East Coast Elevated Expressway


The East Coast Elevated Expressway is a proposed elevated expressway in the city of Chennai, India. It runs along the coast of Bay of Bengal crossing Adyar Estuary passing by the western side of Broken bridge, Chennai. This corridor is being implemented by the Tamil Nadu Highways Department in two phases and forms a part of circular transportation corridors.

Alignment

There are three segments for the project. The vertical clearance is 5.5 m.

Phase 1: Lighthouse — Elliot's Beach 4.7 km

Gandhi Statue — Foreshore Estate: 2.4 km

  • This section is 4-laned. The ramp starts near Light House on the service road left of Kamarajar Salai.
  • The entry ramp starts next to the lighthouse and takes a right turn into the elevated corridor.
  • The exit ramp starts in front of the IG ramp takes a left turn after 300 m and turns right 50m just after the Lighthouse and runs along the median of the Nochikuppam Road/ Elevated Expressway.
  • Both ramps meets @ 0.5 km and run for distance of 1.9 km and continue to pass through the next section.
  • This section provides the connectivity between the Buckingham corridors with the Adyar Corridor of circular corridors.

Foreshore Estate — Elliot's Beach: 2.3 km

  • An entry and exit ramp at Foreshore Estate junction joins the main section and continues as a 4-lane road till Elliot's Beach.
  • It runs for a distance of 1.7 km and joins Besant Nagar 5th Avenue Road @ Elliot's Beach.
  • It crosses Adyar River and passes to the west of Broken Bridge.
  • It also includes a 4-lane Through arch bridge called "Signature Bridge" across Adyar Estuary for a distance of 250 m.
  • This section was proposed as a 6-lane stretch by the consultant but the committee wants it to be 4-laned uniformly throughout the corridor!

Phase 2: Elliot's Beach — East Coast Road 5 km

This stretch runs over Elliots Beach Road and turns east near velankanni church and runs parallel to the Bay of Bengal till Kottivakkamkuppam and take a right turn to join the East Coast Road at Kottivakkam

Ramps

The corridor will have entry and exit ramps at the following places.

Project Status

2009

January:
26 August:
14 October:
  • Entry and exit ramps at light house realigned.
  • Broken bridge to be demolished and rebuild as a steel-arched bridge.

2010

5 May: Detailed Feasibility Study approved and DPR would be prepared.