Baltic 1 Offshore Wind Farm


EnBW Baltic 1 is the first commercial offshore wind farm of Germany in the Baltic Sea. Siemens supplied 21 SWT 2.3-93 wind turbines for the 48.3 megawatt wind farm. EnBW Baltic 1 is located about north of the Darss-Zingst Peninsula and covers about seven square kilometers. Work started in July 2010; the wind farm was officially commissioned on 2 May 2011.
Due to the Kriegers Flak Combined Grid Solution, power from Sweden, the 600 MW Kriegers Flak, the 288 MW Baltic 2 is sent via Baltic 1 to Germany, and is synchronized to the Nordic grid via a 150 kV 400 MW alternating current subsea cable.

Generation

YearProduction
GWh
Full load hours
20122044,224
20131913,954
20141964,048