2001 Humber Refinery explosion
The 2001 Humber Refinery explosion was a major incident at the then Conoco-owned Humber Refinery at South Killingholme in North Lincolnshire, England. A large explosion occurred on the Saturate Gas Plant area of the site on Easter Monday, 16 April 2001 at approximately 2:20 p.m. There were no fatalities, but two people were injured.
Background
The Humber refinery occupies a 480 acre site on the south of the Humber. It is about 1.5 km from the town of Immingham and 0.5 km from the village South Kilingholme.The refinery was commissioned in 1969-70 and comprises a number of processing plants including crude distillation, catalytic reforming, a fluidized cracking unit, an alkylation unit, and a saturate gas plant.
At the time of the incident the refinery was owned and operated by Conoco Limited. On a normal weekday there were about 800 people on the site, at the time of the incident, on Easter Monday a public holiday, there were only about 185 people on the site.
The plant
The incident on 16 April 2001 occurred in the Saturate Gas Plant which separates hydrocarbons into various gas and liquid streams. The plant comprises a number of tall distillation columns, separators and condensers. The first column in the plant is the de-ethaniser which removes methane, ethane, and propane vapour from the liquid product. The vapour at the top of the column is at a pressure of 400 psig and a temperature of 119°F. The vapour flows through a 6-inch diameter overheads line to the condensers.After the SGP was commissioned salts and hydrates started to accumulate in the condensers. This began to cause fouling problems and blockages. This had been anticipated in the original design and a water injection point had been installed in a line upstream of the de-ethaniser. Water dissolved corrosive agents in the feed fluid. However, this arrangement was not sufficient to prevent fouling in the downstream condensers. In November 1981 a study recommended that an additional water injection point should be installed in the overheads line. This was done by using a 1” vent point in line P4363 as a water injection point. No Injection quill or other dispersion device was fitted. The injection point was 670 mm upstream of a 90° elbow.