Port Phillip Channel Deepening Project
The Port Phillip Channel Deepening Project began on 8 February 2008 to deepen the shipping channels leading to Melbourne, Australia.
The project was to deepen channels in Port Phillip to draught to allow greater access for container ships. An estimated A$969 million was to be spent on the works, with $150 million funded by taxpayers. The dredging works were conducted by Dutch company Royal Boskalis for the Port of Melbourne Corporation, a statutory body established by the Victorian Government responsible for the running of the port, at a cost of $500 million and was expected to be completed before 31 December 2009, pending auditor reports and various legal actions against the project. This project was to be conducted under a controversial Public-Private-Partnership.
Operating almost 24 hours a day, the project involved the removal of approximately 22.9 million m3 of sand, fine river silt. The material removed was transported to designated "dump sites". According to numerous scientists, community representatives, environmental and community groups, the dredging would disturb marine plant, animal and microbial life through large areas of the bay.
The project caused significant controversy among many communities throughout the Victorian population, and was strongly opposed by scientists such as biologists and geologists, the CSIRO, university academics and scientists including Monash University, and many groups representing the community including the Dive Industry of Victoria, the Victorian Greens, the Australian Peak Shippers' Association, and the Victorian National Parks Association. The amalgamated community group Blue Wedges held public rallies and several pickets from 2004 to 2008, involving surfers, canoes, kayaks, boats and yachts who put themselves in the path of the dredging ship Queen of the Netherlands, which delayed the project for a time. The project eventually began, although under limited conditions, after Blue Wedges won a reprieve in the Federal Court. The limited conditions were stripped from 28 March 2008 after ensuing legal proceedings saw the Blue Wedges case dismissed. Legal costs were pursued by the state government.
In 2009 the Victorian Auditor-General's report was released. The Auditor-General sourced information on what percentage of ships could and could not enter the bay, from the Port of Melbourne exclusively, who had twice previously overestimated the number of ships that could not enter the bay prior to dredging. In contrast, in the Drewry Report, the more accurate calculation of ships that were not loading to full capacity in Melbourne was calculated to be between 10% and 4% -- this Drewry Report was commissioned by the Port of Melbourne Corporation in 2001, but was not made accessible to the public until the Victorian Greens obtained it under a Freedom of Information request in 2005—the Drewry Report concluded that, were the channel deepening project to be completely cancelled, the economic loss from this small percentage of ships unable to load to capacity would be in the vicinity of $13 million, rather than the $30 million that had previously been claimed by PoMC. Furthermore, the Drewry Report also concluded that a dredge of 0.5 metres would be sufficient for 96% of vessels, and the PoMC's planned dredge to 2.5 metres depth was "extreme" and "potentially disastrous" and expensive and unnecessary. In addition, almost all of the shipping companies that use Melbourne's ports stated that there was no need for dredging or channel deepening in the bay or around the ports.
The government announced the completion of works in November 2009, ahead of schedule and $200 million under budget.
The project
The Port Phillip Channel Deepening Project was carried out by Dutch dredging company Royal Boskalis for the Port of Melbourne Corporation. The PoMC also sought the assistance of Boskalis Australia Pty Ltd, a daughter company of Royal Boskalis.Prior to the completion of the works, ships entering the Port of Melbourne were restricted to draught. Larger container ships instead need to carry full loads. The PoMC estimated that in the 2006-07 financial year, 38.5% of ships visiting the port was already potentially affected by draught limitations because the channel did not allow for the extra depth, with this figure rising to 44.3% in the December quarter of 2007. The key objective of the Channel Deepening Project was to address these draught restrictions.
Project areas
The PoMC has specified four project 'areas' of the bay to be completed progressively.| Project No. and Area | Shipping channel | Location | Status | Start | Finish | Dredging volumes/Type of material dredged |
| 1. Yarra River and Hobsons Bay | Yarra River & Williamstown Channels | Completed | 24 April 2008 | 5.38 million m3 of clay and silt, approximately 2.07 million m3 of this contaminated | ||
| 2. North of Bay | Port Melbourne Channel | Completed | 29 February 2008 | 2.40 million m3 of mainly clay, approximately 43, 000 m3 of this contaminated | ||
| 3. South of Bay | South Channel | Completed | 8 February 2008 | 14.59 million m3 of mainly sand | ||
| 4. The Entrance | The Great Ship Channel | Completed | 5 April 2008 | 0.55 million m3 of limestone/sandstone |
Yarra River and Hobsons Bay
North of Bay
The second area to be dredged, dredging was expected to begin in this area but was delayed after a court injunction, with dredging instead beginning in the south of the bay.
South of bay
The first area to be dredged under limited conditions specified in a court injunction.
The Entrance
The Entrance was argued to be one of the more sensitive areas of Port Phillip Bay to be dredged, after a rockfall incident that occurred during trial dredging in 2005.
Disposal of dredged material
Materials dredged in Port Phillip were disposed of in two areas.Contaminated dredged material from the Port Melbourne, Williamstown and Yarra River channels was disposed of in the existing Port of Melbourne Dredge Material Ground, which covers an area of about . The site was expected to be extended to the south by an area of to accommodate the dredged material volumes as a result of the dredging project as well as to accommodate dredged material volumes from future maintenance dredging.
Uncontaminated dredged material from the South Channel and the Great Ship Channel was to be disposed of in a dredged material ground yet to be built in the south east part of the bay, expected to cover an area of .
Those materials which are contaminated were to be stored in an underwater clay containment area known as a 'bund' at the existing Port of Melbourne DMG, and capped with clean dredged sand.
Environmental management
Various environmental monitoring activities must be carried out by the PoMC as stipulated in the Environmental Management Plan- Turbidity monitoring
- Office of the Environmental Monitor
- Environmental Protection Authority
- Monitoring Tool
Project approval
Cooperating with the Environment Effects Act 1978, the PoMC released its Environmental Effects Statement, a report on the environmental, economic and social impacts of the channel deepening project, on 5 July 2004. The EES was available for public viewing until 16 August 2004 and an independent panel sat from 21 September to 17 December 2004 to hear submissions and consider the environmental effects and issues raised in the EES. In February 2005, the independent panel released their report on the EES, presenting 137 key aspects of the EES which needed building on. These included further examination of channel deepening designs; investigation of dredging technology; investigation of best methods of sediment disposal, and examination of turbidity. The panel's recommendations led to the Trial Dredge Program that took place from 6 August 2005.Consequently, on 31 March 2005, the then Minister for Planning Rob Hulls announced that the PoMC would be required to carry out a Supplementary Environmental Effects Statement to further investigate the environmental impact of the dredging project and address its shortcomings. Hulls said the SEES would "build upon the EES process to date" and would be "based upon the key areas outlined by the panel and allow for further expert analysis". On 21 March 2007 the PoMC released its Supplementary Environment Effects Statement for public viewing until 7 May.
The EES and the SEES culminated in the Environmental Management Plan, a report prepared by the PoMC consisting of "regulatory controls, environmental controls, project delivery standards and environmental monitoring" for the channel deepening project. On 5 February 2008, Environment Minister Peter Garrett approved of the EMP.