Drax Power Station


Drax power station is a large biomass power station in Drax, North Yorkshire, England. It has a 2.6 GW capacity for biomass and had a 1.29 GW capacity for coal that was retired in 2021. Its name comes from the nearby village of Drax. It is situated on the River Ouse between Selby and Goole. Its generating capacity of 3,906 megawatts, which includes the shut down coal units, is the highest of any power station in the United Kingdom, providing about 6% of the United Kingdom's electricity supply.
Opened in 1974 and extended in the 1980s, the station was initially operated by the Central Electricity Generating Board. Since privatisation in 1990 ownership has changed several times, and it is operated by the Drax Group. Completed in 1986, it was the newest coal-fired power station in England until it closed in 2021. Flue gas desulphurisation equipment was fitted between 1988 and 1995. The high and low pressure turbines were replaced between 2007 and 2012.
By 2010, the station was co-firing biomass. In 2012, the company announced plans to convert three generating units to solely biomass, burning 7.5 million tonnes imported from the United States and Canada. This work was completed in 2016 and a fourth unit was converted in 2018. The company planned to convert its remaining two coal units to Combined Cycle Gas Turbine units and 200 MW battery storage. However, those two coal units were shut in 2021 without converting them to biomass.
In 2025, the UK government extended its operation to 2031, but at a reduced load factor so it would run less than half as often from 2027 using 100% biomass.

History

Drax was initially conceived by the Central Electricity Generating Board in 1962 as the country's largest power station thus far, at about 3,000 MW. Subsequently, it was decided to use this opportunity as their first station to use the 660 MW turbogenerator sets which were planned to become the new standard, so the planning consents were revised to about 4,000 MW.
Following the Selby Coalfield discovery in 1967 the Board would build three large power stations to use its coal. These were an expansion of the station at Ferrybridge, a new station at Eggborough, and Drax, which would be the largest.

Construction

Authority to carry out preparatory works was granted in December 1964, leading to full permission in March 1966, on the basis that the station would be designed to accommodate six 660 MW units, but that only the first three be proceeded with for the time being.
Ground work for these three units, known at the time as 'Drax First Half', started in 1967. Two units were synchronised to the grid in 1973, and the third in 1974.
Although authorised, the second half of the project – known as 'Drax Completion' – was deferred, because during the project's gestation the Board's energy mix policy shifted to working towards a majority nuclear system. The board decided in 1977 that construction of the final three units would commence in 1979 with the target of commissioning in 1985/6, as part of meeting load growth with an adjusted mix policy aiming for a balance of coal, nuclear, and oil. However, later that year in July, the Government requested that Drax Completion proceed immediately, ahead of requirements, in order to secure jobs in the North East's heavy manufacturing industries. The Board agreed to this subject to being compensated.
The architects were Jeff King and Dennis Merritt of Clifford, Tee and Gale. The architectural critic Reyner Banham was scathing of the design: 'less a brick cathedral than a concrete bunker... obsession with ribbed surfaces and forceful projections that have their origins in brutalism'. Costain constructed the foundations and cable tunnels; Sir Robert McAlpine Ltd. laid the roads and built the ancillary buildings; Mowlem laid the deep foundations; Alfred McAlpine built the administration and control buildings; Balfour Beatty undertook general building works; and James Scott installed cabling.
Tarmac Construction undertook the civil engineering works; Holst Civil Engineers built the chimney; Bierrum & Partners built the cooling towers; N.G. Bailey installed cabling; Reyrolle, English Electric and South Wales Switchgear produced and installed the switchgear; English Electric manufactured the generator cooling water pumps; T.W. Broadbent maintained the temporary electrical supplies; and Sulzer Brothers manufactured the boiler feed pumps. In both phases the boilers were made by Babcock Power Ltd and the generators by C. A. Parsons and Company.
The second phase was completed in 1986.
Construction of the power station entailed the demolition of a farm known as Wood House.
Mitsui Babcock fitted flue-gas desulphurisation equipment between 1988 and 1995.

Post-privatisation

On privatisation of the CEGB in 1990, the station was transferred from the CEGB to the privatised generating company National Power, which sold it to the AES Corporation in November 1999 for £1.87 billion. AES relinquished ownership in August 2003, after falling into £1.3 billion of debt. Independent directors continued the operation to ensure security of supply. In December 2005, after refinancing, ownership passed to the Drax Group.
Separate acquisition offers from International Power, private equity group Texas Pacific, and a private equity backed bid from Constellation Energy were rejected for undervaluing the company. The company's valuation subsequently increased to 2005 as a result of rising electricity prices, and on 15 December 2005 Drax Group plc floated its shares on the London Stock Exchange, issuing £400 million worth of shares, on a valuation of £2.6 billion.
In 2009, Drax Group submitted a planning application for the 300 MW biomass Ouse Renewable Energy Plant next to the power station. Government approval was obtained in mid 2011. In February 2012 the company ceased planning development of the plant, citing logistics costs, and uncertainty concerning government financial support for biomass.

