Lufeng Nuclear Power Plant
The Lufeng Nuclear Power Plant is a nuclear reactor under construction in the Guangdong province of eastern China. It is planned to house 6 pressurized water reactors.
CGN Lufeng Nuclear Power Corporation has been working on developing a nuclear plant in Lufeng, Shanwei since 2013. The National Development and Reform Commission approved the plant in 2014, starting with two AP1000 reactors. The National Nuclear Safety Administration gave its approval in 2015. In April 2022, the government approved the construction of two Hualong One reactors, which were designated Units 5 and 6.
Construction
Construction of the first unit began on 8 September 2022 and construction of the second unit on 26 August 2023. The first unit is expected to begin operation in 2028, and the second unit in 2029.Construction of the first CAP1000 unit began on 24 February 2025. and construction of the second CAP1000 unit began in December 2025.