Hastings Power Station
Hastings Power Station was a gas turbine power station situated in Hastings in East Sussex, England. It was built on the site of the Broomgrove coal-fired power station. When the power station was completed in 1966 it had two 55-megawatt gas turbine generating sets; the first set was commissioned in January 1966 and the second two months later in March.
Specifications
Infrastructure
;BuildingThe station consisted of a steel framed building clad with thick brick walls without windows. The access doors were double-skinned to reduce noise emissions. The compressor intakes, at each end of the station, were at roof level. Silencing was provided at the air intakes by attenuators fitted between the exhaust gas ducting and the bases of the two chimney stacks.
;Chimneys
Exhaust gases entered the exhaust casing at 450 degrees Celsius and left the 200 ft high chimneys at 300 degrees Celsius. The chimneys were concrete, lined with heat- and acid-resistant bricks and a stainless steel 'cap'. About 1.4 million cubic feet per minute of gas containing 19% oxygen was exhausted from each chimney at a velocity of ~.
;Cooling water
Cooling water for the station auxiliaries and alternator was drawn from a local pond, through a small independent mechanical draught-tower.
;Emergency generator
An emergency Diesel generator-driven exciter set was housed in a separate building. In the event of a system shut down, the generator was capable of driving sufficient auxiliaries to start up, under black start conditions, and put on full load, using both main turbines consecutively.
;Fuel oil
The gas turbine fuel oil supplies were held in five vertical main oil storage tanks, with a total capacity of 4,440 tonnes - equivalent to little more than 130 hours continuous generating at full load. Fuel was delivered by rail to the station's own siding located off the Hastings to Ashford Railway line, a few hundred metres north east of Ore railway station.
Power plant
;Gas generatorsRolls-Royce gas generators were used. With little modification, these had been adapted to burn diesel oil with a high degree of reliability. They were developed from the well-tried aircraft engine used in the Comet and Caravelle aircraft. It had a single-shaft engine with a 17-stage axial flow compressor and cannular combustion chamber, before reaching the three-stage turbine.
;Turbine
There were two 55 MW AP4 Rolls-Royce/AEI sets. Four gas generators in 'box' formation powered a two-stage turbine having discs of 2.5% nickel chrome and a stator of Nimonic 80A. The turbine blades were also forged from Nimonic 80A and were, at the time, the largest Nimonic forging ever made.
;Alternator
The alternator was designed to operate at 3,000 rpm and was coupled to the turbine via a clutch. The main and pilot exciters were gear-driven from the end of the alternator shaft at 1,000 rpm.
Automatic control
The station was controlled from the Grid Control Centre at East Grinstead. But it could also be controlled locally. The main turbines and auxiliaries were controlled with manual overriding features. The main turbine sets could achieve a load of 10 MW from the pressing of a button within 2 minutes and 40 seconds. From the stabilizing load of 10 MW, the full capacity of 55 MW could be achieved in a matter of seconds.This fast start-up of a power-station was particularly useful for supplying the national electricity grid at very short notice where sharp drops in supply occurred.