APR-1400
The APR-1400 is an advanced pressurized water nuclear reactor designed by the Korea Electric Power Corporation. Originally known as the Korean Next Generation Reactor, this Generation III reactor was developed from the earlier OPR-1000 design and also incorporates features from the US Combustion Engineering System 80+ design. Currently in South Korea there are 4 units in operation, and 2 units in construction. Four units are completed and in commercial operation in the United Arab Emirates at Barakah.
History
APR-1400 design began in 1992 and was awarded certification by the Korean Institute of Nuclear Safety in May 2002. The design certification application was submitted to the US Nuclear Regulatory Commission in December 2014 and in March 2015, it was accepted for technical review to determine if the reactor design meets basic US safety requirements.In October 2017, European Utility Requirements organization approved changes to the APR-1400 design for emergency cooling, allowing the design to be built in countries outside Europe to EUR certification.
As of September 2018, the NRC issued its final safety evaluation report and standard design approval finding the design technically acceptable and valid for 15 years. In April 2019, the NRC approved a rule to certify the APR-1400 standard design.
In September 2018, the U.S. Nuclear Regulatory Commission gave the APR-1400 Standard Design Approval, and in September 2019 it received a design certificate valid for 15 years.
In 2022, Westinghouse Electric Company, which had acquired Combustion Engineering in 2000, filed a lawsuit in a U.S. federal court against KHNP and Kepco alleging that the APR-1400 was copied from the System 80 reactor. This had the indirect effect that the U.S. government rejected a request for necessary APR-1400 permission to export to a third country while the case is resolved.
Locations
South Korea
The first commercial APR-1400 reactors at Shin Kori were approved in September 2007, with construction starting in October 2008 and August 2009. Shin Kori-3 was initially scheduled to commence operation by the end of 2013, but the schedules for both Units 3 & 4 were delayed by approximately one year to replace safety-related control cabling, which had failed some tests. Construction of two more APR-1400 units at Shin Kori, Korea had been expected to begin in 2014, but as of December 2016 plans had not been finalised.Construction of two new APR-1400s, Shin Hanul Units 1 & 2, began in May 2012 and June 2013, with Unit 1 expected to be completed in April 2017. Two more APR-1400s at Shin Hanul were approved in 2014, with construction to start in 2017.
After the election of President Moon Jae-in in May 2017, Korea Hydro & Nuclear Power suspended design work on Shin Hanul-3 and -4, and construction work was suspended on Shin Kori-5 and -6 in July 2017 for a three-month period while a government-appointed committee met to discuss the country's future nuclear power policy. President Moon had signed an agreement in March 2017 calling for the phase-out of nuclear energy while campaigning for president. In October 2017, the committee recommended proceeding with the construction of Shin Kori-5 and -6. President Moon announced he supported the committee's decision, but added that no new construction would be allowed, throwing doubt on the fate of Shin Hanul-3 and -4.
As of April 2020, Shin-Kori 1 and 2 and Shin-Hanul 1 are operational while Shin-Hanul 2 being loaded with fuel.
United Arab Emirates
In December 2009, a KEPCO-led consortium was awarded the contract to build four APR-1400 reactors at Barakah, United Arab Emirates. Construction of Barakah Unit 1 started in July 2012, Unit 2 started construction in May 2013, Unit 3 started construction in September 2014 and Unit 4 started construction in September 2015. Block 1 started to produce energy on 1 August 2020 and went into commercial operation on 6 April 2021. several research projects were performed at Khalifa University to ensure the safe operation for the APR1400 nuclear power plant. On 5 September 2024, the fourth and final reactor started commercial production.United Kingdom
was formed as the joint venture between Engie, Iberdrola, and Scottish and Southern Energy to develop the Moorside Nuclear Power Station in Cumbria; the initial plans called for three Westinghouse AP1000 units. SSE was bought out by Engie and Iberdrola in 2011, and Iberdrola's share, in turn, was purchased by Toshiba in 2013. Following the bankruptcy of Toshiba's subsidiary Westinghouse Electric Corporation in March 2017, Engie pulled out of NuGen in July, leaving Toshiba as the sole owner of NuGen. In December 2017, NuGen announced that KEPCO was named the preferred bidder to acquire NuGen from Toshiba; the three AP1000 reactors were to be replaced by two APR-1400 units. In July 2018 Kepco's preferred bidder status was terminated, in response to difficulties financing the development.Poland
In October 2022, Polish utilities PGE and ZE PAK announced an agreement with KHNP to build a number of APR-1400 reactors near ZE PAK's coal-fired plant at Pątnów.Czech Republic
In 2024 KHNP was selected to supply 2 of APR-1400 reactors. The expected date for the unit for test operation is 2036 and commercial operation in 2038. In May 2025 French EDF appealed the decision to award the contract to KHNP, the court ordered temporarily to stop the contract.On June 4th 2025 the contract with KHNP for 2 units of APR-1400 was signed after the court has lifted injunction. Local Czech companies will take 60% of construction work. The price of electricity will be under 90 euros per megawatt hour.
The total cost of 2 APR-1400 units is projected to be $18.6 billion. Construction is expected to start in 2029.
Summary
;NotesDesign
The APR-1400 is an evolutionary Advanced Light Water Reactor which is based on the previous OPR-1000 design. Under Korean conditions, the reactor produced 1455 MW gross electrical power with a thermal power capacity of 3983 MW.The design was developed to meet 43 design requirements, with the main developments being evolution in capacity, increased lifetime and enhanced safety. The design improvements also focus on meeting economic objectives and licensing requirements. Compared to the OPR-1000, the key features are:
- Net Electric power: 1400 MW
- Design Life: 60 years
- Seismic Design Basis: 0.3g
- Core Damage Frequency: less than 10−5/yr
- Core fuel assemblies: 241