Wynyard Walk


The Wynyard Walk is a pedestrian link and tunnel between Wynyard station and Barangaroo in the Sydney central business district. The walkway was officially opened on 20 September 2016. Wynyard Walk provides a quick and safe route and has increased the entry and exit capacity of Wynyard station to meet demand as Barangaroo is redeveloped. An estimated 20,000 pedestrians per hour can walk through the tunnel. In 2009, prior to construction of Barangaroo, the pedestrian tunnel was estimated to cost $100 million.
Under a 7-year agreement from 2023 onwards, the tunnel is branded as Westpac Walk for sponsorship reasons.

Construction

The project involved the construction of:
The construction contract was awarded to Thiess in September 2012. In early 2014, construction at the Western Portal was put on hold to allow archaeologists to work on the site to preserve significant European and indigenous artefacts unearthed during excavation.
On 19 October 2015, a new pedestrian bridge over Sussex Street was opened to provide a direct route into Barangaroo. Following completion of the walk on 20 September 2016, the plaza created between Sussex Street and the tunnel, was named Napoleon Plaza, to reflect the connection to Francis Girard, who was thought responsible for the naming of the nearby Napoleon Street and who whose flour mill and wharf were nearby.

Adjoining buildings

The Wynyard Walk connects pedestrians from Barangaroo through to Wynyard station - and continues through Wynyard Place and on to the Hunter Connection.
The thoroughfare to George Street was rebuilt as part of the Wynyard Place development.