Winnipeg Rapid Transit
Winnipeg Rapid Transit is a bus rapid transit system of Winnipeg Transit in Winnipeg, Manitoba, Canada, currently consisting of the BLUE line. The system's only route runs on both dedicated transitway and arterial road in Southern Winnipeg. Future expansions are in the planning stages, consisting of an Eastern Corridor connecting downtown to Transcona and a West-North Corridor connecting St. James with Downtown and West Kildonan.
History
The timeline of accomplishing some form of rapid transit in the Winnipeg area goes back to the late 1950s, when the Greater Winnipeg Transit Commission hired an urban planner from Toronto to design a subway for Winnipeg.The Future Development of the Greater Winnipeg Transit System recommended 3 semi-circular lines intersecting at various points in the metro area. Combined, these three rapid transit lines would have cost $449 million.
During the 1960s when the Greater Winnipeg Development Plan was being written, the Metropolitan Corporation of Greater Winnipeg studied a future transit system for the region. In their report, Winnipeg Area Transportation Study: Projections & Recommendations , a 5.4-mile underground subway system between Polo Park Shopping Centre and Henderson and Hespeler Avenue in Elmwood was recommended. The WATS study did computerized modelling for a bus only transit system, but found it woefully inadequate for a metro population of 781,000 in 1991.
The transit system visualized in this scheme would involve the introduction of 36 different transit routes totalling 622 route miles and requiring a fleet of 1,090 buses. Such an operation would ensure that, on the average, in the peak hours, buses in the metropolitan area would be spaced at 3.38 minute intervals along their routes. This compares with 6.43 minutes under the system in operation in 1962.In 1972, Mayor of Winnipeg Steve Juba advocated for a suspended monorail operating along Portage Avenue and later St. Vital. Juba said that it would be cheaper to construct than a subway. Cost estimates were $22 million for the completed project, or $1 million per mile. At the time, the only monorail operating in North America was the Seattle monorail. While Juba was away, City Council held a vote on the monorail, which was lost.
After the amalgamation of Winnipeg with its suburbs in 1972 and the creation of Winnipeg Transit, the newly-created transit department completely changed its view on rapid transit, opting for Bus Rapid Transit instead, and changing where it should initially go to between downtown Winnipeg and the Fort Garry campus of the University of Manitoba. Deleuuw Dillon was hired to create a plan for bus rapid transit, now the Southwest Transit Corridor. However, politicians balked at the cost of any form of rapid transit—rail or bus, due to the very high initial construction costs. Dillon Consulting remains involved in planning for Southwest BRT.
In 2002, Mayor Glen Murray pushed for BRT as the mode choice for the Southwest Transit Corridor using guided bus technology like that in the Essen, Germany. He made a deal with Premier Gary Doer that would see the construction of the Kenaston Underpass, the construction of the Manitoba Hydro headquarters downtown, and the construction of Phase I of the Corridor. All projects except the BRT were funded and constructed. Murray quit his job as Mayor to run for a seat in the 2004 Federal election, which he lost.
The next Mayor, Sam Katz, promised to cancel a $43-million federal grant for the Southwest Transit Corridor and use that for improving recreation centres. At the same day of the 29 September 2004 vote on rapid transit, 25-year veteran Transit Director Rick Borland quit the position and retired over the issue when one of Katz's advisors, Bryan Gray, criticized a report by Winnipeg Transit used to request funding for the busway.
In November 2004, Katz visited Ottawa and rode the O-Train. Katz commented "And it's new, it's innovative -- it's the 21st century. There's no reason in my mind that we shouldn't explore this."
Instead, Katz formed an ad hoc group, chaired by Councillor Wyatt, in the same ward that New Flyer has its manufacturing plant, to complete a study on the viability of LRT for Winnipeg, though Katz could not accomplish an LRT for Winnipeg. The Rapid Transit Task Force report was released in 2005.
Columnist Tom Brodbeck wrote in a September 2004 Winnipeg Sun article that there had been no cost-benefit analysis of the BRT project.
As a compromise, Katz allowed Phase I of BRT that "could be converted to LRT at a later date." Papers were signed in September 2008, with construction beginning during the Summer of 2009.
On April 8, 2012, Phase 1 of the Southwest Transitway opened.
On April 12, 2020, Phase 2 of the Southwest Transitway opened.
Southwest Transitway
The Southwest Transitway is a dedicated bus rapid transit roadway in Winnipeg, Manitoba, Canada, which commenced operation in April 2012.The first section was built parallel to the railway tracks running southwest from Queen Elizabeth Way at The Forks to Pembina Highway at Jubilee Avenue. An extension from Jubilee Avenue to Markham Road and the University of Manitoba was then built, which opened on April 12, 2020. Bus rapid transit services through the downtown Winnipeg area use the Graham Avenue Transit Mall and other bus priority routes.
