Olympic Stadium (Montreal)


Olympic Stadium is a multi-purpose stadium in Montreal, Canada, located at Olympic Park in the Hochelaga-Maisonneuve district of the city. Built in the mid-1970s as the main venue for the 1976 Summer Olympics, it is nicknamed "The Big O", a reference to both its name and to the doughnut-shape of the permanent component of the stadium's roof. It is also disparagingly referred to as "The Big Owe" in reference to the high cost of its construction and of hosting the 1976 Olympics as a whole.
The stadium is one of the largest by seating capacity in Canada. After the Olympics, artificial turf was installed and it became the home of Montreal's professional baseball and football teams. The Montreal Alouettes of the CFL returned to their previous home of Molson Stadium in 1998 for regular season games, but continued to use Olympic Stadium for playoff and Grey Cup games until 2012. Following the 2004 baseball season, the Expos relocated to Washington, D.C., to become the Washington Nationals. The stadium currently serves as a multi-purpose facility for special events with a permanent seating capacity of 56,040. The capacity is expandable with temporary seating. CF Montréal of Major League Soccer has used the venue when demand for tickets justifies the large capacity or when the weather restricts outdoor play at nearby Saputo Stadium in the spring months.
The stadium has not had a main tenant since the Expos left in 2004. Despite decades of use, the stadium's history of numerous structural and financial problems has largely branded it as a white elephant.
Incorporated into the north base of the stadium, inclined at 45°, and not completed until a full decade after the stadium's opening, is the Montreal Tower. At it is the world's tallest inclined tower. The stadium and Olympic Park grounds border Maisonneuve Park, which includes the Montreal Botanical Garden, adjacent to the west across Sherbrooke Street.

History

Background and architecture

As early as 1963, Montreal Mayor Jean Drapeau sought to build a covered stadium in Montreal. A covered stadium was thought to be all but essential for Drapeau's other goal of bringing a Major League Baseball team to Montreal, given the cold weather that can affect the city in April, October and sometimes even September. In 1967, soon after the National League granted Montreal an expansion franchise for 1969, Drapeau wrote a letter promising that any prospective Montreal team would be playing in a covered stadium by 1971. However, even though Quebec mayors have broad executive power, Drapeau could not make such a guarantee on his own authority. Just as Charles Bronfman, who was slated to become the franchise's first owner, was ready to walk away, Drapeau had his staffers draw up a proposal for a stadium. It was enough to persuade Bronfman to continue with the effort.
The stadium was designed by French architect Roger Taillibert to be an elaborate facility featuring a retractable roof, which was to be opened and closed by cables suspended from a huge tower – the tallest inclined structure in the world, and the tenth tallest structure in Montreal. The design of the stadium has been likened to that of the Australian Pavilion at Expo '70 in Osaka, Japan, although Taillibert had previously explored the concept of an umbrella-style roof for a theatre in Cannes and Piscine Carnot in Paris. Soon after Montreal was awarded the 1976 Games, Drapeau struck a secret deal with Taillibert to build the stadium. It only came to light in 1972.
The Olympic swimming pool is located under this tower. An Olympic velodrome was situated at the base of the tower in a building similar in design to the swimming pool. The building was built as the main stadium for the 1976 Summer Olympic Games. The stadium was host to various events including the opening and closing ceremonies, athletics, football finals, and the team jumping equestrian events.
The building's design is cited as a masterpiece of Organic Modern architecture. Taillibert based the building on plant and animal forms, aiming to include vertebral structures with sinews or tentacles, while still following the basic plans of Modern architecture.

Construction

The stadium was originally slated to be finished in 1972, but the grand opening was cancelled due to a strike by construction workers. The Conseil des métiers de la construction union headed by André "Dédé" Desjardins kept the construction site in "anarchic disorder" until the Quebec Premier Robert Bourassa bought him off in a secret deal. In his 2000 book Notre Cher Stade Olympique, Taillibert wrote "If the Olympic Games took place, it was thanks to Dédé Desjardins. What irony!" Further delays ensued due to the stadium's unusual design and Taillibert's unwillingness to back down from his original vision of the stadium even in the face of escalating costs for raw materials. It did not help that the original project manager, Trudeau et Associés, seemed to be incapable of handling some of the most basic construction tasks. In 1974, the Quebec provincial government lost patience with the delays and cost overruns and fired Taillibert from the project.
Additionally, the project was plagued by circumstances beyond anyone's control. Work slowed to a snail's pace for a third of the year due to Montreal's typically brutal winters. As a result, the stadium and tower remained unfinished at the opening of the 1976 Olympic Games.
The roof materials languished in a warehouse in Marseille until 1982, and the tower and roof were not completed until 1987. It would be another year before the 66-tonne, Kevlar roof could retract. Even then, it could not be used in winds above. Ultimately, it was only opened and closed 88 times.

