Snowy Mountains Scheme


The Snowy Mountains Scheme, also known as the Snowy Hydro or the Snowy scheme, is a hydroelectricity and irrigation complex in south-east Australia. Near the border of New South Wales and Victoria, the scheme consists of sixteen major dams; nine power stations; two pumping stations; and of tunnels, pipelines and aqueducts that were constructed between 1949 and 1974. The scheme was completed under the supervision of Chief Engineer, Sir William Hudson. It is the largest engineering project undertaken in Australia.
The water of the Snowy River and some of its tributaries, much of which formerly flowed southeast onto the river flats of East Gippsland, and into Bass Strait of the Tasman Sea, is captured at high elevations and diverted inland to the Murray and Murrumbidgee Rivers irrigation areas. The scheme includes two major tunnel systems constructed through the continental divide of the Snowy Mountains, known in Australia as the Great Dividing Range. The water falls and travels through large hydro-electric power stations which generate peak-load power for the Australian Capital Territory, New South Wales and Victoria. The Scheme also provides some security of water flows to the Murray-Darling basin, providing approximately of water a year to the basin for use in Australia's irrigated agriculture industry.
In 2016, the Snowy Mountains Scheme was added to the Australian National Heritage List.

History

Background

In the late 19th and early 20th centuries, the Murray and Murrumbidgee rivers were subject to development and control, to meet water supply and irrigation needs. By contrast, the Snowy River, that rose in the Australian Alps and flowed through mountainous and practically uninhabited country until debouching onto the river flats of East Gippsland, had never been controlled in any way, neither for the production of power nor for irrigation. A great proportion of its waters flowed eastwards into the South Pacific Ocean. The Snowy River had the highest headwater source of any in Australia and drew away a large proportion of the waters from the south-eastern New South Wales snowfields. It was foreseen that construction works in the Snowy Mountains could supplement the flow of the great inland rivers, provide a means for developing hydro-electric power, and increase agricultural production in the Murray and Murrumbidgee valleys.
Following World War II, the Government of New South Wales proposed that the flow of the Snowy River be diverted into the Murrumbidgee River for irrigation and agricultural purposes. There was little emphasis placed on the generation of power. A counter proposal by the Government of Victoria involved a greater generation of power, and involved diversion of the Snowy River to the Murray River. Additionally, the Government of South Australia was concerned that downstream flows on the Murray River would be severely jeopardised.
The Commonwealth Government, looking at the national implications of the two proposals, initiated a meeting to discuss the use of the waters of the Snowy River, and a committee was set up in 1946 to examine the question on the broadest possible basis. This committee, in a report submitted in November 1948, suggested consideration of a far greater scheme than any previously put forward. It involved not only the simple question of use of the waters of the Snowy River, but consideration of the possible diversion of a number of rivers in the area, tributaries, not only of the Snowy, but of the Murray and Murrumbidgee. The recommendations of the committee were generally agreed to by a conference of Ministers representing the Commonwealth, New South Wales, and Victoria, and it was also agreed that the committee should continue its investigations.
However, limitations in the Australian Constitution meant that the Commonwealth Government was limited in the powers it could exercise, without the agreement of the States. Subsequently, the Commonwealth Government introduced legislation into the Federal Parliament under its defence power; and enacted the that enabled the formation of the Snowy Mountains Hydroelectric Authority. Ten years later, the relevant states and territories introduced their own corresponding legislation and in January 1959 the Snowy Mountains Agreement was reached between the Commonwealth and the states.
The legislation created the Snowy Mountains Hydroelectric Authority that was given responsibility for the final evaluation, design and construction of the Snowy Mountains Scheme. The final agreed plan was to divert the waters of the Snowy Mountains region to provide increased electricity generating capacity and to provide irrigation water for the dry west. It was "greeted with enthusiasm by the people of Australia" and was seen to be "a milestone towards full national development".
The chief engineer, New Zealand-born William Hudson, was chosen to head the scheme as Chairman of the Snowy Mountains Hydroelectric Authority, and was instructed to seek workers from overseas. Hudson's employment of workers from 32 countries, many of whom had been at war with each other only a few years earlier, had a significant effect on the cultural mix of Australia.

