M2 (Warsaw)


The M2 line is the second line of the Warsaw Metro. It is currently long, has 18 stations and runs from Bródno neighborhood in Targówek district to the Górce district in Bemowo. The planned line completion is in 2026, and will run from Targówek to Bemowo and number 21 stations.
The route of the M2 metro line was confirmed in 2006. In 2007, a tender was announced for the completion of the central section of the route from Wola to Praga. In 2008, the tender was cancelled and a new one announced. In 2009, the new tender was complete and an agreement with the AGP Metro Polska consortium was signed. On 30 September 2014, the construction of the central section was complete and the final acceptance of the investment followed. The line opened on 4 March 2015.
In 2014 a tender was announced for the first extension "3+3", consisting of the completion of three stations in the west and three stations to the east of the existing central section. The tender was complete at the end of 2015 and an agreement for the completion of the eastern extension was signed at the start of 2016, followed in September by the signing of an agreement for the extension in the west. The opening of the eastern extension to Trocka occurred on 15 September 2019, and the western extension to Księcia Janusza on 4 April 2020.
In 2016 Warsaw Metro chose the contractors of the second extension, known initially as "3+2", which included 3 stations in the east and 2 in the west. This was further expanded to "3+5", adding 3 more stations at the western end. Bemowo and Ulrychów metro stations opened on 30 June 2022. The expansion to Zacisze, Kondratowicza and Bródno stations opened on 28 September 2022. The planned completion of the extension is in 2026, with the opening of Lazurowa, Chrzanów and Karolin stations.

Planned extensions

First plans

The first plans presumed that following the completion of the central branch, an extension to Bemowo could be complete by 2017, and followed by an offshoot extension to Bródno by 2020. Following these proposals the Warsaw city council analysed the concept of extending the M2 metro line in both directions simultaneously although in smaller increments. It was assumed the extensions to Księcia Janusza and Trocka would be opened to public use by 2017.

Białołęka project

On 14 December 2011 the Białołęka district council adopted an official resolution for the alteration of the planned M2 metro line route. The resolution proposed the removal of the Bródno metro station by Kondratowicza and Rembielińska streets. The new concept suggested the continuation of the line north past Kondratowicza street, routing the metro line to a newly proposed metro station by the Trasa Toruńska highway and Głębocka street.
In April 2013 the proposed M2 metro line extension was declined. The main allegations concerned inconsistencies between the projects and the provision of local spatial development plans and the lack of appropriate documents describing the impact of the investment on groundwater.

Return to initial extension concept

In June 2014, a new line expansion schedule was presented, which assumed that three more stations in both directions would be completed by 2018, and the next sections to Górce and Bródno stations would be built by 2020. It was assumed then that the construction of 11 metro stations over the course of 6 years would cost around 8 billion PLN. This meant that the metro would probably not decide to build a branch to Białołęka. In August 2014, an environmental decision was issued for the section towards Targówek, and at the end of September for the section in Wola.

Current stations

CodeNamePhotoInterchangesServicesDateLocationCoordinates
C04Bemowo Veturilo, Bike and Ride30 June 2022Bemowo
C05Ulrychów Veturilo, Bike and Ride30 June 2022Wola
C06Księcia Janusza Veturilo, Bike and Ride, Kiss and Ride4 April 2020Wola
C07Młynów Warszawa Młynów railway station Veturilo, Bike and Ride, Kiss and Ride4 April 2020Wola
C08Płocka Veturilo, Bike and Ride4 April 2020Wola
C09Rondo Daszyńskiego Veturilo, Bike and Ride8 March 2015Wola
C10Rondo ONZ Veturilo, Bike and Ride8 March 2015Wola/
Śródmieście
C11Świętokrzyska Veturilo, Bike and Ride8 March 2015Śródmieście
C12Nowy Świat-Uniwersytet Veturilo, Bike and Ride8 March 2015Śródmieście
C13Centrum Nauki Kopernik Veturilo, Bike and Ride8 March 2015Śródmieście
C14Stadion Narodowy Warszawa Stadion railway station Veturilo, Park and ride, Bike and Ride8 March 2015Praga-Północ
C15Dworzec Wileński Warszawa Wileńska railway station Veturilo, Bike and Ride, Kiss and Ride8 March 2015Praga-Północ
C16Szwedzka Veturilo, Bike and Ride15 September 2019Praga-Północ
C17Targówek Mieszkaniowy Veturilo, Bike and Ride, Kiss and Ride15 September 2019Targówek
C18Trocka Veturilo, Bike and Ride, Kiss and Ride15 September 2019Targówek
C19Zacisze Veturilo, Bike and Ride28 September 2022Targówek
C20Kondratowicza Veturilo, Bike and Ride28 September 2022Targówek
C21Bródno Veturilo, Bike and Ride28 September 2022Targówek

Future stations

CodeNameLineDateStatusCoordinates
STP2STP Karolin2026under construction
C01Karolin2026under construction
C02Chrzanów2026under construction
C03Lazurowa2026under construction