Carbon capture and storage

In 2006 Drax Power Limited, in response to a government consultation, stated they were sponsoring development studies into carbon capture and storage, but noted that it was not then commercially viable, with costs comparable with nuclear or offshore wind power. On 17 June 2009, Secretary of State for Energy and Climate Change Ed Miliband announced plans that would require all UK coal-fired power stations to be fitted with CCS technology by the early 2020s or face closure.
In 2012 a CCS project at Drax was shortlisted for government funding. In 2013 the White Rose Carbon Capture and Storage project was shortlisted for the UK government's CCS scheme and in late 2013 was awarded a two-year FEED contract for the CCS project. As of June 2014, Drax is engaged in a joint venture with Alstom and BOC to build a 626 MW oxygen-fuelled combustion power station adjacent to the existing Drax site. National Grid would simultaneously construct a pipeline to transport to the Yorkshire coast for sequestration.
In July 2014 the project was awarded €300 million funding from the European Commission.
In September 2015 Drax announced it would not be making any further investments into the CCS scheme after completion of the feasibility study because negative changes to government support for renewable energy had made the project too financially risky, plus drops in the company's share price due to the same uncertainty had reduced Drax's ability to raise funds. Front End Engineering Design was expected to continue under Alstom and BOC with the project still being hosted at Drax. In late 2015 the UK Government withdrew its potential financial support for CCS projects – up to £1 billion of funding, reversing support promised in the governing party's 2015 election manifesto. As a result, Leigh Hackett, CEO of Capture Power stated that "t is difficult to imagine its continuation in the absence of crucial government support".
In May 2018, Drax announced a new carbon capture and storage pilot scheme that it would undertake in conjunction with the Leeds-based firm, C-Capture. The focus of this pilot will be on capturing carbon post combustion from the biomass burners as opposed to the coal burners. Drax will invest £400,000 into the project. The company, C-Capture, is a side company of the Department of Chemistry established at the University of Leeds. This would yield about of stored per day from the process, which could be sold on for use in the drinks industry. The pilot scheme was launched in February 2019. The capture of carbon from biomas burners is known as Bio Energy with Carbon Capture and Storage.

Design and specification

The main buildings are of steel frame and metal clad construction. The main features are a turbine hall, a boiler house, a chimney and 12 cooling towers. The boiler house is high, and the turbine hall is long.
The chimney stands tall, with an overall diameter of, and weighs 44,000 tonnes. It consists of three elliptical flues of reinforced concrete, each serving two of the six boilers, set within a cylindrical 'wind shield', also of reinforced concrete. The topmost elements, the three cap rings of the flues which extend above the wind shield, are of cast iron. When finished, the chimney was the largest industrial chimney in the world, and is still the tallest in the United Kingdom. The chimney's dimensions, including the height, were dictated by a design total capacity of 5,100 m3/s of gases at 26 m/s. As the station was designed and constructed prior to the CEGB's commitment to Flue Gas Desulphurisation, extensive measures were made to limit acid attack from 'sulphurous condensate', namely the lining of the flues with a fluoroelastomer, and coating of the upper of the external surfaces with a mix of acid-resisting tiles and said fluoroelastomer.
The twelve tall natural draft cooling towers stand in two groups of six to the north and south of the station. They are made of reinforced concrete, in the typical hyperboloid design, and each have a base diameter of.
The station was the third-largest coal-fired power station in Europe, after Bełchatów Power Station in Poland, and Neurath Power Station in Germany. It produces around 24 terawatt hours of electricity annually. Although it generates around 1,500,000 tonnes of ash and 22,800,000 tonnes of carbon dioxide each year, it is the most carbon-efficient coal-fired power plant in the United Kingdom.
The design life was set out in terms of number of start-ups and operating "cycles", but with the presumption that the station would operate as a standard 2nd-tier baseload generator in the pattern well established under the centralised state-owned electricity system, it was summarised as "in the order of 40 years". The minimum requirement was for providing 'full load for weekdays, over a spell of 3 months' with an availability over 85%. Weekend operations were expected to be between 50–100% of full power. Despite this intent for baseload operation, it was designed with a reasonable ability for load-following, being able to ramp up or down by 5% of full power per minute within the range of 50–100% of full power.