Construction

Construction of the Snowy Scheme was managed by the Snowy Mountains Hydroelectric Authority. It officially began on 17 October 1949 and took 25 years, being officially completed in 1974.
An agreement between the United States Bureau of Reclamation and Snowy Mountains Hydro to provide technical assistance and training of engineers was agreed between the United States and Australia in Washington, D.C., on 16 November 1951. A loan for $100 million was obtained from the World Bank in 1962.
Tunneling records were set in the construction of the Scheme and it was completed on time and on budget in 1974, at a cost of 820 million; a dollar value equivalent in 1999 and 2004 to A$6 billion. Around two thirds of the workforce employed in the construction of the scheme were immigrant workers, originating from over thirty countries. The official death toll of workers on the Scheme stands at 121 people. Some of roads and tracks were constructed, seven townships and over 100 camps were built to enable construction of the 16 major dams, seven hydroelectric power stations, two pumping stations, of tunnel and of pipelines and aqueducts. Just 2% of the construction work is visible from above ground.
Two of the towns constructed for the scheme are now permanent; Cabramurra, the highest town in Australia; and Khancoban. Cooma flourished during construction of the Scheme and remains the headquarters of the operating company of the Scheme. Townships at Adaminaby, Jindabyne and Talbingo were inundated by the flooded waters from Lake Eucumbene, Lake Jindabyne and Jounama Reservoir. Improved vehicular access to the high country enabled ski-resort villages to be constructed at Thredbo and Guthega in the 1950s by former Snowy Scheme workers who realised the potential for expansion of the Australian ski industry.
The Scheme is in an area of, almost entirely within the Kosciuszko National Park. The design of the scheme was modelled on that of the Tennessee Valley Authority. Over 100,000 people from over 30 countries were employed during its construction, providing employment for many recently arrived immigrants, and was important in Australia's post-war economic and social development. Seventy percent of all the workers were migrants. During construction of the tunnels, a number of railways were employed to convey spoil from worksites and to deliver personnel, concrete and equipment throughout.
The project used Australia's first transistorised computer; one of the first in the world. Called 'Snowcom', the computer was used from 1960 to 1967.
At the completion of the project, the Australian Government maintained much of the diverse workforce and established the Snowy Mountains Engineering Corporation, which is now an international engineering consultancy company. The Scheme is the largest renewable energy generator in mainland Australia and plays an important role in the operation of the National Electricity Market, generating approximately 67% of all renewable energy in the mainland National Electricity Market. The Snowy Scheme's primary function is as a water manager, however under the corporatised model must deliver dollar dividends to the three shareholder governments - the NSW, Commonwealth and Victorian Governments.
The Scheme also has a significant role in providing security of water flows to the Murray-Darling Basin. The Scheme provides approximately of water a year to the Basin, providing additional water for an irrigated agriculture industry worth about A$3 bn per annum, representing more than 40% of the gross value of the nation's agricultural production.
The Snowy Mountains Hydro-electric Scheme, is one of the most complex integrated water and hydro-electric power schemes in the world and is listed as a "world-class civil engineering project" by the American Society of Civil Engineers. The scheme interlocks seven power stations and 16 major dams through of trans-mountain tunnels and of aqueducts. The history of the Snowy Scheme reveals its important role in building post World War II Australia.
Sir William Hudson was appointed the first commissioner of the Snowy Mountains Hydroelectric Authority, serving between 1949 and 1967. The Commissioner's role was the overall management of the Scheme. He represented the Scheme at the highest levels of government, welcomed international scientists and engineers, encouraged scientific and engineering research, as well as attending many social and civic activities. Sir William's management style 'stressed cooperation between management and labour and scientific knowledge over opinion'.
The Scheme was completed with the official opening of the Tumut 3 Power Station project by the Governor-General of Australia, Sir Paul Hasluck on 21 October 1972.