Mahoma Hydroelectric Power Station


Mahoma Hydroelectric Power Station is a mini-hydroelectric power plant in Uganda.

Location

The power station is located across the Mahoma River, in Kabarole District, Western Uganda. This location is approximately, south of the city of Fort Portal, where the district headquarters are located.
The power station has a catchment area that measures, with an average elevation of, above mean sea level.

Overview

This power station was developed by two Sri Lankan companies, the MG Group of Companies and Renewgen Limited. The Mahoma mini-hydro project is a run-of-the-river hydroelectricity project with planned annual output of 3,000kW of energy
The power generated is sold to the Uganda Electricity Transmission Company Limited, and distributed into the national electricity grid, with priority being given to local residents, by design and by agreement with the Electricity Regulatory Authority, via a 20 year power purchase agreement.

Ownership and funding

The power station is owned and operated by the two Sri Lankan energy companies that developed the power station, over a twenty-months period, from January 2017 until October 2018. The cost of construction is reported at US$8 million. The main contractor on this project was KSJ Construction of Sri Lanka.
The same investors also own the 7.6 megawatts Kyambura Hydroelectric Power Station, developed across the Kyambura River in Rubirizi District.