Phase 1
Phase 1 of the Southwest Transitway commenced operation on 8 April 2012. The first section runs parallel to the railway tracks in a southwest direction from Queen Elizabeth Way to Pembina Highway at Jubilee Avenue. Bus rapid transit services through the downtown Winnipeg area used the Graham Avenue Transit Mall and other bus priority routes.Jubilee Station was the last one to be constructed and was completed on June 21, 2015. City Council was set to vote on approval of the station's construction in late 2012. It had a construction budget of C$3.9 million, with costs shared between the City and developer Gem Equities. Due to cost overruns, Jubilee Station's actual cost was C$8.8 million after construction. The City owed more than C$1.3 million back to Gem to equalize the shared costs.
Funding was approved for the planned extension of the transitway south from the Jubilee interchange to Bison Drive and the University of Manitoba. A funding announcement was made in February 2015, construction began in late 2016, project completion in Fall of 2019. Driver testing commenced in the Fall of 2019, with plans to begin service on 8 April 2020.
Winnipeg Transit tried to mitigate pigeon droppings at Osborne Station, but in 2018 it was still a problem at that location. Winnipeg Transit sought advice from Orkin Canada who recommended using OvoControl P in nearby bird feeders to control the pigeon population.
Phase 2
Phase 2 of the Southwest Transitway commenced operation on 12 April 2020. Phase 2 of the project saw the Southwest Transitway extended from the Jubilee Overpass, through the Parker Lands and the Manitoba Hydro right of way before joining the CN Lettelier line north of Abinojii Mikanah. The Transitway then goes through Waverley Heights to Markham Road, where BLUE buses continue to the University of Manitoba or to St. Norbert.In March 2019, Winnipeg Transit introduced a new route structure, which begun at the opening of Phase 2. Previously, the Southwest Transitway operated as an "Open Busway" design. The new "Spine & Feeder" routing is similar in functionality to rail-transit lines. Switching to "Spine & Feeder" meant that Winnipeg Transit has significantly changed its ideology since 1973, when it began promoting BRT, as the "Open Busway" ensured a "one-seat ride" and
Parker Station was put on hold, pending legal settlements. It will be part of a future single-family and multi-family neighbourhood, Fulton Grove, situated within the Parker lands planning area. The station will be located between the existing Jubilee and Beaumont stations.
Financing Phase 2's estimated $590-million cost will be split three ways: $225m provincially, $140m federally, and $225m municipally. Of the City's share, $19.7-million will have to be budgeted annually for the project, starting in 2020. In order to raise the revenue to pay the costs, one or a combination of "cash-to-capital funding, a property tax increase, a transit fare increase" would be needed, according to the Dillon report of 2014.
Stations
Routes
The following table lists all routes that travel on part or all of the Southwest Transitway, excluding routes which only enter the Transitway at a station to faciliate transfers:| Route Number & Name | Termini | Stops on the Southwest Transitway | Notes |
| BLUE | Unicity Hub, University of Manitoba / St. Norbert | All stops | The main route on the Southwest Transitway, travelling on its entire length. |
| FX3 Regent - Grant | Redonda Loop, Sturgeon at Silver | Osborne, Harkness | Enters/exists the Southwest Transitway via Warsaw Avenue just south of Osborne Station. |
| F5 McPhillips - Donald | Garden City Hub, Fort Rouge Station | Fort Rouge | Enters/exists the Southwest Transitway via Warsaw Avenue just south of Osborne Station. |
| 557 Island Lakes - Morley | Sage Creek, Windermere Loop | Jubilee, Fort Rouge | Enters/exists the Southwest Transitway via Jubilee Overpass just south of Jubilee Station, and at Fort Rouge Station onto Morley Avenue. Weekday service only. |
| 649 Chevrier | Fort Whyte, Seel Station | Beaumont, Seel | Enters/exists the Southwest Transitway via Jubilee Overpass just south of Jubilee Station. |
| 690 Industrial | West Fort Garry Industrial, Seel Station | Clarence, Seel | Enters/exists the Southwest Transitway via Clarence Avenue just south of Clarence Station. Weekday peak direction service only. |
| 691 Whyte Ridge | Whyte Ridge, Seel Station | Chevrier, Clarence, Seel | Enters/exists the Southwest Transitway via Chevrier Avenue just south of Chevrier Station. Weekday peak direction service only. |