Number One Electronic Switching System


The Number One Electronic Switching System was the first large-scale stored program control telephone exchange or electronic switching system in the Bell System. It was manufactured by Western Electric and first placed into service in Succasunna, New Jersey, in May 1965. The switching fabric was composed of a reed relay matrix controlled by wire spring relays which in turn were controlled by a central processing unit.
The 1AESS central office switch was a plug compatible, higher capacity upgrade from 1ESS with a faster 1A processor that incorporated the existing instruction set for programming compatibility, and used smaller remreed switches, fewer relays, and featured disk storage. It was in service from 1976 to 2017.

Switching fabric

The voice switching fabric plan was similar to that of the earlier 5XB switch in being bidirectional and in using the call-back principle. The largest full-access matrix switches in the system, however, were 8x8 rather than 10x10 or 20x16. Thus they required eight stages rather than four to achieve large enough junctor groups in a large office. Crosspoints being more expensive in the new system but switches cheaper, system cost was minimized with fewer crosspoints organized into more switches. The fabric was divided into Line Networks and Trunk Networks of four stages, and partially folded to allow connecting line-to-line or trunk-to-trunk without exceeding eight stages of switching.
The traditional implementation of a nonblocking minimal spanning switch able to connect input customers to output customers simultaneously—with the connections initiated in any order—the connection matrix scaled on. This being impractical, statistical theory is used to design hardware that can connect most of the calls, and block others when traffic exceeds the design capacity. These blocking switches are the most common in modern telephone exchanges. They are generally implemented as smaller switch fabrics in cascade. In many, a randomizer is used to select the start of a path through the multistage fabric so that the statistical properties predicted by the theory can be gained. In addition, if the control system is able to rearrange the routing of existing connections on the arrival of a new connection, a full non-blocking matrix requires fewer switch points.

Line and trunk networks

Each four stage Line Network or Trunk Network was divided into Junctor Switch Frames and either Line Switch Frames in the case of a Line Network, or Trunk Switch Frames in the case of a Trunk Network. Links were designated A, B, C, and J for Junctor. A Links were internal to the LSF or TSF; B Links connected LSF or TSF to JSF, C were internal to JSF, and J links or Junctors connected to another net in the exchange.
All JSFs had a unity concentration ratio, that is the number of B links within the network equalled the number of junctors to other networks. Most LSFs had a 4:1 Line Concentration Ratio ; that is the lines were four times as numerous as the B links. In some urban areas 2:1 LSF were used. The B links were often to make a higher LCR, such as 3:1 or 5:1. Line Networks always had 1024 Junctors, arranged in 16 grids that each switched 64 junctors to 64 B links. Four grids were grouped for control purposes in each of four LJFs.
TSF had a unity concentration, but a TN could have more TSFs than JSFs. Thus their B links were usually to make a Trunk Concentration Ratio of 1.25:1 or 1.5:1, the latter being especially common in 1A offices. TSFs and JSFs were identical except for their position in the fabric and the presence of a ninth test access level or no-test level in the JSF. Each JSF or TSF was divided into 4 two-stage grids.
Early TNs had four JSF, for a total of 16 grids, 1024 J links and the same number of B links, with four B links from each Trunk Junctor grid to each Trunk Switch grid. Starting in the mid-1970s, larger offices had their B links wired differently, with only two B links from each Trunk Junctor Grid to each Trunk Switch Grid. This allowed a larger TN, with 8 JSF containing 32 grids, connecting 2048 junctors and 2048 B links. Thus the junctor groups could be larger and more efficient. These TN had eight TSF, giving the TN a unity trunk concentration ratio.
Within each LN or TN, the A, B, C and J links were counted from the outer termination to the inner. That is, for a trunk, the trunk Stage 0 switch could connect each trunk to any of eight A links, which in turn were wired to Stage 1 switches to connect them to B links. Trunk Junctor grids also had Stage 0 and Stage 1 switches, the former to connect B links to C links, and the latter to connect C to J links also called Junctors. Junctors were gathered into cables, 16 twisted pairs per cable constituting a Junctor Subgroup, running to the Junctor Grouping Frame where they were plugged into cables to other networks. Each network had 64 or 128 subgroups, and was connected to each other network by one or several subgroups.
The original 1ESS Ferreed switching fabric was packaged as separate 8x8 switches or other sizes, tied into the rest of the speech fabric and control circuitry by wire wrap connections. The transmit/receive path of the analog voice signal is through a series of magnetic-latching reed switches.
The much smaller Remreed crosspoints, introduced at about the same time as 1AESS, were packaged as grid boxes of four principal types. Type 10A Junctor Grids and 11A Trunk Grids were a box about 16x16x5 inches with sixteen 8x8 switches inside. Type 12A Line Grids with 2:1 LCR were only about 5 inches wide, with eight 4x4 Stage 0 line switches with ferrods and cutoff contacts for 32 lines, connected internally to four 4x8 Stage 1 switches connecting to B-links. Type 14A Line Grids with 4:1 LCR were about 16x12x5 inches with 64 lines, 32 A-links and 16 B-links. The boxes were connected to the rest of the fabric and control circuitry by slide-in connectors. Thus the worker had to handle a much bigger, heavier piece of equipment, but did not have to unwrap and rewrap dozens of wires.

