Marinus Link
Marinus Link is a proposed 750 megawatt capacity high voltage direct current electricity interconnector, to strengthen the connection between the Australian states of Tasmania and Victoria, on Australia's National Electricity Market. Due to inflation, Marinus link was scaled back from an initial plan of 1500 MW via two cables, down to 750 MW via one cable with negotiations to continue on a second cable.
It involves approximately 250 km of subsea cables and approximately 90 km of underground land cables. Marinus Link will also incorporate significant optical fibre capacity for system control, with the remaining capacity available to strengthen telecommunications and data connectivity between the regions. Marinus Link will be supported by approximately 220 km of high voltage alternating current of proposed transmission developments in North West Tasmania, known as the North West Transmission Developments. Collectively, Marinus Link and the North West Transmission Developments are known as Project Marinus. In October 2022, authorities pledged loans for the project, as well as supporting facilities such as pumped hydro in Tasmania.
Stage 1 of the project is expected to commence construction in 2026 with completion in 2030. On the 1st of August 2025, Marinus Link announced Stage 1 will proceed after final investment decision was made by shareholders. The project received federal environmental approval on the 3rd of August.
Role of TasNetworks
owns, operates and maintains the electricity transmission and distribution network in Tasmania, delivering electricity supply to more than 295,000 residential, commercial and industrial customers, and also provides telecommunications and technology services. TasNetworks is wholly owned by the State of Tasmania and operates as a commercial business with assets of $3.5 billion. As the jurisdictional planner for the state of Tasmania, TasNetworks is progressing Marinus Link and supporting transmission developments. TasNetworks has established the subsidiary business Marinus Link Pty Ltd to progress Marinus Link.Background
The first Bass Strait interconnector, Basslink, was constructed between 2003 and 2005, with a capacity rating of 630 MW. Basslink experienced a fault in December 2015, rendering it out of service for six months. The impact of this outage was further compounded by low water levels in Tasmania's hydroelectric power system. After the eventual restoration of service, the capacity rating of Basslink was reduced to 500 MW.In response to the resulting energy supply challenges, the Australian and Tasmanian governments commissioned a study into the feasibility of a second interconnector in April 2016. The study, often referred to as 'the Tamblyn Report', was conducted by Dr John Tamblyn, and was released in April 2017. The study built on a preliminary report released by governments in June 2016, and recommended that the Tasmanian Government develop a detailed business case for a second Tasmanian interconnector.
Project timeline
Initial Feasibility Report and Business Case Assessment Phase
The Tasmanian Government, with support from the Australian Renewable Energy Agency on behalf of the Australian Government, directed TasNetworks to undertake a feasibility study and business case assessment for a second Bass Strait interconnector, which commenced in 2017, building on the 'Tamblyn Report'. The Feasibility and Business Case Assessment phase of Project Marinus concluded with the release of the ' and the ' in December 2019. The Initial Feasibility Report showed that Marinus Link and the supporting transmission is technically and economically feasible. The Business Case for Marinus Link is positive and demonstrated that work should continue into the ‘Design and Approvals’ phase, to deliver a ‘shovel ready’ Marinus Link project in time to meet the needs of a National Electricity Market, which is undergoing a rapid and significant transition to a low emissions future.Design and Approvals Phase
The project is currently in the Design and Approvals phase, which includes:- developing plans outlining how the existing transmission networks and potential new transmission routes will be developed, to increase network capacity and ensure the power system in Tasmania can accommodate future energy developments in the region
- undertaking economic and regulatory analysis of the project
- engaging with landowners and communities to gather feedback which helps to further refine or confirm sections of the proposed transmission routes, through in-person meetings, community information sessions, briefings and webinars
- conducting a range of field investigations, including ecology, cultural heritage and geotechnical surveys
- preparation and completion of planning and approval applications
The Design and Approvals phase is timed to proceed in accordance with timeframes envisaged in the Australian Energy Market Operator's 2020 Integrated System Plan.
Manufacturing, Construction and Commissioning
The original proposal was for a 1500 MW capacity Marinus Link, planned to be built in two 750 MW stages, commissioned two to three years apart, with the first 750 MW stage in service as early as 2027. The second 750 MW of Marinus Link was to be in service as early as 2030.In September 2023, the project was limited to 750 MW as costs increased to $3bn for that size. Ownership was 49% federal government, 33.3% Victoria and 17.7% Tasmania.
In May 2024, Marinus Link released an update regarding the timing of Stage 2 of the project with the second stage expected to be 2033 subject to market demand.
Following Final Investment Decision in 2025, Prysmian confirmed they had received a notice to proceed.
Economic Analysis
The economics and regulation for Project Marinus is assessed under the Regulatory Investment Test for Transmission. The RIT-T is a regulatory mechanism defined in the National Electricity Rules that applies an economic cost benefit test on new electricity infrastructure proposed for the National Electricity Market.According to the Australian Energy Regulator : “The purpose of the RIT-T is to identify the credible option that maximises the present value of net economic benefit to all those who produce, consume and transport electricity rules.” The role of the RIT-T is to undertake a cost benefit analysis focusing on different technical solutions by looking in detail at engineering aspects, refining costs, considering alternate options, and staging.
Regulatory Investment Test for Transmission (RIT-T)
The RIT-T assesses the economic and technical impact of, and preferred timing for, all major network investments in the national energy market. The RIT-T process ensures regulated transmission investment decisions are in the long term interests of customers. The RIT-T process involves multiple stages, and culminated with the Project Assessment Conclusions Report, published in June 2021, which shows that Project Marinus satisfies the RIT-T.All RIT-T reports and associated documentation have been .