Perth Stadium


Perth Stadium, also known as Optus Stadium under sponsorship agreement, is a multi-purpose stadium in the Burswood suburb of Perth, Western Australia. It was completed during late 2017 and officially opened on 21 January 2018. The stadium's total capacity is 61,266, including standing room, extendable to 65,000 seats for rectangular sports. It is the third-largest stadium in Australia.
Perth Stadium is primarily used for Australian rules football and cricket. Perth's two Australian Football League teams – the Fremantle Football Club and the West Coast Eagles – relocated their home games from Subiaco Oval to Perth Stadium, while the Perth Scorchers play their Big Bash League home games at the venue, having previously played at the WACA Ground.
Perth Stadium was built by a consortium led by Multiplex. The announcement of the Burswood location in June 2011 followed a series of earlier proposals for the stadium, including locations in Subiaco and East Perth.

History

Early proposals

In 2003, the Government of Western Australia led by Alan Carpenter approved Terms of Reference for a review to examine the future of major sporting venues in Western Australia with Terms of Reference approved in December 2003. Having spent 2004 working with Football and Cricket bodies to try and advance the project the Government decided, in 2005, to appoint a taskforce. It was chaired by John Langoulant, Chief Executive of the Chamber of Commerce and Industry of Western Australia, and included private sector experts in finance, planning and architecture working with Department of Sport and Recreation infrastructure experts and the Department's Chief Executive Officer, Ron Alexander. The taskforce released its final report in May 2007. The report recommended the construction of a new 60,000-seat stadium at either Kitchener Park or in East Perth, which would be suitable for Australian rules football, cricket and also rectangular-field sports such as soccer, rugby union and rugby league. The taskforce recommended against the further development of Subiaco Oval, which would be demolished. It also recommended against building the new stadium at the site of Burswood, stating that "The development costs at the Burswood site would be significantly higher due to local site conditions and the need for significant upgrades to transport infrastructure."
In July 2007, the Government of Western Australia announced its preference to build a new 60,000-seat stadium rather than re-develop Subiaco Oval, and in early 2008 it confirmed that Subiaco Oval would be demolished for the new Perth super-stadium to be built next door at Kitchener Park. This site was chosen ahead of the other suggested site at the old East Perth Power Station, which was set aside to house a new $500 million museum.
The new stadium at Subiaco was scheduled to be built between 2011 and 2016, with the majority of the stadium to be completed in 2014. Subiaco Oval was to be demolished between 2014 and 2016 to allow the end of construction on Perth Stadium. The staged construction would have allowed for Australian rules football to be played at the new venue by 2014, when the stadium was two-thirds completed with an initial capacity of 40,000 seats. The final stage would be completed in 2016 and expand the stadium's capacity to 60,000.
Stadium plans suggested its playing surface would have been oval in shape to accommodate Australian rules football and cricket games. The stadium was also expected to have retractable seating which would have reconfigured the venue to make it suitable for rectangular-field sports codes, such as soccer, rugby union and rugby league. These retractable seats were to number 22,000, and were to be situated along the touch lines and behind the posts in the rectangular configuration. With an overall planned capacity of 60,000, Perth Stadium would have been Western Australia's largest sports venue, and it was designed to be built such that the capacity could be increased to 70,000 if needed in the future.
The stadium was expected to be primarily used for Australian rules football with the ability to host cricket, rugby union, rugby league and soccer matches. It was planned that it would be the home ground for the West Coast Eagles and Fremantle Dockers, the two Western Australian teams in the Australian Football League. It was also planned to host rugby union Test matches, soccer and rock concerts. In reality AFL matches have been joined by the AFLW games and WAFL grand finals.
The cost for the Kitchener Park stadium was expected to reach $1.1 billion, including $800 million on construction of the stadium itself and $300 million on associated infrastructure, property acquisition, escalation, transport infrastructure and other costs. Construction of the new stadium would have involved moving 27 private residences and moving residents from another 66 state housing properties surrounding Subiaco Oval. These state housing tenants would have been relocated within the Subiaco area. The project was going to be funded by the Government of Western Australia.
Following the election of a new State Government under Colin Barnett, the new stadium's plans were scrapped in early February 2009. Barnett stated that a new stadium would not be considered for at least two years. As a result of Australia's failed bid for the 2022 World Cup, $250 million in potential federal government funding for a new stadium was also withdrawn in December 2010.