Observatory

When construction on the stadium's tower resumed after the 1976 Olympics, a multi-storey observatory was added to the plan, accessible via an inclined elevator, opened in 1987, that travels along the curved tower's spine. The elevator cabin ascends from base of the tower to the upper deck in less than two minutes at a rate of, with space for 76 persons per trip and a capacity of 500 persons per hour. The cabin is designed to remain level throughout its trip, while providing a panoramic view to its passengers.
The elevator faces north-east, offering a view to the north, south and east. It overlooks the Olympic Village, the Biodome, the Botanical Gardens and Saputo Stadium. The Olympic Park, the stadium's suspended roof and downtown Montreal can be viewed from the south-west-facing Observatory at the top of the tower.

Stadium financing

Despite initial projections in 1970 that the stadium would cost only C$134 million to construct, strikes and construction delays served to escalate these costs. By the time the stadium opened, the total costs had risen to C$1.1 billion.
The Quebec government introduced a special tobacco tax in May 1976 to help recoup its investment. By 2006, the amount contributed to the stadium's owner, the Olympic Installations Board , accounted for 8% of the tax revenue earned from cigarette sales. The 1976 special tobacco tax act stipulated that once the stadium was paid off, ownership of the facility would be returned to the City of Montreal.
In mid-November 2006, the stadium's costs were finally paid in full, more than 30 years after it opened.
The total expenditure amounted to C$1.61 billion, making it—at the time all costs were paid off—the second most expensive stadium built. Despite initial plans to complete payment in October 2006, an indoor smoking ban introduced in May 2006 curtailed the revenue gathered by the tobacco tax. By 2014, the stadium's expense ranking had fallen to fifth, with the construction of costlier venues like MetLife Stadium, AT&T Stadium, and the new Yankee Stadium. Perceived by many to be a white elephant, the stadium has also been dubbed The Big Owe due to its astronomical cost.
The stadium has generated on average $20 million in revenue each year since 1977. It is estimated that a large-scale event such as the Grey Cup can generate as much as $50 million in revenue.

Continuing problems

Although the tower and retractable roof were not completed in time for the 1976 Olympics, construction on the tower resumed in the 1980s. During this period, however, a large fire set the tower ablaze, causing damage and forcing a scheduled Expos home game to be postponed. In 1986, a large chunk of the tower fell onto the playing field prior to another Expos game August 29 vs. San Diego Padres forcing a doubleheader on August 30.
In January 1985, approval was given by the Quebec government to complete the project and install a retractable roof, financed by an Olympic cigarette tax in the province. The tower construction and installation of the orange-coloured Kevlar roof were completed by April 1987, a decade later than planned. The roof experienced numerous rips, allowing rain to leak into the stadium.
As part of various renovations made in 1991 to improve the stadium's suitability as a baseball venue, 12,000 seats were eliminated, most of them in distant portions of the outfield, and home plate was moved closer to the stands.
On September 8 of that year, support beams snapped and caused a concrete slab to fall onto an exterior walkway. No one was injured, but the Expos had to move their final 13 home games of that season to the opponents' cities. The Expos hinted that the 1992 season was at risk unless the stadium was certified safe. In early November, engineers found the stadium was structurally sound. However, it took longer to certify the roof as safe because it had been badly ripped in a June windstorm. For the 1992 season, it was decided to keep the roof closed at all times. The Kevlar roof was removed in May 1998, making the stadium open-air for the 1998 season. Later in 1998, a $26 million non-retractable opaque blue roof was installed.
In 1999, a portion of the roof collapsed on January 18, dumping ice and snow on workers that were setting up for the annual Montreal Auto Show. The auto show and a boat show the following month were cancelled, and the auto show left the venue for good. Repaired once again, the roof was modified to better withstand winter conditions: the OIB installed a network of pipes to circulate heated water under the roof to allow for snow melting. Despite these corrective measures, the stadium floor remained closed from December to March.
Birdair, the fabric provider and designer of the roof, was later sued for the roof failure. The installer of the roof, Danny's Construction, having suffered tremendous cost overruns along with its subcontractor Montacier, due to changes in the plans and specifications and delays, was terminated during the construction, and Birdair completed the project. Danny's Construction sued Birdair in 1999. In February 2010, after a lengthy trial, the Quebec Superior Court awarded a judgement in favour of Danny's Construction and dismissed Birdair's countersuit.
The stadium's condition suffered considerably in the early 21st century. During the Expos' final years in Montreal, it was coated with grime, and much of the concrete was chipped, stained, and soiled.