EnBW Baltic 1 is the first commercial offshore wind farm of Germany in the Baltic Sea. Siemens supplied 21 SWT 2.3-93 wind turbines for the 48.3 megawatt wind farm. EnBW Baltic 1 is located about north of the Darss-Zingst Peninsula and covers about seven square kilometers. Work started in July 2010; the wind farm was officially commissioned on 2 May 2011.
Due to the Kriegers Flak Combined Grid Solution, power from Sweden, the 600 MW Kriegers Flak, the 288 MW Baltic 2 is sent via Baltic 1 to Germany, and is synchronized to the Nordic grid via a 150 kV 400 MW alternating current subsea cable.
Generation
| Year | Production GWh | Full load hours |
| 2012 | 204 | 4,224 |
| 2013 | 191 | 3,954 |
| 2014 | 196 | 4,048 |