Mori–Torbole tunnel
The Mori–Torbole Tunnel is a diversion tunnel completed in 1959 between the Italian towns of Mori and Nago-Torbole to connect the Adige river with Lake Garda.
Its function is to reduce water levels in the river upstream of the province of Verona by discharging excess water into the lake. The tunnel reduces the risk of flooding in Verona and environs from once every seventy years to once every two centuries.
To increase the level of Lake Garda by, the tunnel must divert about of water.
When the tunnel is open, the temperature shock and inflow of mud caused by the sudden influx of the Adige's water endanger the lake's fish populations, although the lake's larger volume is able to absorb large quantities of extraneous water into itself. For these reasons the tunnel is used only on the rare occasion when there is a flood risk in the Veronese basin.
Main characteristics
- Length:
- Share of lead: a.s.l.
- Opening level: a.s.l.
- Difference:
- Slope: 0.8688%
- Average diameter:
- Hydraulic section:
- Maximum capacity:
- Water speed at the maximum capacity:
- Water speed at the minimum flow:
History
After the great floods of the second part of the 19th century, defense of the city of Verona from Adige floods was deemed urgent. Using an idea already established in the 18th century, Venice's Water Magistrate proposed constructing a diversion tunnel to Lake Garda that would alleviate flooding by conveying that part of the Adige's flow exceeding the river's carrying capacity. The lake's surface area, equal to about, would allow the diversion of huge volumes of river water with only a modest increase in the lake's level. The most appropriate solution was considered to be a tunnel originating on the right bank of the Adige near Ravazzone and terminating at Lake Garda to the south of Torbole. The depth of the lake at that location would allow solid material that might be transported by the water to be deposited without damage. Construction began under the fascist government in March 1939, was suspended for the war in 1943, then resumed in 1954 to finish in May 1959.Lake Loppio was drained during the construction of the tunnel. Water leaks became common as the tunnel approached the lake, and the lake was drained to prevent these and to reduce the danger posed to the workers.
The tunnel has been used only 13 distinct times since its opening. Here's a full list of those uses:
| Date | Water discharged | Maximum flow rate |
| 17 September 1960 | m³ | 450 m³/s |
| 2 September 1965 | m³ | 440 m³/s |
| 17 August 1966 | m³ | 280 m³/s |
| 4 November 1966 | m³ | 492 m³/s |
| 14 September 1976 | m³ | 300 m³/s |
| 17 November 1980 | m³ | 300 m³/s |
| 19 July 1981 | m³ | 300 m³/s |
| 23 May 1983 | m³ | 300 m³/s |
| 17 November 2000 | m³ | 100 m³/s |
| 26 November 2002 | m³ | 100 m³/s |
| 30 October 2018 | m³ | 350 m³/s |
| 31 October 2023 | m³ | 150 m³/s |