Responsibility assignment matrix
A responsibility assignment matrix, RACI matrix or linear responsibility chart, is a project management technique that describes the responsibilities of various stakeholders in completing tasks or deliverables. The matrix assigns one of four responsibilities to each stakeholder in executing a deliverable: Responsible, Accountable, Consulted, and Informed.
Under the RACI framework:
- Responsible stakeholders are involved in the planning, execution, and completion of the task;
- Accountable stakeholders are held to be individually and ultimately responsible for the success or failure of the task;
- Consulted stakeholders are sought for their opinions on a task;
- Informed stakeholders are updated as the project progresses.
RACI model
R: Responsible — Those who complete the task. There is at least one role with a participation type of responsible, although others can be delegated to assist in the work required.
A: Accountable — The one ultimately answerable for the correct completion of the deliverable or task, ensuring the prerequisites of the task are met, and delegating the work to those responsible. Accountable stakeholders sign off and approve work that responsible stakeholders provide. According to some theories of project management, there must be only one accountable stakeholder specified for each task or deliverable.
C: Consulted — Those whose opinions are sought, such as subject-matter experts, and with whom there is two-way communication.
I: Informed — Those who are kept up-to-date on progress, often only on completion of the task or deliverable, and with whom there is just one-way communication.
The RACI model is also known as a responsibility assignment matrix and linear responsibility chart.
Alternatives
There are a number of alternatives to the RACI model, including:- DACI: Driver, Approvers, Contributors, Informed
- PARIS: Participant, Accountable, Review required, Input required, Sign-off required
- RACI + F: includes Facilitation in Scrum projects
- RACIS/RASCI/RASIC/RASI: includes Support
- RACIO/CAIRO: includes Omitted
- RACIQ: includes Quality review
- RACI-VSL includes Verifier and Signatory
Charting
| Tasks | Maintenance supervisors | Maintenance analyst | Maintenance planner | Maintenance technician | Maintenance support | Rel specialist | CMMS project engineer |
| Inputting failure data | A | C | I | R | C | C | |
| Work order completion | R | C | C | C | A | I | I |
| Work order closeout | C | R | C | I | I | A | |
| QA of failure data input | C | R | I | C | I | C | A |
| Analyze failure reports | C | C | I | C | A | R | I |
| Maintenance strategy adjustments | C | I | I | C | A | R | R |
| Implementing new strategies | R | I | R | C | A | I | I |