August 2012. The section between Warsaw and Mińsk Mazowiecki was opened in 2020. The longest section from Mińsk Mazowiecki to Biała Podlaska is in realization and is planned to get completed by 2024. The last segment to the Belarusian border is under design.It is worth noting that the A2 motorway doesn't actually run through Warsaw, as the inhabitants of the districts through which it was to pass have successfully blocked its construction. This outcome was somewhat unusual, since the corridor for the motorway has been reserved by the city planners since the 1970s and kept free of construction. Instead, the traffic is rerouted through two express roads, of lower standard than the originally planned motorway. One of these roads runs along the originally planned motorway corridor. In the most affected area, the district of Ursynów, the express road runs in a tunnel, built at considerable expense.