Chennai BRTS was a bus rapid transit system taken up as an integrated part of Circular Corridor Project in India. Beginning at Adyar, the route will cover Saidapet, Jafferkanpet, Ramavaram, Puzhal, Manali, Chennai Central Railway Station, Lighthouse and will return to Adyar. The corridor will cover a distance of. The route of the elevated BRTS corridor was planned to run along the banks of Adyar river and Buckingham canal. The project was expected to be completed by 2013.

Corridors

The BRTS system was supposed to be integrated with the Circular Corridor 1 of the High Speed Circular Corridors.Lighthouse — Adyar — IT corridor — Kundrathur — Madhuravoyal — Ennore — Vyasarpadi — Chennai Port — Lighthouse

Alignment

The Exclusive BRTS lane was proposed to be integrated with the circular corridor 1. Two different types were under consideration.
  • Along the median of the 6-lane single-tier system.
  • On top of the 6-lane two-tier system. BRTS 2-lanes was proposed on the top tier and 4-lane for general traffic at the bottom second tier.
The following was the general alignment of the entire BRTS corridor. This was the alignment of the entire BRTS corridor.

Stations

Station type

Tower structure was proposed for the BRTS stations. Two types depending on the type of the corridor were proposed.
  • Towers along the median of the 6-lane single tier system.
  • Towers along the curb-side for the 2-tier and 3-tier system.

Station locations

21 bus stations were proposed for the first phase of the BRTS.
Corridor NameLengthNumber of Bus stationBus station Name
Adyar Corridor15.8 km7Adyar, West Canal Road, Kotturpuram, Saidapet, Jafferkhanpet, Nandambakkam, Porur
NH-Bypass Corridor13 km5Porur, Madhuravoyal, Ambattur, NH-205 cross road, Puzhal
Northern IRR section8 km3Madhavarm junction, Manjambakkam, TPP road junction
North B' Canal Corridor12 km6Junction of Manali High Road and Buckingham Canal, interchange with Kamarajar Salai,
Basin road, near Indian Oil Corporation bottling plant, Korukkupet, Basin Bridge, near central station
South B' Canal Corridor-4at walajah Road junction, Triplicane, near Madaveli MRTS Station, Kotturpuram

Design speed

The speed design for the BRTS corridor was proposed to be 60 km/h - 70 km/h.

Integration of BRTS with other transits

The BRTS was proposed to be integrated with different modes of transits already existing or under construction or proposed for the city. Apart from that major roads were also to be integrated. The following is a list of locations of BRTS integrating different modes of Transport in Chennai city.
Major roadsIT corridor extension via West Canal Bank Road, Gandhimandapam / TurnBulls Road,
Anna Salai, Jawaharlal Nehru Road, Mount-Poonamallee Road, Arcot Road
Major railway stationsChennai Central, Basin Bridge Junction
MRTS stationsKotturpuram, Chepauk, Mandaveli
Metro stationsSaidapet, Jafferkhanpet

Project status

2008

November:

2009

28 May:
3 June:
  • Residents oppose the project as they will be displaced for the project.
  • Adyar Poonga Trust promises to resettle the displaced.
26 August:
  • Feasibility study for the project was likely to be over by January 2010. Total Corridor length was 110 km.