Ayebo Biomass Power Station
Ayebo Biomass Power Station, also Biovéa Biomass Power Station, is a biomass-fired thermal power plant under development in Ivory Coast. Biovéa Énergie SA, a special purpose vehicle company, has been awarded the concession contract to design, finance, construct, operate and maintain the power station. As raw material, the power station is designed to use palm oil waste.
Location
The power plant is under construction in the village of Ayebo, in Aboisso Department, Comoé District, Sud-Comoé Region, in southeastern Ivory Coast. Ayebo is located approximately, by road, south of Abengourou, the district capital. This is about, by road, northeast of Abidjan, the capital and largest city in the country.Overview
In January 2020, the development contract was awarded to Électricité de France, the national electricity utility of France Meridiam, a French public infrastructure financier and Biokala SA., an "Ivorian biomass producer", a subsidiary of the Sifca Group.The power station will burn palm oil waste, sourced from 12,000 Ivorian farmers, to heat water and produce steam. The steam will be used to turn turbines and generate electricity. The power generated will be sold to the Electricity Company of Ivory Coast, under a 25-year power purchase agreement.
Ownership
The Ayebo biomass power plant is under development by the consortium that owns it. The owners formed a special purpose vehicle that owns and plans to operate and maintain the power station after completion. That company is called Biovéa Énergie SA. The table below illustrates the shareholding in Biovéa Énergie SA.| Rank | Shareholder | Domicile | Percentage | Notes |
| 1 | Électricité de France | France | 40.00 | |
| 2 | Meridiam | France | 36.00 | |
| 3 | Biokala SA | Ivory Coast | 24.00 | |
| Total | 100.00 |
Construction costs and timeline
The total cost for the power plant is estimated at US$223 million. Proparco, the subsidiary of the French Development Agency, FMO (Netherlands) and Société Générale have jointly lent €90 million, towards this project.Électricité de France was assigned the engineering, procurement, and construction function. Meridiam was assigned the financial role, while Biokala is responsible for the supply chain of the palm oil waste. Construction was expected to start in 2020, with commercial commissioning in 2023.
In March 2022, Afrik21.africa reported that earthworks at the construction site had started on 24 February 2022, with completion anticipated in 2023. In August 2022, Biovea Energie, the special purpose vehicle company contracted China Energy Engineering Corporation to build the plant. Completion is expected in 2024.