The site was constructed at the Nanliao landfillarea with an area of 30 hectares. The area used to be a beach but was transformed into a landfill in 1973 but was eventually closed inNovember 1994.
Architecture
The plant was designed by architect Ieoh Ming-pei. It occupies a 5.5 hectares of land.
Technical details
The plant can treat 900 tons of garbageper day from Hsinchu City, Miaoli County and Taoyuan City and produce 24 MWh of electricity per day. As of 2020, it received a total of 22,606 tons of garbage annually and incinerated 21,827 tons of them.