Indefatigable gas field
The Indefatigable gas field is a large natural gas and associated condensate field located under the North Sea 60 miles off the Norfolk coast.
The field
The Indefatigable gas field is a natural gas field located in the North Sea. The field is 67 miles north-east of Great Yarmouth and is named after the Indefatigable Banks, a shallow sand bank beneath which it is situated. The gas reservoir is a Rotliegendes sandstone 200–300 feet thick at a depth of 8000–9000 feet. It was discovered in June 1966 and extends over several blocks: 49/18, 49/19, 49/23 and 49/24. The original determination of the gas in place amounted to 126 billion cubic metres. Blocks 49/18 and 49/23 were originally licensed to Amoco and Block 49/19 and 49/24 to Shell. Production from the field began in September and October 1971. Gas and associated condensate are produced via the Leman gas field to the Bacton Gas terminal, Norfolk.The Indefatigable gas composition and properties are as follows.
| Composition | % |
| Methane | 91.8 |
| Ethane | 3.39 |
| Propane | 0.85 |
| i-butane | 0.16 |
| n-butane | 0.20 |
| i-pentane | 0.07 |
| Hexanes | 0.06 |
| Heptanes plus | 0.16 |
| Nitrogen | 2.73 |
| Carbon dioxide | 0.52 |
| Hydrogen sulfide | Nil |
| Gas gravity | 0.61 % |
| Mean condensate content | 3.0 bbl/million cubic foot |
| Btu rating | 1015 Btu/cubic foot |
Baird gas field
The Baird gas field is located in Block 49/23 and is licensed to Perenco. It was discovered in September 1993 and has recoverable reserves of 1.82 billion cubic metres. Gas is produced via a seabed well assembly and a pipeline to Inde 49/23 D. The peak production was 0.66 billion cubic metres per year.Development
The Indefatigable field has been developed through a number of offshore installations.The Inde installations developed by Amoco, now owned by Perenco, were:
| Installation | Location Block | Platforms | Function | Type | Legs | Well slots | Installed | Production start | Production to |
| Inde A Complex | 49/18 | Inde AD | Drilling | Steel jacket | 8 | 12 | July 1970 | September 1971 | Inde AT |
| Inde A Complex | 49/18 | Inde AP | Production | Steel jacket | 8 | – | 1970 | September 1971 | Inde AT |
| Inde B Complex | 49/18 | Inde BD | Drilling | Steel jacket | 8 | 12 | 1973 | June 1974 | Inde AT |
| Inde B Complex | 49/18 | Inde BP | Production | Jackup | 4 | – | 1973 | June 1974 | Inde AT |
| Inde C Complex | 49/23 | Inde CD | Drilling | Steel jacket | 8 | 12 | August 1976 | July 1977 | Inde AT |
| Inde C Complex | 49/23 | Inde CP | Production | Steel jacket | 8 | – | 1976 | July 1977 | Inde AT |
| Inde Compression | 49/23 | Inde AT | Pipeline terminal | Steel jacket | 6 | – | May 1971 | September 1971 | Leman 49/27B |
| Inde Compression | 49/23 | Inde AC | Compression | Steel jacket | 12 | – | Jacket June 1979, topsides Summer 1980 | November 1980 | – |
| Inde Compression | 49/23 | Inde AQ | Accommodation | Steel jacket | 4 | – | June 1979 | – | – |
| Inde D | 29/23 | Inde D | Wellheads and production | Steel jacket | 4 | 4 | 1990 | 1990 | Inde C |
The Perenco Indefatigable 49/23A complex also receives gas from other fields and third parties:Bessemer installation and its satellite N.W. Bell via a 14.5 km 16-inch pipeline.Wenlock installation owned by Alpha Petroleum via a 36.231 km 8-inch pipeline. A three well-slot installation was installed in the Wenlock field in 2006 with wells commissioned in 2007, 2008 and 2009. Production declined quickly and make the installation uneconomic and a Decommissioning Programme application was submitted to the Oil & Gas Authority in 2021.Davy installation and its satellites Davy North and Davy East via a 43 km 16-inch pipeline.
The Inde installations developed by Shell were:
| Installation | Location Block | Platforms | Function | Type | Legs | Well slots | Installed | Production start | Production to |
| Inde J Complex | 49/24 | Inde JD | Drilling/production | Steel jacket | 8 | 6 | June 1970, April 1971 | September 1971 | Inde AT |
| Inde J Complex | 49/24 | Inde JP | Satellite | Steel jacket | 4 | – | April 1972 | – | – |
| Inde K Platform | 49/24 | Inde K | Drilling/production/ accommodation | Steel jacket | 10 | 6 | July 1971, June 1972 | March 1973 | Inde AT |
| Inde L Platform | 49/24 | Inde L | Drilling/production | Steel jacket | 6 | 6 | February 1977 | October 1978 | Inde K |
| Inde M Platform | 49/19 | Inde M | Drilling/production | Steel jacket | 4 | 4 | Spring 1985 | October 1985 | Inde J |
| Inde N Platform | Inde N | Drilling/production | Steel jacket | 4 | 4 | 1980's | Inde K |
Production from the Shell Inde field ceased in 2005, Inde J, K, L, M, and N were subsequently decommissioned and removed.