Green Line (Karachi Breeze)
The Green Line is a bus rapid transit line of the Karachi Breeze metrobus system, operational since December 2021 in Karachi, Sindh, Pakistan. Its construction began in February 2016 on the orders of the then Prime Minister Nawaz Sharif. Being stalled for years, it was then completed by the orders of Prime Minister Imran Khan. The busway is the first phase of the Karachi Metrobus network and has 22 stations. The Green Line was expected to be functional by November 2021 and to have a fleet of 80 buses operated by Daewoo. So far, 80 buses for the project have reached from China at the Karachi Port. Speaking at the ceremony held to celebrate the arrival of buses in Karachi, Federal Planning and Development Minister Asad Umar said, "The proper commercial operation of the Green Line bus service would begin in Karachi by 25 December 2021 after completion of the trials". Buses were purchased from Foton Motor.
Route
The route of Green Line is mentioned Below:Common Corridor Stations :
- Tower B Station
- Tower A Station
- Light House Station
- Civil Hospital Station
- Jama Cloth Station
- Municipal Park Station
- Shownu Point Station
- Gul Plaza Station
- Sea Breeze Station
- Numaish Station
- Patel Para Station
- Lasbela Chowk Station
- Sanitary Market Station
- Nazimabad No.1 Station
- Enquiry Office Station
- Annu Bhai Park Station
- Board Office Station
- Hyderi Station
- Five Star Chowrangi Station
- Jummah Bazaar Station
- Erum Shopping Mall Station
- Nagan Chowrangi Station
- U.P. More Station
- Road 4200 Station
- Power House Chowrangi Station
- Road 2400 Station
- 2 Minute Chowrangi Station
- Surjani Chowrangi Station
- Karimi Chowrangi Station
- KDA Flats Station
- Abdullah Chowk Station
Financing and construction
The Government of Pakistan financed the majority of the project. Engineering Associates were contracted as the designers and supervision consultants for Green Line while Think Transportation was contracted as urban engineering consultants.On 10 December 2021, Prime Minister Imran Khan formally inaugurated the Green Line Bus Rapid Transit project. He announced that "commercial operations will begin on 25 December and total operations will start by 10 January ". Limited operations began from 25 December 2021, with only 11 out of the 22 stations operational. The project started its full operations from 10 January 2022, as announced.
A Spanish Firm Grupsa which provided platform screen doors for the Project, approached Pakistani Anti-corruption agencies for over invoicing its services. It claimed that a Pakistani contractor was embezzling funds.