Fabric error

The two controllers in each Junctor Frame had no-test access to their Junctors via their F-switch, a ninth level in the Stage 1 switches which could be opened or closed independently of the crosspoints in the grid. When setting up each call through the fabric, but before connecting the fabric to the line and/or trunk, the controller could connect a test scan point to the talk wires in order to detect potentials. Current flowing through the scan point would be reported to the maintenance software, resulting in a "False Cross and Ground" teleprinter message listing the path. Then the maintenance software would tell the call completion software to try again with a different junctor.
With a clean FCG test, the call completion software told the "A" relay in the trunk circuit to operate, connecting its transmission and test hardware to the switching fabric and thus to the line. Then, for an outgoing call, the trunk's scan point would scan for the presence of an off hook line. If the short was not detected, the software would command the printing of a "Supervision Failure" and try again with a different junctor. A similar supervision check was performed when an incoming call was answered. Any of these tests could alert for the presence of a bad crosspoint.
Staff could study a mass of printouts to find which links and crosspoints were causing calls to fail on first tries. In the late 1970s, teleprinter channels were gathered together in Switching Control Centers, later Switching Control Center System, each serving a dozen or more 1ESS exchanges and using their own computers to analyze these and other kinds of failure reports. They generated a so-called histogram of parts of the fabric where failures were particularly numerous, usually pointing to a particular bad crosspoint, even if it failed sporadically rather than consistently. Local workers could then busy out the appropriate switch or grid and replace it.
When a test access crosspoint itself was stuck closed, it would cause sporadic FCG failures all over both grids that were tested by that controller. Since the J links were externally connected, switchroom staff discovered that such failures could be found by making busy both grids, grounding the controller's test leads, and then testing all 128 J links, 256 wires, for a ground.
Given the restrictions of 1960s hardware, unavoidable failure occurred. Though detected, the system was designed to connect the calling party to the wrong person rather than a disconnect, intercept, etc.

Scan and distribute

The computer received input from peripherals via magnetic scanners, composed of ferrod sensors, similar in principle to magnetic core memory except that the output was controlled by control windings analogous to the windings of a relay. Specifically, the ferrod was a transformer with four windings. Two small windings ran through holes in the center of a rod of ferrite. A pulse on the Interrogate winding was induced into the Readout winding, if the ferrite was not magnetically saturated. The larger control windings, if current was flowing through them, saturated the magnetic material, hence decoupling the Interrogate winding from the Readout winding which would return a Zero signal. The Interrogate windings of 16 ferrods of a row were wired in series to a driver, and the Readout windings of 64 ferrods of a column were wired to a sense amp. Check circuits ensured that an Interrogate current was indeed flowing.
Scanners were Line Scanners, Universal Trunk Scanners, Junctor Scanners and Master Scanners. The first three only scanned for supervision, while Master Scanners did all other scan jobs. For example, a DTMF Receiver, mounted in a Miscellaneous Trunk frame, had eight demand scan points, one for each frequency, and two supervisory scan points, one to signal the presence of a valid DTMF combination so the software knew when to look at the frequency scan points, and the other to supervise the loop. The supervisory scan point also detected Dial Pulses, with software counting the pulses as they arrived. Each digit when it became valid was stored in a software hopper to be given to the Originating Register.
Ferrods were mounted in pairs, usually with different control windings, so one could supervise a switchward side of a trunk and the other the distant office. Components inside the trunk pack, including diodes, determined for example, whether it performed reverse battery signaling as an incoming trunk, or detected reverse battery from a distant trunk; i.e. was an outgoing trunk.
Line ferrods were also provided in pairs, of which the even numbered one had contacts brought out to the front of the package in lugs suitable for wire wrap so the windings could be strapped for loop start or ground start signaling. The original 1ESS packaging had all the ferrods of an LSF together, and separate from the line switches, while the later 1AESS had each ferrod at the front of the steel box containing its line switch. Odd numbered line equipment could not be made ground start, their ferrods being inaccessible.
The computer controlled the magnetic latching relays by Signal Distributors packaged in the Universal Trunk frames, Junctor frames, or in Miscellaneous Trunk frames, according to which they were numbered as USD, JSD or MSD. SD were originally contact trees of 30-contact wire spring relays, each driven by a flipflop. Each magnetic latching relay had one transfer contact dedicated to sending a pulse back to the SD, on each operate and release. The pulser in the SD detected this pulse to determine that the action had occurred, or else alerted the maintenance software to print a FSCAN report. In later 1AESS versions SD were solid state with several SD points per circuit pack generally on the same shelf or adjacent shelf to the trunk pack.
A few peripherals that needed quicker response time, such as Dial Pulse Transmitters, were controlled via Central Pulse Distributors, which otherwise were mainly used for enabling a peripheral circuit controller to accept orders from the Peripheral Unit Address Bus.