Burswood location

In June 2011, the State Government announced that the new stadium would be built in Burswood on the northern section of the Burswood Park golf course. The government stated that the Burswood site was preferred because it was unconstrained by surrounding developments and had the additional benefit of being government-owned. It would also allow for a special events six-platform Perth Stadium railway station to be built and could be connected to the central business district via a pedestrian bridge across the Swan River to East Perth. A car park was not built to service the stadium, with visitors expected to either park in the city and walk across the bridge or use public transport.
The Government stated that planning for the new stadium at Burswood was due to be completed by mid-2012, with construction commencing in 2014 and scheduled for completion in 2018. It announced Multiplex as the contract holders for the construction of the stadium and appointed the firm Populous as the project's architectural consultants.

Construction

Cost

Following the Barnett Government's announcement to move the site of the proposed stadium to Burswood, it stated that the stadium would cost around $700 million, with an extra $300 million allocated to public transport works. However, in December 2011 Premier Colin Barnett stated that it was too early to say what the final cost would be, explaining that "No one can put a price on it until it's designed, until it goes out to tender".
The previous Government's Major Stadia Taskforce had earlier put the total cost of the Burswood stadium option, including transport needs, at $1.147 billion. This higher cost, comparative to the sites at Subiaco or East Perth, was mainly "due to the need to provide substantial transport infrastructure as well as the additional costs associated with site conditions." In June 2011 the West Australian newspaper reported that due to an increase in construction costs since the release of the task force report in 2007, the total cost will be close to $1.5 billion, assuming work begins within two years.
The Australian Football League agreed to help pay for Perth's new stadium at Burswood, although it was not revealed how much money it would contribute. However, the nearby Crown Perth, which is expected to benefit commercially from the presence of the stadium, was not asked by the Barnett Government to help meet the construction costs.
In October 2017 it was reported that the final cost of the completed stadium was $1.6 billion. This equated to an average cost per Western Australian household of $1500, and per person of $600. In February 2018 a State Government inquiry into Western Australia's finances under the former Barnett government found that the full cost of the stadium including transport infrastructure will be $1.8 billion, around $200 million more than previous estimates.

Impacts

The site is located on the Burswood Peninsula, previously known as the Swan Portland Cement Site. The Swan Portland Cement Company Ltd operated at the site from 1927 and James Hardie Industries operated at the adjacent site from the 1920s up until 1981. In its report and recommendations, Remediation and Redevelopment of the Swan Portland Cement Site, Burswood, the Environmental Protection Authority, states "The current site is contaminated with asbestos waste from the James Hardie operations and cement kiln dust, kiln bricks and associated contaminated soil and hydrocarbons from the Swan Portland cement operations." In its report it estimates cement kiln dust on the site, the effects of which should be managed, with regard to its effects upon public health, groundwater and surface water. Three zones of asbestos contamination on the site were identified in the report; zone 1 having of broken and loose asbestos, zone 2 having of asbestos contamination up to below ground level and zone 3 being of asbestos contamination within of cement kiln dust.
The EPA report states that while undisturbed in the soil, the contamination poses no threat to public health but disturbing the site will result in airborne asbestos fibres and contamination from the soil. The EPA recommended a management plan for any disturbance of asbestos contamination to be conducted by the Town of Victoria Park.
In November 2012, Victoria Park residents contacted the Health Department to notify them asbestos and other material had been unearthed by work on the southern parking lot of the Casino complex. Alarmed residents feared asbestos exposure to locals, park users and Casino patrons. Although the Health Department advised that no risk had been identified, stock piles were sprayed with hydromulch, windbreaks were put on fencing, contaminant levels were being monitored and paths and loose soil were sealed. The Premier's office advised that the Department of Building Management and Works were undertaking the project. The Health Department assured residents there was "no risk to the general public".
The construction of the stadium affected Aboriginal communities. Although the State Solicitor's Office advises that native title has been extinguished over the site, it has heritage significance for the local indigenous people, the Whadjuk Noongar, being a burial site. Despite the Department of Indigenous Affairs advising the existence of the registered Aboriginal Heritage site affecting the Burswood Peninsula and East Perth foreshore, the site was deregistered by the Barnett Liberal State Government. Following the Supreme Court decision Robinson v Fielding WASC 108 to reinstate DAA 22874 after it had been deregistered by the Barnett government, the Burswood Island Burial site was reassessed in October 2016 but remains "Not a Site" under the Aboriginal Heritage Act. Previously the site was recognised by the Department of Aboriginal Affairs under the Aboriginal Heritage Act 1972 as DAA site 15914: Burswood Island Burial. "Several culturally significant sites around WA have had their protection withdrawn in the past year on the basis they no longer fit the definition of a sacred site. Guidelines issued by the Department of Aboriginal Affairs stated that to be a recognised as sacred site, a place needs to have been devoted to religious use rather than simply mythological stories, songs or beliefs."