Lake Champlain Bridge (2011–present)
The Lake Champlain Bridge is a vehicular bridge traversing Lake Champlain between Crown Point, New York and Chimney Point, Vermont. It replaced an older bridge that was demolished in 2009. The bridge was designed and constructed during an aggressive two-year schedule to minimize the social and economic impact of the original bridge's demolition. It is the only fixed-link crossing of Lake Champlain/Champlain canal between US 4 in Whitehall, to the south and US 2 at Rouses Point, to the north.
The main arch span was prefabricated off-site in Port Henry, floated by barge to the already-constructed approach spans, and then lifted into place on August 26, 2011. The completed bridge was originally scheduled to open on October 9, 2011, but this was pushed back around a month due to construction delays from underwater debris and record flooding.
The bridge opened to the public on Monday, November 7, 2011, following a ribbon-cutting ceremony.