John Dewey Academy of Learning
The John Dewey Academy of Learning is a charter school of the Green Bay Area Public School District serving Green Bay, Wisconsin and the surrounding areas. It was founded in 2010, it has operated in its current location since 2019. It is one of two charter schools in GBAPSD.
Harvey Street School (2010–2019)
John Dewey was formed by a contract with the Green Bay Area Public School District in 2010, opening its doors in the former St. Peter and Paul School building, which now hosts St. Thomas More Catholic School. At the time of its conception, and for a short time later, it operated with a principal overseeing day-to-day operations, who was shared at the time with Beaumont Elementary School.The building, which was leased from the Roman Catholic Diocese of Green Bay, was rudimentary, and lacked essential services including appropriate shop and project space, and adequate food production and serving capabilities. Originally operating in an open concept design, by 2013, high volume levels due to poor acoustic design, and increasing enrollment lead to layout changes that survive today, with sprawling communal workplaces replaced by delineated and separate advisories.
The school remained in the building until funds could be acquired by the 2017 referendum, which allocated $2,250,000 for the building, acquisition, or renovation of a new school space. This referendum also lead to the John Dewey Academy of Learning 2.0 project.
The JDAL 2.0 Project
Intended as a way to allow the students to have a hand in creating the school that would one day be; the staff of the school, as well as the administration of the district organized the JDAL 2.0 project. Multiple designs for renovation and new construction were proposed, with the architects incorporating design elements for each in the final project. Of the multitude of designs created for the school, three were presented to the contracted architectural firm. They were known as: The New Construction Design, The Remodel Design, and The East High School Design.The New Construction Design
The New Construction design was the most popular with students at the time, as accessed by a school administered survey. As popular as the design was, there was concern that the 2.25 million referendum would be insufficient to support the cost of building and outfitting a new school.The "Mystery Space" Remodel Design
The Remodel Design was the second most popular among students, although the district failed to ever reveal which space it was intended to fill. The uncertainty as to whether or not it would involve the school being inside another school lead to the plan being second to the new construction design.The West High School Design
The West High School Design was by far the least popular among students, as it involved the loss of autonomy by integration into available space at nearby Green Bay West High School. Despite the student's opposition, this plan had wide district support because of the ease of retrofitting, and the fact that the district would not need to acquire or maintain further property. The district ultimately capitulated, and the school received its current location on Cherry Street.Cherry Street School (since 2019)
During the summer of 2019, the school moved from its former Harvey Street location to its Cherry Street location, remaining on the east side of the city.The Cherry Street School was converted from an old office building and also temporarily houses the other charter school in Green Bay, the Northeast Wisconsin School of Innovation. The school currently operates on a five-year contractual term, the maximum allowed by Wisconsin state law. The next school year in which the contract will be again up for discussion is 2025–26.