Alten Solar Power Station


Alten Solar Power Station, also Kesses 1 Solar Power Station, is a solar power plant in Kenya, the largest economy in the East African Community.

Location

The power station is located outside the city of Eldoret, in Uasin Gishu County, approximately, by road, north-west of Nairobi, the capital and largest city in Kenya. The solar farm will sit on approximately of former farmland, approximately, south-east of Eldoret and about one kilometer east of Eldosol Solar Power Station and Radiant Solar Power Station.

Overview

Kenya has ambitions to electrify 100 percent of the country's population, up from 70 percent in 2017. This development and the 50 megawatt Kopere Solar Power Station, together with the 55 megawatt Garissa Solar Power Station, owned by Kenya Rural Electrification Authority, are aimed to diversify Kenya electricity sources, given the unpredictability of hydro-power in this East African country. This power station is expected to supply 123 GWh of energy annually, enough to meet the energy needs of over 245,000 Kenyan homes.

Developers

The power station is owned by Alten Energías Renovables, a European independent power producer with two other solar project developments in Kenya, Kesses 2 and Kopere.
Alten notified Kenyan authorities that the French company Voltalia was selected by the owners to carry out the construction as the engineering, procurement and construction contractor, as well as the operations and maintenance contractor for the plant. The power is sold to electricity distributor Kenya Power and Lighting Company via a 20-year power purchase agreement.

Funding

Standard Bank of South Africa, Stanbic Bank of Kenya and CIB Bank jointly provided a syndicated loan of US$41 million. The Emerging Africa Infrastructure Fund of the United Kingdom lent US$35 million towards his project.

Transmission

The 230kV high voltage transmission line between Turkwel Hydroelectric Power Station and the Kenya Power substation at Lessos, passes over this solar farm. The power generated at this solar farm will be injected into the Kenyan grid at the point where that 230kV line crosses the solar farm.

Construction timeline

Construction started in January 2020, with commissioning expected in late 2021 or early 2022. In September 2022, Afrik21.africa reported that the installation of the power station hardware was complete. After the mandatory performance tests and calibrations, the solar farm was expected to come online during the fourth quarter of 2022. The solar farm was commercially commissioned with a capacity of 44 MW in June 2023.