Bromford Tunnel


Bromford Tunnel is a high-speed railway tunnel in North Warwickshire and Birmingham, England that will serve to bring the High Speed 2 rail line into Birmingham upon completion.
The twin-bore tunnels are situated between Water Orton and Washwood Heath. The tunnels were excavated between July 2023 and October 2025.

History

The contract to build the tunnel, as part of the wider N1 and N2 lots on the HS2 programme, was awarded to the Balfour Beatty Vinci JV on 1 April 2020, valued at. This followed them being named by HS2 as part of the intention to award in July 2017.
The route was initially envisioned in the High [Speed Rail Act 2017] to be a tunnel, long and partly on viaduct, less than, in length.
On 20 January 2022, HS2 Ltd made a Transport and Works Act Order application to remove the words "partly on viaduct" in the description of the works, in a bid to extend the tunnel by instead. This decision was claimed to reduce land take, minimise impacts on the Park Hall Nature Reserve, avoid the need to redirect the River Tame, and reduce construction traffic.
The plans were refused by North Warwickshire Borough Council and subsequently dismissed on appeal by Grahame Gould, an inspector of the Planning Inspectorate in March 2023. The Secretary of State for Levelling Up, Housing and Communities and Secretary of State for Transport recovered the appeal to these plans and Schedule 17 approval was granted on 14 May 2024. The council applied for a judicial review, which was heard over three days in the High Court in February 2025 by Justice Dove. The council claimed that HS2 did not have the correct authorisation to extend the tunnel; however, the case was dismissed on all grounds on 20 May 2025. As of 2025, North Warwickshire Borough Council has spent £116,740 of taxpayer money on the case and has sought permission from the Court of Appeal to appeal the ruling.
The two Herrenknecht tunnel boring machines used to construct the tunnel were named Mary Ann, after Mary Ann Evans and Elizabeth, after Elizabeth Cadbury. Most of the second TBM to be delivered, Elizabeth, was repurposed from TBM Dorothy used to construct the Long Itchington Wood tunnel, with a new outer cutter-head and shield ordered.

Design

The tunnel passes underneath the Park Hall Nature Reserve, River Tame, and M6 motorway, and runs up to underground.
The tunnel will have 13 cross-passages, spaced every, and wide, as well as 8 adits.
The western portal at Washwood Heath sits next to the Washwood Heath depot and Network Integrated Control Centre, where trains will be maintained and stored and where operational control of the line will be based.
The eastern portal at Water Orton will have a porous portal, likely in the form of a perforated concrete structure, to mitigate tunnel boom associated with trains travelling at.
The decision to extend the tunnel to over 3 km resulted in the need for an intermediate shaft to allow for adequate airflow. The tunnel will have a deep, diameter ventilation shaft at Castle Vale, around the halfway point of the tunnel. The headhouse, located in the Castle Bromwich Business Park, will have pre-cast concrete walls with an overlaid "flexi-brick" lattice facade made of ceramic tiles and a 'green roof'.

Construction

Tunnelling and excavation was primarily through Mercia Mudstone, at mostly BGS grade II weathering. The groundwater level is, at most, above the tunnels' roof.
The variable pressure TBMs used to construct the tunnel have a cutter-head diameter of, with a length of and weigh approximately 1,600tonnes each. They were both expected to take 16months to complete the tunnel, employing around 450people.
The TBM Mary Ann started boring in July 2023 from an underground box structure, measuring, at the eastern portal in Water Orton, towards the deep portal at Washwood Heath. This was followed by TBM Elizabeth in March 2024.
A total of 40,628 concrete segments, weighing up to 7tonnes each, produced by the joint venture's pre-cast concrete factory in Avonmouth, Bristol, were used to support the tunnels. These formed 5,804 rings, weighing 49tonnes each. Forty percent of the cement used was replaced with ground granulated blast-furnace slag, claimed to reduce the overall carbon footprint involved. The TBMs excavated 1.8milliontonnes of material, which was treated by the on-site slurry treatment plant for use on HS2's delta junction, south of Water Orton, and conveyed on dedicated haul roads.
Mary Ann broke through on 9 May 2025, after advancing at a peak of per day, while Elizabeth broke through on 13 October 2025.