Solar power in Romania
Solar power in Romania had an installed capacity of 1,374 megawatt as of the end of 2017. The country had in 2007 an installed capacity of 0.30 MW, which increased to 3.5 MW by the end of 2011, and to 6.5 MW by the end of 2012. However, the record year of 2013 was an exception, and new installation fell back from 1,100 MW to a moderate level of 69 MW in 2014.
Romania is located in an area with a good solar potential of 210 sunny days per year and with an annual solar energy flux between 1,000 kWh/m2/year and 1,300 kWh/m2/year. From this total amount around 600 to 800 kWh/m2/year is technically feasible. The most important solar regions of Romania are the Black Sea coast, Northern Dobruja and Oltenia with an average of 1,600 kWh/ m2/year.
History
Romania was a major player in the solar power industry, installing in the 1970s and 1980s around of low quality solar collectors that placed the country third worldwide in the total surface area of PV cells. One of the most important solar projects was the installation of a 30 kW solar panel on the roof of the Politehnica University of Bucharest that is capable of producing 60 MWh of electricity per year.Rominterm, a Romanian company, by 2010, installed a total of 600 solar panels in Mangalia, Constanța County making the city self-sufficient in terms of heated water during the summer months and providing around 70% of heated water in the winter months and another 1,150 solar panels used for the generation of electricity spread over an area of. Another Romanian city, Alba Iulia, installed a total of 1,700 PV cells on several public buildings that have a rated power of 257 kW. Other cities include Giurgiu with 174 solar panels and 391.5 kW installed capacity and Saturn with 50 panels and 112 kW installed capacity.
The first two industrial scale solar power plants in the country are the Singureni Solar Park completed in December 2010, and the Scornicesti Photovoltaic Park, completed 27 December 2011. Each is 1 MW.
2023 saw the first hybrid farm, with the installation of a 1.1 MW photovoltaic power plant on wind farm land, giving a combined capacity of 7.25 MW, with a total investment of EUR 10 million. It is planned to add solar units to other wind farms over the next few years as the increased solar output in winter balances the higher wind output in winter whilst utilising the same grid connections.
Projects
In 2023 20 solar projects were operational or planned, the largest operational being:- Ucea de Sus Solar Park – Brasov County - 82 MW
- Sebiș Solar Park – Sebis, Arad County - 65 MW
- Livada Solar Park – Satu Mare County - 56 MW
- Izvoarele Solar Park – Giurgiu County - 50 MW
- Slobozia Solar Park – Giurgiu County - 45 MW
- Târgu Cărbunești Solar Park – Gorj County - 20 MW
- Bucșani Solar Park – Giurgiu County - 10 MW
- Pilu-Grăniceri solar power plant – Ottlaka and Graničar – 1.04 GW